Asia Resorts Ltd. v. Usha Breco Ltd.

Case / Petition Number:
Civil Appeal No. 7391 of 2001
Neutral Citation:[2001] SUPP. 4 S.C.R.

Case Synopsis & Summary

Asia Resorts Ltd. (ARL) contracted with Usha Breco Ltd. (UBL) to construct a passenger ropeway system for a Himachal Pradesh resort. After completion, ARL alleged that the ropeway did not function properly and failed to meet the contracted capacity, claiming substantial financial loss. ARL served a notice on 17.4.1990 demanding rectification and later claimed referral to arbitration. UBL replied on 17.5.1990. On 24.3.1993 ARL wrote about continued discussions, and on 6.4.1993 UBL complained that minutes of negotiations were not properly recorded. ARL then issued a notice on 16.6.1993 threatening arbitration, and filed a petition under Section 20 of the Arbitration Act, 1940 on 30.11.1993. UBL contended the petition was time-barred. The Single Judge of the Delhi High Court held the petition within time, relying on alleged ongoing mutual consultations and a 6.4.1993 acknowledgment under the Limitation Act. The Division Bench reversed, holding the petition barred by limitation for lack of effective mutual consultation up to 1993. The principal issues were whether Article 137 of the Limitation Act, 1963 applies to petitions under Section 20, and whether arbitration clauses require bona fide mutual consultations to suspend limitation, and whether delay can be condoned under Section 5. The Supreme Court held that the cause of action arose on 17 May 1990 and Article 137 applies, but condoned the delay on payment of costs and remitted the matter to the High Court.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • D. P. Mohapatra
  • K. G. Balakrishnan
Judgment Date
2001-10-30
Court Decision / Holding
Delay in filing under Section 20 of the Arbitration Act, 1940 is condoned on the condition of payment of Rs. 20,000 to the respondent within one month; deposit with the Registrar General is required and, upon such deposit, the appeal is allowed and remitted to the High Court to proceed under the Arbitration Act; failure to deposit Rs. 20,000 within the period results in dismissal. I.A. Nos. 1–4 are allowed; the appeal is disposed of accordingly.
Final Disposition
Appeal disposed of.

Parties to the Case

Appellants / Petitioners

  • Asia Resorts Ltd.

Respondents

  • Usha Breco Ltd.

Legal Representation & Advocates

Counsels for Petitioners

  • • R.F. Nariman
  • • Arvind Kumar
  • • Manish Sharma
  • • Sujata Kurdukar

Counsels for Respondents

  • • Dr. A.M. Singhvi
  • • Jaideep Gupta
  • • Suman Jyoti Khaitan

Provisions of Law Cited

Arbitration Act, 1940 – Section 20Limitation Act, 1963 – Section 5Limitation Act, 1963 – Section 18Limitation Act, 1963 – Article 137Arbitration Act, 1940 (general principles)

Legal Doctrines & Maxims

  • Mutual consultation as a precondition under the arbitration clause; bona fide attempts to resolve differences before arbitration
  • Delay should not be wilful to be condoned under Section 5; consequences of non-wilful delay
  • Ackonwledgement under Section 18 of the Limitation Act can toll limitation
  • Cause of action arises when a difference to which the agreement applies arises; the relevant arbitration clause governs timing of filing
  • Article 137 as residuary provision applying to petitions under any Act to civil courts, not limited to CPC-based actions

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant argued that the arbitration clause envisaged a bona fide attempt to settle disputes by mutual consultations, continuing after the 17.4.1990 notice, with the agreement terminated only on 16.6.1993, thus giving rise to a later cause of action. They contended that the 17.4.1990 notice did not show intent to initiate arbitration, but to seek resolution. They relied on letters in 1993 to argue that mutual consultations persisted and that acknowledgments under Section 18 did not occur; hence, conditions under Article 137 should apply to extend the period. They urged that delay should be condoned under Section 5 given the ongoing negotiations and the nature of disputes.

