Arce Polymers Private Limited v. M/s Alphine Pharmaceuticals Private Limited and Others

Case / Petition Number:
Civil Appeal No. 7372 of 2021; Civil Appeal No. 7373 of 2021

Case Synopsis & Summary

This appeal arises from a SARFAESI sale of a mortgaged asset situated at IDA Jeedimetla, Hyderabad, following default by Alphine Pharmaceuticals Private Limited to Andhra Bank. The High Court of Telangana set aside the sale, ruling that the bank failed to comply with Section 13(3A) by not providing a timely, reasoned response to the borrower’s representations and that the valuation/valuation process and the timing of actions violated SARFAESI. The borrower had submitted representations on 1 and 6 November 2016 seeking moratorium and restructuring; the bank had, however, deferred action for nearly a year and engaged in negotiations, including a November 2016 letter recommending deferral and subsequent restructuring discussions. The bank later issued possession under Section 13(4) in March 2017, followed by physical possession and multiple auctions culminating in sale to Basa Chandramouli in September 2018. The Debts Recovery Tribunal upheld the sale, and the Telangana High Court quashed it. The Supreme Court held that the borrower’s conduct, including repeated representations and forbearance by the bank, amounted to waiver/estoppel, and thus nullified the mandatory effect of some aspects of Section 13(3A). It allowed the appeals, set aside the High Court order, dismissed the writ petition, and upheld the DRT’s sale, with no costs order.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • L. Nageswara Rao
  • Sanjiv Khanna
  • B. R. Gavai
Judgment Date
2021-12-03
Court Decision / Holding
Appeals allowed; Impugned Telangana High Court order quashing sale set aside; writ petition dismissed; Debts Recovery Tribunal order upholding SARFAESI sale upheld.
Final Disposition
Appeals allowed; writ petition dismissed; DRT order upheld.

Parties to the Case

Appellants / Petitioners

  • Arce Polymers Private Limited

Respondents

  • M/s Alphine Pharmaceuticals Private Limited
  • Bejjenki Bhaskara Chary
  • M/s Andhra Bank (Bank)
  • Basa Chandramouli (auction purchaser)

Provisions of Law Cited

Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 (SARFAESI Act) – Section 13(2)Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 – Section 13(3A)Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 – Section 13(4)Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 – Section 17(1)SARFAESI Rules, 2002 – Rule 8(1)SARFAESI Rules, 2002 – Rule 8(6)

Legal Doctrines & Maxims

  • Waiver
  • Estoppel (including Equitable Estoppel)
  • Discretionary relief / Moulding of relief
  • Forbearance / equitable considerations in the exercise of statutory rights

Submissions & Arguments

Contentions of Appellants / Petitioners

Arce Polymers argued that the bank’s sale should be sustained as valid under SARFAESI, emphasising that the bank had complied with the Act, engaged in negotiations, and that any alleged violation of Section 13(3A) was superseded by waiver/estoppel due to the borrower’s repeated representations and forbearance by the bank. They contended the valuation process, timing of notices, and the repeated opportunities given to the borrower supported maintaining the sale.

Contentions of Respondents

Alphine Pharmaceuticals and other respondents contended that the bank violated mandatory requirements of Section 13(3A) by failing to provide a reasoned response to representations; that the representations needed timely consideration, that the valuation of machinery and other procedural steps were improper; they urged that the actions leading to sale, including the 13(2) notice, moratorium requests, and deferral of action, were not properly executed and that the High Court rightly quashed the sale.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (12)

