High Court of KeralaSingle JudgeWrit petition dismissed.

Ashrae Clean Room Presentations Private Limited v Department of Industries and Commerce, Government of Kerala and Kerala State Drugs & Pharmaceuticals Limited

Case / Petition Number:WP(C) No. 28448/2021

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • N. Nagareesh, J.
Judgment Date
2022-02-01
Court Decision / Holding
In the facts and circumstances of the case, this Court finds that the petitioner has to resort to arbitration or other civil proceedings for redressal of grievances and a writ petition is not maintainable. The writ petition is consequently dismissed.
Final Disposition
Writ petition dismissed.

Parties to the Case

Appellants / Petitioners

  • Ashrae Clean Room Presentations Private Ltd

Respondents

  • Department of Industries and Commerce represented by its Principal Secretary (Industries), Secretariat, Thiruvananthapuram-695001
  • The Kerala State Drugs & Pharmaceuticals Limited, Kalavoor, Alappuzha, Kerala-688522, represented by its Managing Director

Legal Representation & Advocates

Counsels for Petitioners

  • • Navia Sebastian

Counsels for Respondents

  • • Shri. P.C. Sasidharan, SC, Kerala State Drugs and Pharmaceuticals Limited
  • • Sri. P. Santhoshkumar, SPL.GP (Industries)

Case Synopsis & Summary

Ashrae Clean Room Presentations Private Limited, a company specialised in clean room technology and HVAC systems, petitioned under Article 226 of the Constitution of India, challenging three tenders issued by the Kerala State Drugs and Pharmaceuticals Limited (KSDP) for GMP-compliant projects: non-beta lactam HVAC works, Clean Room PCGI panels, and beta-lactam blister packing HVAC works. The petitioner's core grievance is that the tender calls (Ext.P14–P16, issued on 07/12/2021) were arbitrary, illegal, and unreasonable. It asserts improper process, with incomplete or altered drawings (the partition design reportedly changed 14–16 times), and delays in site access and measurements. The petitioner also complains of withholding payments, invocation of bank guarantees, and termination of the three work orders (07/12/2021 era) without adequate notice or proper joint measurement. The petitioner seeks recall/cancellation of the tenders, restoration of work, settlement of accounts, and continuation of works. The respondents contend that the petitioner failed to progress the works within the contractual timeframes, leading to delays and financial losses; they argue termination was contractually justified and that disputes arise from a commercial arrangement best resolved by arbitration, not by writ. The court ultimately examines the maintainability of a writ in a commercial dispute with arbitration provisions and dismisses the petition in favor of arbitration or civil remedies.

Provisions of Law Cited

Constitution of India, Article 226

Legal Doctrines & Maxims

  • Time is the essence of contract

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that the second respondent invited tenders for three GMP-standard projects without providing complete drawings and site access, and that the design for partitions was altered 14–16 times, making timely completion unfeasible. Payments were withheld and bank guarantees invoked; termination notices were issued against three work orders. Petitioner seeks recall/cancellation of tender calls, joint measurements, return of tools, and relief by writ, arguing arbitration is available per the contracts but writ may be entertained per Union of India v Tantia Constructions Private Limited (2011) 5 SCC 697 to an extent. It emphasises that the contract includes arbitration and that the court should exercise supervisory jurisdiction only where warranted, and that the disputes are commercial in nature.

Contentions of Respondents

The respondents argue that the petitioner failed to progress works, despite meetings and extensions, resulting in delays and losses. They contend that termination was in line with the contracts and that disputes under the agreements must be resolved through arbitration; they assert the writ jurisdiction is not available for commercial disputes and note that the petitioner’s requests for joint inspection and measurements were made after termination. They maintain that payments were due and that bank guarantees were rightly invoked; the matter is fundamentally contractual, requiring arbitration or civil action rather than Writ under Article 226.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Union of India and others v. Tantia Constructions Private Limited(2011) 5 SCC 697Mentioned OnlyCited in argument to support that alternative remedy is not an absolute bar to invoking jurisdiction; the court does not rely on it to grant writ relief, and ultimately dismisses the petition in favor of arbitration/civil remedies.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Ashrae Clean Room Presentations Private Limited v Department of Industries and Commerce, Government of Kerala and Kerala State Drugs & Pharmaceuticals Limited and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