Contentions of Respondents

The respondent contended that a definite reply was issued on 17.5.1990, establishing a clear cause of action well within time, and that there was no sustained mutual consultation to 1993. They argued the arbitration clause required a formal process, and that the Division Bench was correct to hold the petition barred by limitation; the 24.3.1993 and 6.4.1993 letters did not amount to effective mutual consultations or a valid acknowledgment under Section 18.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
Kerala State Electricity Board v. TP KunhaliummaAIR 1997 SC 282PositiveCited to affirm Article 137 applies to petitions under any Act in civil courts, not limited to CPC-based applications.
Major (Retd.) Inder Singh Rekhi v. Delhi Development Authority[1998] 2 SCC 338PositiveSupports applying Article 137 to determine the period for Section 20 petitions.
Union of India v. M/s Vijay Construction Co.AIR 1981 Delhi 193PositiveCited for the Section 5 delay-condonation principle applicable to Section 20 petitions.
Steel Authority of India Ltd. v. J.C. Budharaja, Government and Mining Contractor(1999) 8 SCC 122PositivePart of the jurisprudence that Article 137 governs limitation for filings under Section 20.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,406 words•~21 min read

In The Court Record

Asia Resorts Ltd. v. Usha Breco Ltd.

A '- E ## ASIA RESORTS LTD. _v._ ## USHA BRECO LTD. ## OCTOBER 30, 2001 ## B ## [D.P. MOHAPATRA AND K.G. BALAKRISHNAN, JJ.] _Arbitration Act 1940/Limitation Act, 1963-Seciion 20/SectiOns 5 and 18 and Article 137._ c D _Reference o.f_ arbitration~Limitation _period-Contract between partiesDifference arose on 17.4.1990-Notice-De.finite reply given on 17.5.1990Notice intimating initiation o.f arbitration proceedings given in 1993-No indicatiun in notices that mutual consultatiQn for resolution of differences continued upto 1993-Arbitration applicationfiled-:Held, the application was time barred since cause o.f action had arisen on 17.5.1990-Yet the delay could be condoned if it was not wilfitl._ _Applicability of Article 137-Petition filed u/s. 20 o.f Arbitration ActHeld, applicable-Article 137 is applicable on any petition or application filed under any Act to a Civil Court, including special laws, for which no period o.f limitation is provided elsewhere._ _Words and Phrases: 'applicant' and 'application'-Meaning of in the context of Limitation Act, 1963._ . / App~llant entered into contract with respondent to complete the F work of ropeway system. After completion of work, since the system did not function properly and was for lesser capacity than agreed for, appel· lant sent notice on 17.4.1990 to respondent which was replied by the respondent on 17.5.1990. On 24.3.1993 appellant had sent letter to re· spondent to which respondent replied on 6.4.1993 making complaint therein G that the minutes of the discussion held on certain dates were not properly recorded. Thereafter appellant sent another notice dated 16.6.1993 inti· mating the respondent of initiation of arbitration proceedings. On 30.11.1993 appellant filed petition under Section 20 of Arbitration Act, 1940. Respondent objected that the petition was barred by limita· H tion. Single Judge of the High Court held the petition to be within limita564 ASIA RESORTS LTD. _v._ USHA BRECO LTD. 565 ## - tion period since the parties had made correspondence regarding the disputes till 1993 and that the letter dated 6.4.1993 by the respondent would amount to acknowledgement under Section 18 of the Limitation Act. In appeal Division Bench held that the petition was barred by limitation and there was no acknowledgement on the part of the respondent to extend the period of limitation. In appeal to this court appellant contended that the petition was not barred by limitation since in view of the arbitration clause contained in the agreement the petition should be filed only after making a _bona fide_ attempt to resolve the differences by mutual consultations and since the mutual consultations continued even after 17.4.1990 and the agreement between the parties was terminated on 16.6.1993, cause of action arose thereafter. It was also contended that the notice dated 17.4.1990 was not sent with intention to initiate arbitration proceedings. Respondent contended that the petition was barred by limitation as definite reply was given on 17.5.1990 to the notice dated 17.4.1990. Disposing of the appeal, the Court HELD : 1.1. Under Section 20 of the Arbitration Act, 1940 the cause of action for filing an application may arise whenever "a difference has arisen to which the agreement applies". Regard must be had to the relevant arbitration clause in the agreement. _H_ any specific terms are used in the arbitration clause, that would govern the parties as to when a petition for reference of arbitration shall be filed in Court. [572-F] 1.2. In the present case, cause of action for filing the application had arisen, the moment the appellant received the reply notice denying the claims made by the appellant. Thereafter, the Division Bench has rightly held that the application was barred by time. Though from the arbitration clause it is clear that parties should have made an effort to settle the · differences by mutual consultations and only on failure of such attempt steps could have been taken by the parties for making a reference to the arbitrator, but the notices issued between the parties hardly give any indication that these