Case NameCitationTreatmentExplanation
ITC Limited v. Blue Coast Hotels Limited and Others(2018) 15 SCC 99PositiveUsed to support the principle that Section 13(3A) is mandatory; the Court nevertheless held that waiver/estoppel can override strict compliance in light of attendant circumstances.
Blue Coast Hotels Limited v. IFCI Limited and Another2016 SCC OnLine Bom 2663Mentioned OnlyCited to discuss absence of a rigid sixty-day mandate for filing representations under Section 13(3A); not adopted as controlling law in full due to subsequent reliance on waiver/estoppel.
Authorized Officer, Indian Overseas Bank and Another v. Ashok Saw Mill(2009) 8 SCC 366PositiveCited to support the proposition that actions under SARFAESI can be challenged under Section 17 and that rights can be appealed within the statutory framework.
Blue Coast Hotels Limited v. IFCI Limited and Another(201 ) 2?Positive(Same case as above; included for context in the development of the 13(3A) discussion.)
Goverment of the Province of Madras – AL AR. Vellayan Chettiar (Decd.) v. Government of the Province of Madras(unknown)Mentioned OnlyCited in context of waiver / estoppel principles; no direct adoption of a specific tenet.
S. Raghbir Singh Gill v. S. Gurcharan Singh Tohra and Others(1980) Supp SCC 53PositiveCited for waiver/estoppel principles and the general principle that statutory rights may be waived in private/public policy contexts.
Krishan Lal v. State of Jammu & Kashmir(1994) 4 SCC 422PositiveCited to illustrate the waiver/estoppel framework and the discretionary relief doctrine.
Martin & Harris Ltd. v. VIth Additional Distt. Judge and Others(1998) 1 SCC 732PositiveUsed in the discussion on waivers and estoppel in statutory rights.
Bank of India and Others v. O.P. Swarnakar and Others(2003) 2 SCC 721PositiveCited in the context of waiver/estoppel and relief molding.
Shyam(1971) 1 SCC 619PositiveCited for general principle that a party can waive a private/privilege of private capacity; supports waiver doctrine.
Beg Raj Singh v State of U.P. and Others(2003) 1 SCC 726PositiveCited for the proposition that waiver/estoppel can bar a statutory remedy in appropriate circumstances.
Rameshwar and Others v. Jot Ram and Others(1976) 1 SCC 194PositiveCited in the context of limitations and continuation of cause of action in SARFAESI proceedings.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•6,787 words•~31 min read

In The Court Record

Arce Polymers Private Limited v. M/s Alphine Pharmaceuticals Private Limited and Others