# **IN THE HIGH COURT OF KERALA AT ERNAKULAM** ## **PRESENT** **THE HONOURABLE MR.JUSTICE N.NAGARESH** **TUESDAY, THE 1[ST] DAY OF FEBRUARY 2022 / 12TH MAGHA, 1943** **WP(C) NO. 28448 OF 2021** ## **PETITIONER:** **ASHRAE CLEAN ROOM PRESENTATIONS PRIVATE LTD A COMPANY INCORPORATED UNDER THE COMPANIES ACT, REP BY MANAGING DIRECTOR, MR.MS. ANAND, S/O. N.C.G.NAIR, AGED 74, D-73, 1ST FLOOR, MADHURA NAGAR, S.R.NAGAR P.O., HYDERABAD-500038 , TELENGANA** ## **BY ADV NAVIA SEBASTIAN** ## **RESPONDENTS:** - **1 THE DEPARTMENT OF INDUSTRIES AND COMMERCE REPRESENTED BY ITS PRINCIPAL SECRETARY (INDUSTRIES), SECRETARIAT, THIRUVANANTHAPURAM-695 001** - **2 THE KERALA STATE DRUGS & PHARMACEUTICALS LTD, KALAVOOR, ALAPUZHA, KERALA-688 522, REPRESENTED BY ITS MANAGING DIRECTOR** **BY ADV SHRI.P.C.SASIDHARAN, SC, KERALA STATE DRUGS AND PHARMACEUTICALS LIMITED** **SRI.P.SANTHOSHKUMAR, SPL.GP (INDUSTRIES)** **THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 01.02.2022, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** W.P.(C) No.28448/2021 : 2 : ## **N. NAGARESH, J.** ````````````````````````````````````````````````````````````` ## W.P.(C) No.28448 of 2021 ````````````````````````````````````````````````````````````` _Dated this the 1[st] day of February, 2022_ ## **J U D G M E N T** ~ ~ ~ ~ ~ ~ ~ ~ ~ The petitioner is a Company doing business in Heating, Ventilation and Air Conditioning. The petitioner is also specialised in Clean Room Technology. The petitioner has filed this writ petition seeking the following reliefs: (i) Issue any appropriate Writ by declaring the action of the 2[nd] respondent in calling for Tender for Supply, Installation, Testing, Commissioning & Validation of HVAC Works as per GMP Standard for Non-Beta Lactam Project vide Ext.P14 Tender Reference Number KSDP/PRJ/NB/HVAC/10/2122/124 DATED 07/12/2021 AT 01:43 PM, as arbitrary, illegal and unreasonable. (ii) Issue any appropriate Writ by declaring the action of the 2[nd] respondent in calling for Tender for Supply, Installation, Testing and Commissioning of Clean Room Panel Works Using PCGI Panels as per GMP Standard for Non-Beta Lactam Project vide Ext.P15 Tender Reference Number KSDP/PRJ/NB/PCGI/09/21-22/123 DATED W.P.(C) No.28448/2021 : 3 : 07/12/2021 01:48 PM, as arbitrary, illegal and unreasonable. (iii) Issue any appropriate Writ by declaring the action of the 2[nd] respondent in calling for Tender for Supply, Installation, Testing, Commissioning and Validation of HVAC System as per GMP Standard for Beta Lactam Blister Packing Project vide Ext.16 Tender Reference Number KSDP/PRJ/BETA/11/2122/125 DATED 07/12/2021 01:45 PM, as arbitrary, illegal and unreasonable. (iv) Issue Writ of Mandamus or any other appropriate writ directing the 2[nd] respondent to recall & cancel the Tender for Supply, Installation, Testing, Commissioning & Validation of HVAC Works as per GMP Standard for Non Beta Lactam Project vide Ext.P14 Tender Reference Number KSDP/PRJ/NB/HVAC/10/21-22/124 DATED 07/12/2021 AT 01:43 PM. (v) Issue Writ of Mandamus or any other appropriate writ directing the 2[nd] respondent to recall & cancel the Tender for Supply, Installation, Testing and Commissioning of Clean Room Panel Works Using PCGI Panels as per GMP Standard for NonBeta Lactam Project vide Ext.P15 Tender Reference Number KSDP/PRJ/NB/PCG1/09/2122/123 DATED 07/12/2021 01:48 PM. (vi) Issue Writ of Mandamus or any other appropriate writ directing the 2[nd] respondent to recall & cancel the Tender for Supply, Installation, Testing, Commissioning and Validation of HVAC System as per GMP Standard for Beta Lactam Blister Packing Project vide Ext.P16 Tender Reference Number KSDP/PRJ/BETA/11/21-22/125 DATED 07/12/2021 01:45 PM. (vii) Issue Writ of Mandamus or any other appropriate writ directing the 2[nd] respondent to cancel the Termination of Workup order dated 19/02/2018 and permit the petitioner to continue the works. W.P.