mutual consultations for resolution of differences continued upto 1993. A perusal of the notice sent by the appellant on 17.4.1990 to the respondent and the reply received from the latter would A B C D E F G H 566 > SUPREME COURT REPORTS (2001] SUPP. 4 S.C.R. \ A show that the cause of action had arisen for filing of a petition under Section 20 of the Arbitration Act, 1940 as early as on 17.5.1990. The contention of the appellant that the notice sent by the a'ppellant was not as a prelude to filing of a petition under Section 20 of the Arbitration Act but only to initiate criminal action, is belied by the absence of such a warning B in that notice. The tenor of the notice dated 17.4.1990 is that the appellant wanted the respondent to give a final reply in the matter and to settle all claims of the appellant. [572-H; 571-A] B C > 1.3. In the absence of any other material, it is difficult to discern whether the correspondence dated 24.3.1993 and .6.4.1993 would amount to any effective mutual consuitations between the parties. The Division Bench has rightly held that these letters hardly make any acknowledg· ment under Section 18 of the Limitation Act. [571-G] D E F 1.4. Residuary Article 137 of the Limitation Act, 1963 applies so far as the period of limitation is concerned for an application under Section 20 of the Arbitration Act. By insertion of Article 137, it casts a wider net so as to include any application for which no period of limitation was provided elsewhere in that division. The third _division of the Limitation Act, 1963 deals with various applications to be filed under various special statutes. The definitions of 'applicant' and 'application' are also inserted in the Limitation Act. Therefore, it is clear that the intention of the legislature was to provide a residuary article prescribing period of limitation for filing petitions and applications under the various special laws. Article 137 would apply to any petition or application filed under any Act to a civil court and it cannot be confined to applications contemplated by or under the Code of Civil Procedure. [571-H; 572-A-C] G H 2. Going by the provision contained in Section 20 of the Arbitration Act in an appropriate case the court can extend the benefit of the said Section. Having regard to the nature of disputes between the parties, the delay caused in filing the application by the appellant was not wilful and hence is liable to be condoned. However, in the facts and circumstances of the case, the delay shall be liable to be condoned only upon payment of costs. Accordingly, the delay in filing the application under Section 20 of the Arbitration Act, 1940 is condoned on condition that the appellant pays a sum of Rs. 20,000 to the respondent within a period of one month. , [573-H; 574-A] .- '' ASIA RESORTS LTD. _v._ USHA BRECO LTD. [BALAKRISHNAN, J.] 567 _Union of India_ v. _Mis. Vijay Construction Co.,_ AIR (1981) Delhi 193, A approved. _CNIL_ APPELLATE JURISDICTION : Civil Appeal No. 7391 of 2001. > From the Judgment and Order dated 9.11.98 of the Himachal Pradesh High Court in O.S.A. No. 14 of 1997. R.F. Nariman, Arvind Kumar, Manish Sharma and Ms. Sujata Kurdukar for the Appellant. Dr. A.M. Singhvi, Jaideep Gupta and Suman Jyoti Khaitan for the Respondent. The Judgment of the Court was delivered by BALAKRISHNAN, J. Leave granted. D The appellant constructed a hotel resort by name "Timber Trail Heights" at Bansaar in Himachal Pradesh. This place is at a high altitude of 5000 feet from sea level and in order to ensure a quick access for the visiting tourists to this resort, the appellant wanted to have a passenger ropeway system and for that purpose, the appellant entered into a contract with the respondent, by name, Usha Breco Limited. The respondent completed the work relating to ropeway system and handed over the same to the appellant on 27.4.1988. Initially, the ropeway system was being operated and maintained by the employees of the respondent, but later on the appellant absorbed those workers as its own employees. According to the appellant, right from the beginning, the ropeway system was not functioning well and it did not meet the specification required by the appellant. The appellant had been making a request to the respondent to rectify the defects but the latter failed to rectify the same. The appellant also alleged that the respondent did not cooperate with the appellant for getting clearance from the Himachal Pradesh Ropeway Inspector. The Inspector did not approve the ropeway system for the installed capacity. The appellant alleged that the works undertaken by the respondent were <;lefined in the annexure to the agreement and as per the agreement, the ropeway system must have a capacity for carrying on 150 passengers per hour and it was further stipulated that within 8 hours of operation per day, the total capacity of passengers must be 1200 per day and according to the appeliant, based on E F G H [2001] SUPP. 4 S.