**REPORTABLE** ## **IN THE SUPREME COURT OF INDIA** ## **CIVIL APPELLATE JURISDICTION** ## **CIVIL APPEAL NO. 7372 OF 2021** **(ARISING OUT OF SPECIAL LEAVE PETITION (CIVIL) NO. 5051 OF 2020)** ARCE POLYMERS PRIVATE LIMITED ..... APPELLANT(S) VERSUS M/S. ALPHINE PHARMACEUTICALS PRIVATE LIMITED AND OTHERS ..... RESPONDENT(S) ## **W I T H** ## **CIVIL APPEAL NO. 7373 OF 2021** **(ARISING OUT OF SPECIAL LEAVE PETITION (CIVIL) NO. 6178 OF 2020)** ## **J U D G M E N T** ## **SANJIV KHANNA, J.** Leave granted. 2. The impugned judgment dated 24[th] January 2020 passed by the Division Bench of the High Court of Telangana at Hyderabad allows Writ Petition No. 13936 of 2019 preferred by M/s. Alphine Pharmaceuticals Private Limited and Bejjenki Bhaskara Chary (collectively referred to as the ‘Borrower’) and thereby sets aside and quashes the proceedings initiated by M/s. Andhra Bank (the Signature Not Verified Digitally signed by Anita Malhotra Date: 2021.12.03 17:25:58 IST Reason: _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 1 of 28**_ ‘Bank’, for short) for sale of the mortgaged asset, namely, plot No. 66/B-1, Phase-I, IDA Jeedimetla, Quthbullapur Mandal, Medchal Malkajgiri District, Hyderabad, Telangana (hereinafter referred to as the ‘Subject Property’) as being in violation of the provisions of the Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 and the Security Interest (Enforcement) Rules, 2002 (hereinafter referred to as the ‘SARFAESI Act’ and the ‘Rules’ respectively). 3. Aggrieved by the said judgment, the present appeals have been preferred by M/s. Arce Polymers Private Limited, (for convenience, we would refer M/s. Arce Polymers Private Limited as the ‘Second Purchaser’) who had purchased the property from the original auction purchaser, namely, Basa Chandramouli; and by the Bank. 4. The impugned judgment had formulated five points for consideration, which read: “(a) Whether the 1[st] respondent Bank had an obligation to comply with Section 13(3A) of the Act and give a response to the petitioners’ representation dt.01.11.2016 and whether the Debts Recovery Tribunal was correct in holding that there was no such obligation on the part of the 1[st] respondent Bank? (b) Whether any of the reliefs claimed in the O.A. by the petitioners is barred by limitation? _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 2 of 28**_ (c) Whether it was proper for the 1[st] respondent Bank not to separately value the machinery in the subject property when it obtained the valuation before it sold the property to the 2[nd] respondent? (d) Whether it was incumbent on the part of the 1[st] respondent to obtain a fresh valuation certificate dt.19.02.2018 in view of the long gap between the valuation report and the e-auction sale held on 11.09.2018? (e) Whether the petitioners are entitled to any relief?” The impugned judgment decided the first four points in favour of the Borrower and restored the physical possession of the Subject Property to the Borrower _inter alia_ recording that the secured creditor, namely the Bank, was at liberty to act, in order to recover its dues from the Borrower, strictly in accordance with the SARFAESI Act and the Rules. 5. Before we delve into the legal aspects and issues with reference to the above quoted five questions, we would like to refer to the facts of the case as we believe that they portray a different story and this factual background has not been duly reckoned and considered in the impugned judgment. We, therefore, proceed to narrate the facts in some detail: - (i) The Borrower was sanctioned working capital limit of Rs.35,00,000/- (Rupees thirty five lakhs only) and granted term loan of Rs.1,52,00,000/- (Rupees one crore fifty two _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 3 of 28**_ lakhs only) by the Bank in March 2015 with moratorium period of six months to enable the Borrower to purchase M/s. Alphine Pharmaceuticals Pvt. Ltd. from its erstwhile promoters. - (ii) In accordance with the terms of the loan, the Subject Property was mortgaged by the Borrower with the Bank. - (iii) The Borrower failed to repay the loan as per the payment schedule as a result of which, on 31[st] July 2016, the loans were declared as a Non-Performing Asset. - (iv) On 1[st] August 2016, the Bank issued notice to the Borrower under Section 13(2) of the SARFAESI Act calling upon the Borrower to discharge its liability within sixty days failing which the Bank would be entitled to exercise all or any of its rights under sub-section (4) to Section 13 of the SARFAESI Act. - (v) The Borrower neither made any payment nor responded by way of a reply within sixty days of the notice under Section 13(2) of the SARFAESI Act. - (vi) On 1[st] November 2016 and 6[th] November 2016 the Borrower wrote letter(s) in which, while accepting defaults and nonpayment, it had enlisted reasons for not being able to adhere to the payment schedule, namely, delay in commencement _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 4 of 28**_ of production of pharmaceuticals due to the requirement of renewal of