(C) No.28448/2021 : 4 : (viii) Issue Writ of Mandamus or any other appropriate writ directing the 2[nd] respondent to cancel Termination Notice dated 28/09/2021 of Work order dated 19/02/2018 and permit the petitioner to continue the works. (ix) Issue Writ of Mandamus or any other appropriate writ directing the 2[nd] respondent to cancel the Termination Notice dated 28/09/2021 of Work order 30/12/2017 and permit the petitioner to continue the works. (x) Issue Writ of Mandamus or any other appropriate writ directing the 2[nd] respondent to cancel the Termination Notice dated 28/09/2021 of Work order dated 10/01/2018 and permit the petitioner to continue the works. (xi) Issue Writ of Mandamus or any other appropriate writ directing the 2[nd] respondent to settle the accounts after conducting the measurements for the works done and release the payments to the petitioner. 2. In the writ petition, it has been pleaded as follows. The 2[nd] respondent-Kerala State Drugs and Pharmaceuticals Limited is a Government of Kerala Undertaking. The petitioner has executed a number of works for the 2[nd] respondent. The 2[nd] respondent awarded three new works and issued work order Nos.KSDP/PRJ/NBETA/HVAC/ 30/1718/57 dated 30.12.2017, KDSP/PRJ/NBETA/PCGI/13/ 17-18/38 dated 11.11.2017 and KDSP/PRJ/BETABLISTER/ W.P.(C) No.28448/2021 : 5 : HVAC/38/17-18/77 dated 12.11.2018. Though the petitioner has been executing these works, the 2[nd] respondent withheld payments. The petitioner was not provided with structural drawings and site for progress of the work. At the same time, the 2[nd] respondent tried to invoke Bank Guarantee provided by the petitioner. The petitioner filed O.S. No.1275/2019 before the XXI Junior Civil Judge, Hyderabad. When the 2[nd] respondent tried to invoke Bank Guarantee, the petitioner filed injunction Suit. The 2[nd] respondent arbitrarily invoked Bank Guarantee. 3. The petitioner issued Ext.P3 letter dated 11.08.2021 to the 2[nd] respondent seeking payment of Bills to the tune of ₹1,58,35,448/- due to the petitioner. The 2[nd] respondent, in response, directed the petitioner to complete all pending works within 30 days, as per Ext.P4 letter dated 26.08.2021. The petitioner submitted Ext.P5 reply dated 28.08.2021 pointing out that the work order was amended on three occasions and the 2[nd] respondent has not adhered to the contractual obligation of diminishing Bank Guarantee. W.P.(C) No.28448/2021 : 6 : The design of the partition was changed 14 to 16 times and it is humanly impossible to complete the work even in 90 days. By Ext.P6 letter dated 28.08.2021, the petitioner reminded the 2[nd] respondent about the pending bills. 4. To the dismay of the petitioner, the 2[nd] respondent terminated all the three work orders as per Exts.P7 to P9 dated 28.09.2021. The petitioner submitted Exts.P10 to 12 replies dated 29.09.2021 to Exts.P7 to P9 cancellations. The petitioner also requested for a joint measurement as to the work completed by the petitioner and requested for return of tools, as per Ext.P13 letter dated 10.11.2021. The request of the petitioner fell in deaf ears. Hence, the petitioner is before this Court. 