<;:.R. SUPREME COURT REPORTS 568 A B such representation, assurance and agreement, the appellant invested huge amount for the ropeway system. The appellant later realized that only 800 passengers would be able to reach the destination through the ropeway system per day and this, according to the appellant, caused heavy financial loss. The appellant issued a notice to the respondent but the latter did not accede to their request. Ultimately, on 16.6.1993, the appellant issued a notice to the respondent intimating that it would be constrained to file a petition under Section 20 of the Arbitration Act, 1940 (for.short "the Act"). Clause 15 of the agreement provided for arbitration and the appellant filed a petition under Section 20 of ·the Act on 30.11.1993. c D The respondent filed a reply contending that the petition filed by the appellant was barred by limitation. The respondent contended that the appellant had issued notice on 17.4.1990 through its advocate intimating the respondent that they would take legal action against them. It was contended by the respondent that the petition filed under Section 20 of the Act on 30.11.1993 was more than 3 years after the issuance of notice. The respondent alleged that the subsequent notice on 16.6.1993 was issued beyond the period of 3 years from the earlier notice. The respondent also contended that there was no subsisting agreement between the parties and all matters relating to the contract were concluded and the minutes also were recorded on 12.4.1988. E F The learned Single Judge before whom the application under Section 20 was filed rejected the contention urged by the respondent herein and held that the petition under Section 20 was filed in time. The learned Single Jildge was of the view that parties had made correspondence regarding the disputes till 1993 and therefore, the petition under Section 20 of the Act was within limitation. The learned Single Judge also observed that a letter written on 6.4.1993 by the respondent to the appellant would amount to acknowledgement under Section 18 of the Limitation Act and on that basis also, the petition for arbitration was held to have been filed within time. G G This order was challenged before the Division Bench. After an elaborate consideration of the whole matter, the Division Bench came to the conclusion that the petition filed by the appellant under Section 20 of the Act was barred by limitation and there was no acknowledgement on the part of the respondent to extend the period of limitation. This judgment of the Division Bench is H challenged before us. ASIA RESORTS LTD. _v._ USHA BRECO LTD. [BALAKRISHNAN, J.] 569 We heard Mr. R.F. Nariman, learned senior Counsel for the appellant and Dr. A.M. Singhvi, learned senior Counsel for the respondent. The Counsel for the appellant submitted that the appellant gave notice on 17.4.1990 to the respondent informing them of the difficulties encountered by the ropeway system and making a.request to rectify the same. The disputes and differences between the parties arose after 17.4.1990. Thereafter, there was mutual consultation, which lasted up to 1993 until it ultimately failed and then alone the cause of action arose for filing petition under Section 20 of the Act. It was also argued that the notice sent on 17.4.1990 was not sent with the intention of initiating arbitration proceedings, rather the appellant wanted to intimate that they would initiate criminal action against the respondent. The Counsel for the respondent, on the other hand, contended that the appellant issued notice on 17.4.1990 for which a definite reply was given on 17.5.1990 and, therefore, the cause of action, if any, had arisen and the petition filed after a period of 3 years from that date was barred by limitation. > The counsel for the appellant argued that in view of the arbitration clause contained in the agreement, the petition under section 20 of the Act could be filed only after making a _bona fide_ attempt to resolve the differences by mutual consultations and according to the appellant, these mutual consultations continued even after the notice dated 17.4.1990 and by the notice sent on 16.6.1993 the agreement between the parties was terminated and the cause of action arose for filing of a petition under Section 20 of the Act. A B c D E The arbitration clause contained in the agreement is as follows : "If at any time any question, dispute and difference whatsoever shall arise between ARL and UBL in relation to or in connection with this Agreement, both parties agree to resolve such differences by mutual consultation failing which either party may give to the other notice in writing of the existence of such question, dispute or difference and the same shall be referred for the final determination of a single arbitrator, if agreed upon or to two arbitrators one to be appointed by ARL and another by UBL; or in case of disagreement betwc:<en the said two arbitrators to the final arbitration of an Umpire to be appointed by the said two arbitrators and that the award of the sole arbitrator or the said \ 570 [2001] SUPP. 4 S.C.R. SUPREME COURT REPORTS A c D E F Umpire as the case may be shall be final and binding on both the parties and the said arbitration proceedings shall be governed by the provisions of the Indian Arbitration Act, 1940 and the rules thereunder, to be read together with all statutory amendments or modifications of the said Act." B G H It is true that from the above .arbitration clause it is clear that parties shoQld have made an effort to settle the differences by mutual consultations and only on failure of such attempt steps could ha~ been taken by the parties for making a reference to the arbitrator, but the notices issued between the parties hardly give any indication that these mutual consultations for resolution of differences conti~ued upto 1993. A perusal of the notice sent by the appellant on 17.4.1990 to the respondent and the reply received from the latter would show that the cause of action had