licenses from different statutory bodies, and policy changes by M/s. Singareni Collieries Company Limited, their prime customer, disqualifying them from participating in the tenders. The bank was requested to grant further moratorium of twelve months. - (vii) The letters dated 1[st] and 6[th] November 2016, do not profess being a reply or objection to the notice dated 1[st] August 2016 issued by the Bank under Section 13(2) of the SARFAESI Act. - (viii) On 7[th] November 2016, the Bank informed the Zonal Manager of the Recovery Management Department, in _re_ the proposal submitted by the Borrower for restructuring the term loan, extension of the moratorium period and induction of fresh capital, with the following stipulations: “Sub : NPA A/c M/s Alphine Pharmaceuticals Pvt Limited – Request for restructuring of Term Loan and extension of moratorium period. Ref : Company Letter dated 06.11.2016. With reference to the above, we inform you that the company was sanctioned OCC limit of Rs. 35.00 lakhs and Term Loan limit of Rs.152.00 lakhs vide SME.Sn.Lr.No.2265/52/SMECPC/ 2236/S-197 dated 10.03.15 to acquire the unit. The unit was acquired by the company on 19.06.2015 and due to change in the constitution of the company from proprietary to Private Limited company, the company had to get all the approvals / licenses modified in the name of the company which had taken _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 5 of 28**_ time and production was started in the month of Sept. 2015. The limits are fallen due for renewal on 09.03.16. As per sanction gestation for the Term Loan was 6 months from the date of disbursement and accordingly repayment was started in the month of Dec 2015. Meanwhile M/s Singareni Collieries Company Ltd which is to place orders to erst while firm M/s Alphine Pharmaceuticals stopped placing orders to the company stating that the entity should have Rs.10.00 crore turnover as per the change in their procurement policy which disqualified the company in participation of tenders. This hampered the company orders and they had to look for other clients for new business. During the period the company had serviced the interest and instalment payments by which they had liquidity problem in the working capital and could not execute orders obtained from the new clients. The account was identified as NPA on 31.07.2016 and we have issued Notice under SARFAESI Notice under Section 13(2) was issued on 01.08.2016 and the acknowledgement of notice from the borrower and guarantors has been received on 12.08.16. The company earlier informed that they are entering MOU with an investor group for infusion of Rs.1.00 crore and the liquidity problem will be solved and they can revive the production activity at higher level. It is informed that the investors have invested only Rs.15.00 lakhs from which the company had remitted Rs.10.00 lakhs into OCC account and utilized Rs.5.00 lakhs for payment of salary and other dues. The investors have opted out without investing further amount. The present position of limits and liabilities is as under: **==> picture [377 x 89] intentionally omitted <==** **----- Start of picture text -----**<br> 14. BALANCE OUTSTANDING: (Liability with our bank) (Rs. in Crs)<br>LIMIT OUTSTANDING BALANCE<br>RECOVERY<br>FACILITY SANCTIONED<br>REAL SHADOW PROVISION AFTER NPA<br>Term Loan<br>1.52 1.39 1.50 Nil<br>021230100009479<br>OCC<br>0.35 0.40 0.41 0.10<br>021213100000502<br>Total 1.87 1.79 1.91 0.10<br>**----- End of picture text -----**<br> Company informed that though they are running the unit with low capacity production i.e. Rs. 3 to 4 lakhs per month the fixed expenses and interest charges are amounting to nearly Rs.5.00 _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 6 of 28**_ lakhs per month by which they are incurring losses. Company vide their letter dated 06.11.16 informed that they will to remit Rs.6.00 lakhs by 15[th] of this month in the OCC account to bring the liability in the OCC account within the limit and infuse Rs.60.00 lakhs within three months by which the Working capital liquidity problem will be solved and can execute the orders on hand / to be procured. It is also informed that they have approached M/s Singareni Collieries Company Ltd authorities to reconsider the eligibility of the company in participation of tenders as the erst while firm M/s Alphine Pharmaceuticals was acquired by them and converted to limited company. Now the company is requesting us to restructure the Term Loan limit with further gestation of 12 months and is planning to remit Rs.6.00 lakhs by 15[th] of this month in the OCC account to bring the liability in the OCC account within the limit and permit them to operate the OCC account. We have vide our letter dated 06.11.16 advised the company to submit Detailed Project Report / Techno Economic Viability Report with regard to restructuring of the loan and extension of moratorium period along with ABA as on 31.03.16 and Provisional Balance Sheet as on a latest date at the earliest, to assess the viability of the project and advise to remit Rs.6.00 