5. The 2[nd] respondent filed a Statement and contested the writ petition. The 2[nd] respondent stated that the petitioner though entered into three agreements, did not show any progress in terms of the work order. The respondents have been issuing letters one after another to the petitioner requiring to complete the works as scheduled. W.P.(C) No.28448/2021 : 7 : The entire modernisation work of the 2[nd] respondentCompany was unduly delayed. Negotiations were held with the petitioner. A joint meeting was convened on 12.06.2019. The petitioner agreed to complete all works on or before 31.07.2019. Even thereafter, the works were not proceeding. Further discussions with the petitioner were held on 09.11.2019. The petitioner was granted extended time to complete the works. The petitioner as per Annexure-R2(e) agreed to complete the works by 27.02.2020. 6. The petitioner still did not honour its commitment. The delay on the part of the petitioner in executing the works would result in payment of liquidated damages to the States with whom the 2[nd] respondent entered into agreements for supply of medicines. In the circumstances, the 2[nd] respondent had no other option than to terminate the contracts. Time is the essence of all the three contracts. The agreement provided that if there is a dispute between the petitioner and the 2[nd] respondent, it should be resolved through arbitration proceedings. O.S. No.1275 of 2019 filed W.P.(C) No.28448/2021 : 8 : by the petitioner before the Junior Civil Judge, City Civil Court, Hyderabad was dismissed as per Annexure-R2(f). O.S. No.2174 of 2019 filed by the petitioner was closed as per Annexure-R2(g) as the issue was referred to Arbitrator. 7. The 2[nd] respondent has already revoked the Bank Guarantee and has terminated the agreements. The works were re-tendered. The contention of the petitioner that measurement was not taken in its presence does not merit any consideration. The measurement was taken in the presence of the representatives of the petitioner-Company. The 2[nd] respondent is entitled to recover the loss incurred from the petitioner. The petitioner cannot invoke this Court’s writ jurisdiction for redressal of disputes of a commercial nature. 8. The learned counsel for the petitioner submitted that in view of the judgment of the Apex Court in _**Union of India and others v. Tantia Constructions Private Limited**_ _[(2011) 5 SCC 697]_ , alternative remedy is not an absolute bar to invoke the jurisdiction of this Court. Arbitration is only W.P.(C) No.28448/2021 : 9 : one alternate remedy as per the agreement. The petitioner had assured the 2[nd] respondent that work will be completed in all respects and plant handed over to the 2[nd] respondent on or before 27.02.2020, provided the 2[nd] respondent clears all the 22 points mentioned in the e-mail dated 18.11.2019 forwarded by the petitioner. 9. The counsel for the petitioner pointed out that the measurements noted by the respondents in Ext.R2(k) are not visible and is not countersigned by the petitioner. Entire joint measurements have not been taken. Joint measurements of a large number of works, have not been done. The termination of the contracts is highly arbitrary. As per the terms of contract, Agreement Authority shall give 15 days notice of termination in writing to the Contractor, which has not been done by the 2[nd] respondent. The drawings given by the 2[nd] respondent were incomplete, which is the major reason for the delay. 10. I have heard the counsel for the petitioner, the Special Government Pleader (Industries) for the 1[st] W.P.(C) No.28448/2021 : 10 : respondent and the Standing Counsel for the 2[nd] respondent. 