arisen for filing of a petition under section 20 of the Act as early as on 17.5 .1990. The material portion of the notice sent by the· appellant has been extracted in the impugned judgment. Suffice it to say that in the notice dated 17.4.1990, it is made out in unmistakable terms that the appellant was of the view that the respondent had committed a serious breach of the agreement ~d therefore the respondent was called upon to do the needful within 30 days from the date of that notice, failing which the appellant would take legal action against the respondent in court of law. In the notice, it was stated that the performance of the passenger ropeway was not to the satisfaction of the appellant and the respondent had supplied the equipment which was capable of working up to sixty per cent capacity and that the respondent had charged hundred per cent money. It was also stated that the appellant had spent Rs.70 lakhs and due to the delay in delivery of the equipment, the appellant had suffered liquidated damage to the tune of Rs.3.50 lakhs. The appellant further stated that the project costing Rs.206 lakhs should have been completed in the month of March, 1987, but it was not ready even in April, 1988 and on that account the appellant had suffered damage to the extent of Rs.37 lakhs at the construction stage. In the notice, it was mentioned that the respondent committed the · offence of cheating punishable under section 420 IPC as there was dishonest intention on the part of the respondent · from the very inception of the contract and that the respondent committed extortion by putting the appellant in fear of not completing the project. It is, however, pertinent to note that the appellant did not specifically state in the notice that it would initiate criminal prosecution against the respondent. The contention of the appellant's counsel that the notice sent by the appellant was ASIA RESORTS LTD. _v._ USHA BRECO LTD. [BALAKRISHNAN, J.] 571 not as a prelude to filing of a petition under section 20 of the Arbitration Act but only to initiate criminal action, is belied by the absence of such a warning in that notice. The tenor of the notice dated 17 .4.1990 is that the appellant wanted the respondent to give a final reply in the matter and to settle all claims of the appellant. A B The respondent sent a detailed reply to the notice sent by the appellant wherein all the allegations were denied. The respondent denied the claim made by the appellant in its entirety and it was stated that the appellant issued the notice with a view to delay the payment of about Rs.6 lakhs which was due to the respondent. The appellant was told in clear terms that the respondent was not prepared to accede to the claim made by the appellant. c The crucial question is whether any mutual consultation between the parties to resolve the differences as envisaged under the arbitration clause had taken place even after the reply sent by the respondent on 17.5.1990. The appellant would contend that there was further correspondence between the parties during this interregnum. To substantiate this contention, the appellant relies on the letter written by the appellant on 24.3.1993 to Usha Martin Industries Ltd. and also a letter written by the respondent to the appellant on 6.4.1993. In the letter dated 24.3.1993, it is stated that "We are looking forward for the implementation of your decision to increase the capacity of our passenger ropeway system and we assure you that we will release the payment in your favour as agreed immediately." This Jetter was, in fact, not sent to the respondent, but probably to a sister concern of tjle respondent. We would assume that it was sent to the respondent as we see a reply by the respondent on 6.4.1993 on record. In the letter dated 6.4.1993, the respondent makes a complaint that the minutes of the discussion held on 19th and 20th March, 1993 with the Executive Director of M/s Usha Martin Industries Ltd. were not properly recorded. D E F In the absence of any other material, it is difficult to discern whether this correspondence would amount to any effective mutual consultations between the parties. The Division Bench has rightly held that these letters hardly make' any acknowledgement under Section 18 of the Limitation Act. G There is not much controversy that the residuary Article 137 of the Limitation Act applies so far as the period of limitation is concerned for an 572 SUPREME COURT REPORTS [2001] SUPP. 4 S.C.R. A B c D E application under Section 20 of the Arbitration Act, 1940. The residuary Article 181 of the Limitation Act, 1908 was replaced by Article 137 in the Limitation Act, 1963. Earlier, Article 18i was applicable only in respect of application to be filed under the Civil Procedure Code. This Article was replaced by Article 137 in the Limitation Act, 1963 in a modified form. By insertion of Article 137, it casts a wider net so as to include any application for which no period of limitation was provided elsewhere in that division. The third division of the Limitation Act, 1963 deals with various applications to be filed under various special statutes. The definitions of 'applicant' and 'application' are also inserted in the Limitation Act, 1963. Therefore, it is clear that the intention of the legislature was to provide a residuary article prescribing period of limitation for filing petitions and applications under the various special laws. This Court in _Kera/a St(l.te Electricity Board_ v. _T.P. Kunhaliumma,_ AIR (1997) SC 282 held that Article 137 would apply to any petition or application filed under any Act to a civil court and it cannot be confined to· applications contemplated by or under the Code of Civil Procedure. In _Major (Retd.) Inder Singh Rekhi_ v. _Delhi Development Authority,_ [1998] 2 SCC 338; _Union of India and Am:_ v. _Mis. L.K. Ahuja and Co.,_ [1988] 3 SCC 76; _Steel Authority of India Ltd._ v. _J.C. Budharaja, Government and Mining Contractor,_ [1999] 8 SCC 122 and _Union of India and Am:_ v. _Mis. Vijay Construction Co.,_ AIR (1981) Delhi 193, this Court held that the period of limitation for filing application under Section 20 of the Arbitration Act, 1940, is as prescribed under Article 137 of the Limitation Act. F Under Section 20 of the Act, the cause of action for filing an application may arise whenever "a difference has arisen to which the agreement applies". Regard must be had to the relevant arbitration clause in the agreement. If any specific terms are used in the arbitration clause, that would govern the parties as to when a petition for reference of arbitration shall be filed in Court. In the instant case, the arbitration clause states that all parties would G resolve such differences by mutual consultation failing which either party must give to the other notice in writing of the existence of such question, dispute or difference and the same shall be referred for the final determination. The appellant issued notice to the respondent and a definite reply was received by the appellant. It is clear that cause of action for filing had arisen, the moment H the appellant received the reply notice denying the claims made by the appel- ASIA RESORTS LTD. _v._ USHA BRECO LTD. [BALAKRISHNAN, J.] 573 lant. Therefore, the Division Bench has rightly held that the application was barred by time. The appellant herein has filed an application under Section _5_ of the Limitation Act praying that the delay in filing the application under Section 20 of the Act be condoned. Section _5_ of the Limitation Act says any appeal or any application, other than application under any of the provisions of Order XXI of the Code of Civil Procedure, 1908, may be admitted after the prescribed period, if the appellant or the applicant satisfies the court that he had sufficient cause for not preferring the appeal or making the application within such period. The applicant can show sufficient cause for not filing the application in time. It appears that this Court had no occasion to consider whether Section _5_ of the Limitation Act, 1963 could be applied in the case of an application to be filed under Section 20 of the Arbitration Act, 1940. The Division Bench of the High Court of Delhi in _Union of India and Anr._ v. _Mis. Vijay Construction Co.,_ AIR (1981) Delhi 193 held that the benefit of Section _5_ of the Limitation Act can be availed by the applicant for an application under Section 20 of the Arbitration Act. Going by the provision contained in Section _5_ of the Act, we are also of the view that in an appropriate case the court can extend the benefit of the said Section. The counsel for the appellant contended that a prayer was made before the High Court for condoning the delay, if any, but the same was rejected. As per the Arbitration clause, the disputes between the parties could be referred to a single arbitrator if agreed to by both the parties but in case of disagreement both the parties can appoint one arbitrator each and in case of disagreement between the said two arbitrators there is a provision that an umpire also could be appointed by the two arbitrators. In the instant case, the learned Single Judge straightaway appointed the arbitrator. Though there was a cause of action for the appellant to initiate proceedings under the Arbitration Act for appointment of an arbitrator, the appellant failed to do, so. The letter written by the respondent on 6.4.1993 indicates that the respondent had some proposal for consideration. > Having regard to the nature of disputes between the parties, we are of the view that the delay caused in filing the application by the appellant was not willful and hence is liable to be condoned. However, in the facts and circumstances of the case we are also of the view that the delay shall be liable to be A B ..... C D E F G H SUPREME COURT REPORTS [2001] SUPP. 4 S.C.R. 574 _.("_ A condoned only upon payment of costs. Accordingly, the delay in filing the application under Section 20 of the Arbitration Act is condoned on condition that the appellant pays a sum of Rs.20,000 to the respondent within a period of one month. The said sum of Rs.20,000 shall be deposited with the Registrar General of this Court on or before lst December, 2001 and on such deposit B the respondent would be at liberty to withdraw the same. For payment of cost as stated above, . the. appeal would stand allowed and the matter would be remitted to the High Court to be proceeded with in accordance with the provisions of the Arbitration Act, 1940, read with relevant arbitration clause in the agreement between the parties. In case the appellant fails to deposit the said amount of Rs.20,000 within the stipulated period, the appeal woul~ be c deemed to have been dismissed .without further reference to the Court. B ## I.A. Nos. 1 to 4 would stand allowed. The appeal is disposed of in the aforesaid terms. K.K.T. Appeal disposed of.
End of Judgment Record
Browse All Supreme Court of India (2001) Decisions
2001-08-07

