Ashish Seth v. Sumit Mittal and others
Case Synopsis & Summary
This Supreme Court contempt matter concerns two groups—Seth Group and Mittal Group—whose dispute arises from a Memorandum of Settlement (MOS) dated 4 May 2015, incorporated into the Court’s orders in Writ Petition (Criminal) No. 5 of 2015 and No. 11/2015. The MOS allocated obligations between the groups in relation to renewal of three 2007 licenses (Nos. 34, 35 and 36) and associated EDC liabilities, with bifurcation of land shares (Seth: 14.80 acres; Mittal and others: remaining land) and payment arrangements to be overseen by TFIPL and DTCP Haryana. In an order dated 24 April 2020, the Court held the Mittal Group had deliberately and wilfully failed to fulfill MOS obligations, rendering them liable to contempt, but extended two months from lockdown to complete the obligations. Despite this, renewals were not effected and EDC liabilities remained unpaid. IA 78952/2020 (Seth Group) sought bifurcation/renewal in Seth’s favor and handover to buyers; IA 96206/2020 (Mittal Group) sought to compel Seth to furnish documents and to use the new One-Time Settlement scheme “Samadhan Se Vikas.” The Court, after hearing, reiterated the need for renewal, clarified MOS terms, directed payment of renewal fees and EDC liability, and disposed of the IAs with a fresh eight-week deadline for completion and a three-month compliance report.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- M.R. Shah
- Ashok Bhushan
- Judgment Date
- 2020-10-09
- Court Decision / Holding
- Interlocutory Applications Nos. 96161/2020, 96206/2020, 68143/2020, 78952/2020 and 78953/2020 disposed off. The Court reaffirmed earlier directions from 24.04.2020, directed Mittal Group to apply for renewal within two weeks, clarified liability for renewal fees proportionate to land shares, and ordered both groups to participate in the new EDC settlement scheme “Samadhan Se Vikas.” It directed completion of the renewal exercise within eight weeks and required specific undertakings to comply with the EDC settlement, with warnings that non-compliance would invite contempt actions. The matter is to be placed for reporting compliance after three months.
- Final Disposition
- Interlocutory applications disposed of; fresh directions issued for renewal and EDC settlement; compliance timeline set; contempt consequences reserved; reporting compliance due in three months.
Parties to the Case
Appellants / Petitioners
- Ashish Seth
Respondents
- Sumit Mittal and others
Legal Representation & Advocates
Counsels for Respondents
- • Shri Ranjit Kumar, Senior Advocate
Provisions of Law Cited
Submissions & Arguments
Contentions of Appellants / Petitioners
The Seth Group contends that Mittal Group has deliberately obstructed renewal and failed to comply with MOS obligations incorporated by Court order. It asserts it has fulfilled its MOS 4 May 2015 obligations, having already paid substantial sums, and seeks bifurcation/renewal in Seth’s favor if Mittal defaults, plus handover of flats to buyers in a time-bound manner. It seeks relief in IA 78952/2020 and asks the Court to ensure timely renewal and EDC settlement, with the DTCP framework applied, so that homebuyers are protected.
Contentions of Respondents
The Mittal Group argues renewal requires furnishing documents as per the DTCP Check-List; Seth Group has not provided requisite documents, causing delay. Mittal contends it is ready to avail the new One-Time Settlement Scheme “Samadhan Se Vikas” to settle EDC dues and seeks renewal within the parameters of the scheme, including 90 days after compliance. It asserts that Seth bears responsibility for non-compliance and that renewal should occur only after proper document submission and payment of charges, including those of PAL, ORS and Heritage, with the Mittal Group handling balance renewal payments and related charges.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Ashish Seth v. Sumit Mittal and others
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.