11. Three contracts were entered into by the petitioner and work orders were issued on 11.11.2017, 30.12.2017 and 12.11.2018. The first two works were to be completed within 90 days and the 3[rd] one within 30 days. The petitioner did not carry out the work with promptitude. A joint meeting was convened by the 2[nd] respondent on 12.06.2019. By the time, more than 18 months had elapsed. In this meeting, the petitioner agreed to complete all the works before 31.07.2019. Annexure-R2(d) minutes of the meeting would disclose that the petitioner had not raised any technical issues which would hamper the completion of work. The issue of drawings is not seen raised by the petitioner in the meeting. The only concern expressed appears to be in respect of payment of Bills. 12. The petitioner did not complete the work by 31.07.2019. Again, another meeting was held on 09.11.2019. By Annexure-R2(e), the petitioner again agreed W.P.(C) No.28448/2021 : 11 : to complete the work by 27.02.2020. It is the specific case of the 2[nd] respondent that it had cleared all the 22 points as mentioned in the petitioner’s e-mail dated 18.11.2019. Yet, the work was not completed even by 27.02.2020. The inordinate delay on the part of the petitioner delayed the modernisation plans of the 2[nd] respondent and consequential financial losses were incurred. 13. The agreements provided for arbitration proceedings for resolution of any disputes arising from the agreements. The petitioner, however, filed O.S. No.1275/2019 in the Court of the Junior Civil Judge, City Civil Court, Hyderabad during the extended period of contract, which was withdrawn on 30.07.2019. In another O.S. No.2174/2019 filed before the Court of the Junior Civil Judge, the said court referred the dispute for arbitration as per Annexure-R2(g) order. 14. The 2[nd] respondent has already terminated the contracts and has invoked Bank Guarantee. The works have been already retendered. W.P.(C) No.28448/2021 : 12 : 15. The grounds urged by the petitioner challenging termination of contracts are all disputed questions of facts which cannot be decided by this Court, in exercise of the powers conferred under Article 226 of the Constitution of India. The agreements executed by the petitioner provide for arbitration for resolution of disputes arising out of the contract. The counsel for the petitioner urged that even if the petitioner is to be relegated to arbitration proceedings, this Court may order a joint inspection in respect of the works completed by the petitioner in pursuance of the agreements. The 2[nd] respondent disputed the said claim also stating the measurements of works done by the petitioner have already been taken in the presence of the officials of the petitionercompany. 16. In the facts and circumstances of the case, this Court find that the petitioner has to resort to arbitration or other civil proceedings for redressal of grievances and a writ petition is not maintainable, in the facts of the case. W.P.(C) No.28448/2021 : 13 : The writ petition fails and it is consequently dismissed. Sd/- **N. NAGARESH, JUDGE** aks/28.01.2022 W.P.