Sajan Abraham v. State of Kerala

On 7 August 2001, the Supreme Court rendered its judgment in Sajan Abraham v. State of Kerala arising from a Narcotic Drugs and Psychotropic Substances Act case. The appellant was charged under Section 21 for possession of Buprenorphine and three syringes near Palluruthy, after information from a Head Constable led to seizure by a Special Squad and arrest following an on-site search. The Trial Court acquitted due to inconsistencies; the Kerala High Court, on reappraisal, convicted and sentenced the appellant to ten years’ rigorous imprisonment and a Rs 1 lakh fine. The prosecution contended violations of Sections 42, 50 and 57: failure to record information in writing and communicate it to the immediate superior before arrest; failure to inform the accused in writing of the right to be searched in the presence of a Magistrate or Gazetted Officer; and non-submission of a full report within 48 hours. The Supreme Court adopted a pragmatic approach to mandatory provisions in the NDPS Act, recognizing the stringent nature of the statute but allowing substantial compliance to suffice when it results in no prejudice and promotes timely action to prevent escape. It held that the information was conveyed promptly, the Section 50 right was validly communicated orally, and that copies of FIR and seizure records were sent to the superior, satisfying substantial compliance with Section 57. Citing State of Punjab v Baldev Singh and Balbir Singh, the Court dismissed the appeal, upholding the conviction and sentence.