lakhs into OCC account as promised. On receipt of the Detailed Project Report / Techno Economic Viability report, we shall take up the matter with our Zonal office. In view of the above and considering that the production of the unit is continuing at a minimum level, which can be increased to the full extent by infusing Rs.60.00 lakhs within three months by the company as promised and payment of Rs.10.74 lakhs into OCC account after NPA date, we recommend for deferring action under SARFAESI till the TEV Report is appraised and viability of the company is established by our approved agency and allow operations in the OCC account after bringing the liability to within the limit in OCC account.” Thus, the action under the SARFAESI Act was recommended to be deferred to enable the Borrower to submit detailed project/viability report, bring OCC account _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 7 of 28**_ within limit and increase production to the fullest extent by infusing Rs.60,00,000/- (Rupees sixty lakhs only) towards the working capital. The Borrower was to be allowed operations in their bank account after bringing the OCC liability within the prescribed limit. - (ix) The third party investor brought in Rs.15,00,000/- (Rupees fifteen lakhs only), out of which Rs.5,00,000/- (Rupees five lakhs only) was utilised for payment of salary and Rs.10,00,000/- (Rupees ten lakhs only) was remitted to the OCC account. Thereafter, the third party investor opted out and did not bring in the balance Rs. 45,00,000/- (Rupees forty five lakhs only). Detailed project/viability report was not submitted. - (x) On failure of the Borrower to translate its promise into action, the Bank issued notice under Section 13(4) of the SARFAESI Act read with Rule 8(1) of the Rules and took symbolic possession of the Subject Property _vide_ possession notice dated 3[rd] March 2017. - (xi) Thenceforth, the Bank filed Crl.M.P.No.343/2017 under Section 14 of the SARFAESI Act before the Chief Metropolitan Magistrate, Cyberabad, Ranga Reddy District and took physical possession of the secured asset on 3[rd] _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 8 of 28**_ May 2017 through Advocate Commissioner appointed by the court. - (xii) On 1[st] June 2017, the Bank issued notice under Rule 6(2) read with Rule 8(6) of the Rules informing the Borrower that the Subject Property was being put to auction with a reserve price of Rs.2,78,10,000/- (Rupees two crores seventy eight lakhs ten thousand only). The Borrower was given an option to repay the amount due along with interest so that the auction could be halted. - (xiii) The Borrower did not respond to this letter. It neither protested nor made any payment. - (xiv) The auction held on 6[th] October 2017 did not fructify as no bidder came forward to purchase the Subject Property. - (xv) On 20[th] October 2017, 8[th] November 2017 and 17[th] November 2017, the Borrower made representations for regularisation of the account. The last letter dated 17[th] November 2017 refers to meetings with senior officers of the Bank on 30[th] October 2017, 6[th] November 2017 and 8[th] November 2017 and that the Bank had agreed to restructure the Borrower’s account upon furnishing of additional collateral security of Rs.50,00,000/- (Rupees fifty lakhs only) for which the Borrower had been advised to furnish _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 9 of 28**_ documentation. To establish _bona fides_ , the Borrower had furnished an undated cheque of Rs.25,00,000/- (Rupees twenty five lakhs only) which could be presented upon approval of the restructuring proposal. The Borrower would furnish techno economic viability study-cum-restructuring proposal. The Bank on consideration of the restructuring proposal would allow the Borrower to reopen the factory. The Bank was requested to handover keys to enable the Borrower to assess the stock and build the unit for commercial production. (xvi) The Bank _vide_ letter dated 30[th] November 2017, recapped the Borrower the need to submit the restructuring proposal in the prescribed format along with the details of additional collateral security as well as legal opinion and valuation report. The documentation, it was stated, was not received. Also, visit of the Bank officers to the proposed collateral security property had not been arranged. The Borrower was informed that the Bank would take a call on Borrower’s request for opening the factory, which was in the Bank’s possession, after receipt of the aforementioned papers etc. along with realisation of cheque presented by the Borrower. The Borrower was advised to comply with the terms _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 10 of 28**_ immediately to enable the Bank to consider the proposal for restructuring, with a warning that in case of delay, the Bank would set into motion the proceedings under the SARFAESI Act which had been temporarily halted. - (xvii) On 18[th] December 2017, the Borrower again wrote seeking regularisation of the account and waiver of penal charges levied in terms of the