(C) No.28448/2021 : 14 : ## **APPENDIX OF WP(C) 28448/2021** ## **PETITIONER'S EXHIBITS** **Exhibit P1 TRUE COPY OF ORDER IN IA NO.223/2019 IN OS NO.1275/2019 DATED 06.06.2019 PASSED BY THE HON'BLE XXI JUNIOR CIVIL JUDGE, HYDERABAD Exhibit P2 TRUE COPY OF ORDER IN IA NO.510/2019 IN OS NO.2174/2019 DATED 19.09.2019 PASSED BY THE HON'BLE XXI JUNIOR CIVIL JUDGE, HYDERABAD Exhibit P3 TRUE COPY OF LETTER DATED 11.08.2021 ISSUED BY THE PETITIONER TO THE RESPONDENT NO.2 REGARDING NON PAYMENT OF AN AMOUNT OF RS 1,58,35,448/Exhibit P4 TRUE COPY OF RESPONDENT NO.2 ISSUED LETTER DATED 26.08.2021 TO PETITIONER WHEREIN 30 DAYS WERE PROVIDED TO COMPLETE ALL THE PENDING WORKS Exhibit P5 TRUE COPY OF REPLY LETTER DATED 28.08.2021 ISSUED BY THE PETITIONER TO THE LETTER DATED 26.08.2021 Exhibit P6 TRUE COPY OF LETTER DATED 28.08.2021 ISSUED BY THE PETITIONER WHEREIN IT WAS CATEGORICALLY STATE THAT THE DESIGN FOR THE PETITIONERS WERE CHANGED 14 TO 16 TIMES Exhibit P7 TRUE COPY OF LETTER DATED 28.09.2021 ISSUED BY RESPONDENT NO.2 TERMINATING WORK ORDER DATED 19.02.2018** **Exhibit P8 TRUE COPY OF LETTER DATED 28.09.2021 ISSUED BY RESPONDENT NO.2 TERMINATING WORK ORDER DATED 30.12.2017** **Exhibit P9 TRUE COPY OF LETTER DATED 28.09.2021 ISSUED BY RESPONDENT NO.2TERMINATING WORK ORDER DATED 10.01.2018 Exhibit P10 TRUE COPY OF THE SAID CANCELLATION OF** **TRUE COPY OF THE SAID CANCELLATION OF WORK ORDER DATED 30.12.2017 WAS REPLIED BY THE PETITIONER BY VIRTUE OF LETTER DATED 29.09.2021** W.P.(C) No.28448/2021 : 15 : - **Exhibit P11 TRUE COPY OF THE SAID CANCELLATION OF WORK ORDER DATED 10.01.2018 WAS REPLIED BY THE PETITIONER BY VIRTUE OF LETTER DATED 29.09.2021** - **Exhibit P12 TRUE COPY OF THE SAID CANCELLATION OF WORK ORDER DATED 19.02.2018 WAS REPLIED BY THE PETITIONER BY VIRTUE OF LETTER DATED 29.09.2021** - **Exhibit P13 TRUE COPY OF LETTER DATED 10.11.2021 ISSUED BY PETITIONER FOR REQUESTING FOR COMBINED MEASUREMENTS FOR ALL THE JOBS ALONG WITH RETURNING OF TOOLS AND TACKLES TO THE RESPONDENT NO.2** - **Exhibit P14 TRUE COPY OF TENDER FOR SUPPLY INSTALLATION TESTING COMMISSIONING & VALIDATION OF HVAC WORKS AS PER GMP STANDARD FOR NON-BETA LACTAM PROJECT VIDE TENDER REFERENCE NUMBER KSDP/PRJ/NB/HVAC/10/21-22/124 DATED 07.12.2021 AT 01.43 PM** - **Exhibit P15 TRUE COPY OF TENDER FOR SUPPLY INSTALLATION TESTING AND COMMISSIONING OF CLEAN ROOM PANNEL WORKS USING PCGI PANELS AS PER GMP STANDARD FOR NONBETA LACTAM PROJECT VIDE TENDER REFERENCE NUMBER KSDP/PRJ/NB/PCGI/09/2021-22/123 DATED 07.12.2021 AT 01.48 PM** - **Exhibit P16** - **TRUE COPY OF TENDER FOR SUPPLY INSTALLATION TESTING COMMISSIONING AND VALIDATION OF HVAC SYSTEM AS PER GMP STANDARD FOR BETA LACTAM BLISTER PACKING PROJECT VIDE TENDER REFERENCE NUMBER KSDP/PRJ/BETA/11/21-22/125 DATED 07.12.2021 AT 01.45 PM** ## **RESPONDENT EXHIBITS** - **Exhibit R2(a) COPY OF WORK ORDER DT 11.11.2017 Exhibit R2(b) COPY OF WORK ORDER DT 30.12.2017 BY 2ND RESPONDENT** - **Exhibit R2(c) COPY OF WORK ORDER DT 12.11.2018 Exhibit R2(d) COPY OF MINUTES OF MEETING WITH THE PETITIONER ON 12.6.2019** W.P.(C) No.28448/2021 : 16 : **Exhibit R2(e) COPY OF AGREEMENT REGARDING COMPLETION OF WORKS DT 28.11.2019 Exhibit R2(f) COPY OF ORDER OF JUNIOR CIVIL JUDGE, CITY CIVIL COURT, HYDERABAD. Exhibit R2(g) COPY OF ORDER OF JUNIOR CIVIL JUDGE, CITY CIVIL COURT, HYDERABAD IN IA.581/2019 Exhibit R2(h) COPY OF EMAIL DT 31.5.2021. Exhibit R2(I) TRUE COPY OF THE LETTER DATED 03/10/2019 ADDRESSED TO THE PETITIONER REGARDING INFORMING OF THE ACT** **Exhibit R2(J) TRUE COPY OF THE HVAC WORK FOR NON BETALCTUM PLANT MEASURED BY THE 2ND RESPONDENT** **Exhibit R2(K) TRUE COPY OF THE MEASUREMENT IN RELATION TO PCGI PANEL OF NON BETALACTUM PROJECT WAS MADE ON 09/03/2021** **Exhibit R2(L) TRUE COPY OF THE JOINT MEASUREMENT MADE ON 25/03/2021 Exhibit R2(M) TRUE COPY OF THE ACKNOWLEDGEMENT MADE BY THE PETITIONER REGARDING THE JOINT MEASUREMENT DATED 05/07/2021** **Exhibit R2(N) TRUE COPY OF THE TENDER DETAILS CONTAINING THE DRAWINGS DATA SHEET AND SPECIFICATION**