2001-08-08

P. C. Joshi v. State of U.P. and ORS.

This Supreme Court appeal concerns a judicial officer challenged termination following disciplinary proceedings. The Allahabad High Court had dismissed a writ petition filed by the appellant after the Enquiry Officer held him guilty of several charges, including missteps in bail orders. The central issue was whether initiation of disciplinary action is warranted where an order is faulty or where a different action could have been taken. The Court emphasized that a bona fide erroneous exercise of judicial powers cannot be treated as misconduct and warned against a chilling effect on judicial independence: if every faulty judgment triggered a disciplinary inquiry, subordinate judges would fear writing judgments. It relied on established constitutional principles that safeguard the independence of the judiciary and prevent routine harassment through disciplinary machinery over minor or non-mala fide errors. The Court referred to the tests laid down in Union of India v. A.N. Saxena and Union of India v. K.K. Dhawan for determining when disciplinary action may be initiated. In evaluating the bail-related charges, the Court found that the Enquiry Officer’s conclusions rested on inferences rather than legally tenable evidence, rendering substantial parts of the findings vitiated. Consequently, the judgment of the High Court was set aside and the appellant was reinstated with continuity of service and arrears of salary, with no costs.

2001-04-09

Bank of India v. Secretary, Bank of India Staff Union and Anr.

Bank of India v. Secretary, Bank of India Staff Union and Anr. concerns entitlement to special 'Special Assistant' allowances for staff serving as clearing-house representatives. The Industrial Tribunal-cum-Labour Court at Kanpur held that the concerned workmen were entitled to special assistant allowances for the number of days they worked at various collection centres and clearing-house duties, with payment to be made for the days actually worked from the date of reference. The Bank challenged the award on two fronts: first, that the duties performed by the workers did not require the greater skill and responsibility of a Special Assistant, being largely clerical in nature; and second, that the Special Assistant duties were defined by the Bipartite Settlements (1966 and its modifications, including 1984) and awards (Sastry and Desai). The workers contended that they performed duties as authorised representatives at clearing houses of RBI and State Bank of India and carried out routine bank duties connected with clearing. On appeal, the Supreme Court found that the Tribunal had not adjudicated the precise duties and responsibilities with reference to the parties’ contentions and evidence, and there was no concrete finding that the workers discharged duties warranting Special Assistant status. The Court set aside the Tribunal’s award and remitted the matter for fresh consideration, directing examination of the exact duties in light of the Bipartite Settlements and Sastry/Desai framework.

2001-09-13

KANHAIYALAL AGRAWAL AND ORS. v. THE FACTORY MANAGER, GWALIOR SUGAR CO. LTD.

These cross-appeals arise from termination of employees by the Gwalior Sugar Company. The Labour Court held that three workmen—Kanhaiyalal Agrawal and two others—had contravened prescribed procedures and, on the basis of evidence, found loss of confidence in them, denying reinstatement and awarding half salary with full retirement benefits. The Industrial Court, by contrast, held that the employees had not committed misappropriation of money but were negligent in performing their duties, and directed reinstatement without back wages. A Single Judge of the Madhya Pradesh High Court upheld the Industrial Court’s order. A Division Bench of the High Court dismissed the writ appeals on the ground that they arose under Article 227 (revisional jurisdiction) and were not maintainable. The present appeals before the Supreme Court, by management and workmen, focus on whether loss of confidence can be reversed and whether back wages should be payable. The Supreme Court held that the Industrial Court was correct in reversing the Labour Court’s finding of loss of confidence since such loss must be based on objective facts rather than subjective managerial belief. It affirmed the permissibility of reinstatement without back wages and declined to disturb the earlier orders, dismissing the appeals with no costs.