loan agreement. A restructuring proposal was submitted as per the format with a request that the same should be considered and the Borrower be permitted to bring the unit to commercial operation as a onetime opportunity. - (xviii) As per the Bank there was non-compliance and failure. No payment was made. In these circumstances, the Bank made second and third attempts to sell the Subject Property by way of auctions held on 28[th] March 2018 and 14[th] June 2018. Both the attempts failed as no bidder came forward to participate in the auction. - (xix) Importantly, the attempts to sell the Subject Property remained unchallenged by the Borrower. - (xx) On 20[th] August 2018, the Bank issued the fourth notice for auction, regarding which the Borrower was duly informed. Given the fact that in the earlier auctions no bidder had _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 11 of 28**_ participated, the Bank reduced the reserve price from Rs.2,78,10,000/- (Rupees two crores seventy eight lakhs ten thousand only) to Rs.2,60,00,000/- (Rupees two crores sixty lakhs only). Yet again, the Borrower did not respond. It neither questioned the sale notice, the reduction in reserve price, nor made any payment. - (xxi) In the auction held on 11[th] September 2018, two bidders had participated and the Subject Property was sold at a bid price of Rs.2,91,20,000/- (Rupees two crores ninety one lakhs twenty thousand only) to Basa Chandramouli. On 14[th] September 2018, sale confirmation letter was issued to Basa Chandramouli. On 27[th] September 2018, after Basa Chandramouli had made the total payment, the sale certificate was issued. 6. In October 2018, the Borrower approached and filed a petition before the Debts Recovery Tribunal challenging the enforcement proceedings in respect of the Subject Property including all steps taken right from issue of notice under Section 13(2) of the SARFAESI Act. 7. The Debts Recovery Tribunal, Hyderabad by its judgment dated 1[st] July 2019 dismissed the Borrower’s application holding that the _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 12 of 28**_ Bank had followed the prescribed procedure under the SARFAESI Act and the sale was valid. 8. Thereupon, the Borrower had preferred a writ petition before the High Court of Telangana. The Borrower did not go in appeal to the Debts Recovery Appellate Tribunal, Kolkata as it was not functioning due to want of members. In the meanwhile, on 8[th] July 2019, the auction purchaser Basa Chandramouli sold the Subject Property to the Second Purchaser, the appellant herein. Before this sale, Basa Chandramouli had already sold machinery and equipment. It is the case of the Second Purchaser that he had no information or knowledge about the writ petition preferred by the Borrower on 6[th] July 2019. The Second Purchaser had acquired the plot with the bare structure, which the Second Purchaser claims was in a dilapidated condition. The Second Purchaser had an existing industrial establishment on a plot of land adjacent to the Subject Property. After the purchase, the structure standing on the Subject Property was demolished and the Second Purchaser has constructed a new structure, as per the Second Purchaser at the cost of over Rs.70,00,000 (Rupees seventy lakhs only). 9. After a detailed perusal of the facts in the present matter, we would like to refer to the findings of the High Court and our findings on _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 13 of 28**_ the legal issues with reference to the points formulated by the High Court, as set out in paragraph 4 above. For convenience, we would like to simultaneously deal with points (a) and (b). 10. In brief, the impugned judgment upholds the contention on violation of Section 13(3A) of the SARFAESI Act relying on the judgment of this Court in _**ITC Limited**_ v. _**Blue Coast Hotels Limited and Others**_ ,[1] that compliance with Section 13(3A) being mandatory, the Bank had failed to respond with reasons to the representations made by the Borrower dated 1[st] /6[th] November 2016. The stance of the Bank that these representations were not in response to the notice under Section 13(2) dated 1[st] August 2016 was rejected as the Borrower through representations had pleaded difficulties being faced by it in repaying the loan instalments and sought extension of moratorium/more time for repayment. The High Court held that it was not necessary for the Borrower to specifically mention that the representations were in response to the notice under Section 13(2) of the SARFAESI Act. Further, relying upon the decision of the Bombay High Court in _**Blue Coast Hotels Limited**_ v. _**IFCI Limited and Another**_ ,[2] which decision on challenge became the subject matter of the appeal > 1 (2018) 15 SCC 99 > 2 2016 SCC OnLine Bom 2663 _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 14 of 28**_ and decision of this Court in _**ITC Ltd.**_ (supra), the High Court held that there is no specific provision or mandate under Section 13(3A) of the SARFAESI Act that the representation of the Borrower to the demand notice under Section 13(2) should be filed within a period of sixty days from the date of notice. The impugned judgment also refers to the letter dated 7[th] November 2016 to observe that the Chief Manager of the Bank had recommended deferring of action under the SARFAESI Act with the intent that the unit running in the Subject Property should be granted benefit of deferment of action. The Bank had proceeded to issue possession notice on 3[rd] March 2017 under Section 13(4) of the SARFAESI Act long after receipt of the representations dated 1[st] /6[th] November 2016, but without making any reference to the aforesaid representation. Accordingly, on the first point, the High Court concluded that there had been a violation by the Bank of its mandatory statutory duty under Section 13(3A) of the SARFAESI Act. 11. On the second question, reference was made to Section 17(1) of the SARFAESI Act which deals with the right of appeal by a party aggrieved by the measures referred to in sub-section (4) to Section 13. Relying on the decision of this Court in _**Authorised Officer, Indian Overseas Bank and Another**_ v. _**Ashok Saw Mill**_ ,[3] it was 3 (2009) 8 SCC 366 _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 15 of 28**_ held that the series of steps from the date of action by the secured creditor under Section 13(2) of the SARFAESI Act up to the date of auction and sale confirmation can be challenged by the Borrower when it challenges the measures referred to in the sub-section (4) to Section 13 under Section 17 of the SARFAESI Act. In this view of the matter, the High Court with respect to the second issue held that though the O.A. was filed on 1[st] October 2018, the Borrower can challenge the possession notice issued on 3[rd] March 2017, taking of symbolic possession, taking of physical possession in May 2017, the sale notice issued on 2[nd] July 2018, and the sale certificate dated 27[th] September 2018 as they all form part of the same cause of action. Consequently, it was observed that challenge to the actions/measures prior to 2[nd] July 2018 would not be barred by limitation. 12. In view of the factual matrix of the present case, which has been set out in detail above and the aspect of waiver and estoppel discussed subsequently, it is not necessary for us to examine the question of violation of Section 13(3A) of the SARFAESI Act and also whether the cause of action from the date of issue of notice under Section 13(2) of the SARFAESI Act till the issuance of the sale certificate is a continuing cause of action. Suffice it would be _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 16 of 28**_ to observe that in the case of _**ITC Ltd.**_ (supra), this Court in spite of holding that there was violation of Section 13(3A) of the SARFAESI Act and consequently the notice of possession under Section 13(4) was vitiated, had allowed the appeal in view of the attendant circumstances set out in sub-paragraphs of paragraph 30 on the ground that the debtor, post the notice under Section 13(4) of the SARFAESI Act, had given proposals with assurances, letter of undertaking for repayment of the mortgage debt, pursuant to which time was granted and consequently the sale notice was deferred. Only when payments were not made as promised that the creditor had proceeded to recover the dues. Paragraph 31 and 32 of the decision in _**ITC Ltd.**_ (supra) record as under: “31. From the above, it is clear that the creditor was induced by the debtor not to take action against them through assurances and promises. The creditor appeared to have entered into negotiations for the settlement of the dues and even accepted cheques in repayment much after the notice [Dated 26-3-2013] under Section 13(2) and after the debtor's letter of representation [Dated 27-5-2013] . Many opportunities were granted by the creditor to the debtor to repay the debt which were all met by proposals for extension of time. Eventually, the debtor even executed “A Letter of Undertaking [On 25-11-2013] ” acknowledging the right of IFCI to sell the assets in the case of default. 32. In these circumstances, we have no doubt that the failure to furnish a reply to the representation is not of much significance since we are satisfied that the creditor has undoubtedly considered the representation and the proposal for repayment made therein and has _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 17 of 28**_ in fact granted sufficient opportunity and time to the debtor to repay the debt without any avail. Therefore, in the fact and circumstances of this case, we are of the view that the debtor is not entitled to the discretionary relief under Article 226 of the Constitution which is indeed an equitable relief.” 13. We would like to elaborate on the aforesaid principle as the dictum, as declared in _**ITC Ltd.**_ (supra), will equally apply to proceedings before the Debts Recovery Tribunal and the Appellate Tribunal under the SARFAESI Act. The principle applied is that of waiver and estoppel. 14. Waiver is an intentional relinquishment of a known right. Waiver applies when a party knows the material facts and is cognizant of the legal rights in that matter, and yet for some consideration consciously abandons the existing legal right, advantage, benefit, claim or privilege. Waiver can be contractual or by express conduct in consideration of some compromise. However, a statutory right may also be waived by implied conduct, like, by wanting to take a chance of a favourable decision. The fact that the other side has acted on it, is sufficient consideration. It is correct that waiver being an intentional relinquishment is not to be inferred by mere failure to take action, but the present case is of repeated positive acts post the notices under Sections 13(2) and (4) of the SARFAESI Act. Not only did the Borrower not question or object to the action of the _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 18 of 28**_ Bank, but it by express and deliberate conduct had asked the Bank to compromise its position and alter the contractual terms. The Borrower wrote repeated request letters for restructuring of loans, which prayers were considered by the Bank by giving indulgence, time and opportunities. The Borrower, aware and conscious of its rights, chose to abandon the statutory claim and took its chance and even procured favourable decisions. Even if we are to assume that the Borrower did not waive the remedy, its conduct had put the Bank in a position where they have lost time, and suffered on account of delay and laches, which aspects are material. Action on the Subject Property was delayed by more than a year as at the behest of the Borrower, the Bank gave them a long rope to regularise the account. To ignore the conduct of the Borrower would not be reasonable to the Bank once third party rights have been created. In this background, the principle of equitable estoppel as a rule of evidence bars the Borrower from complaining of violation. 15. The question of waiver of mandatory requirement of a statute was considered by this Court in depth in _**Commissioner of Customs, Mumbai**_ v. _**Virgo Steels, Bombay and Another**_ ,[4] by referring to a catena of judgments beginning from the judgment of the Privy - 4 (2002) 4 SCC 316 _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 19 of 28**_ Council in _**AL.AR. Vellayan Chettiar (Decd.) and Others**_ v. _**Government of the Province of Madras, Through the Collector**_ _**of Ramnad at Madura, and Another[5]**_ wherein it was held that though notice under Section 80 of the Code of Civil Procedure, 1908 is mandatory, the suit would not be bad if the non-issuance of notice is waived by the party for whose benefit the provision has been enacted. Similarly, in _**S. Raghbir Singh Gill**_ v. _**S. Gurcharan**_ _**Singh Tohra and Others**_ ,[6] the argument that the requirement of Section 94 of the Representation of Peoples Act, 1951 cannot be waived was rejected observing that a privilege conferred or a right created by a statute, if it is solely for the benefit of a party, the said party can waive it. However, where a provision enacted is founded on public policy, the courts would be slow to apply the doctrine of waiver. The doctrine applies in the first situation as the right to waive inheres in the concept of personal privilege and right. Reference in this regard can be also made to the ratio in _**Krishan Lal**_ v. _**State of J&K[7]**_ and _**Martin & Harris Ltd.**_ v. _**VIth Additional Distt. Judge and Others**_ .[8] In _**Bank of India and Others**_ v. _**O.P. Swarnakar and Others**_ ,[9] and in _**Shri Lachoo Mal**_ v. _**Shri Radhey**_ 5 AIR 1947 PC 197 - 6 (1980) Supp SCC 53 > 7 (1994) 4 SCC 422 8 (1998) 1 SCC 732 9 (2003) 2 SCC 721 _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 20 of 28**_ _**Shyam**_ ,[10] this Court elucidated the general principle that everyone has a right to waive and to agree to renounce an advantage of law or rule made solely for the benefit and protection of the person in private capacity. If a party gives up the advantage that could be taken of a particular position in law, it cannot later be permitted to change and turn around so as to avail of that advantage. However, this rule will not apply when there is a prohibition against contracting out of the statute, which prohibition would have its consequences or in case the waiver would be contrary to public policy. Further, a person cannot waive a right of a third person. 16. This principle has been subsequently followed in _**Pravesh Kumar Sachdeva**_ v. _**State of Uttar Pradesh and Others**_ ,[11] to hold that waiver is abandonment of a right which normally everybody is at liberty to waive. Waiver is nothing unless it amounts to release, _albeit_ it can be adduced from acquiescence or may be implied. The essence of waiver is an estoppel and they are questions of conduct and, therefore, necessarily determined on the facts of each case. As a rule and judicial policy, the courts of law do not allow a litigant to take inconsistent position to gain advantage through the aid of judicial proceedings. > 10 (1971) 1 SCC 619 11 (2018) 10 SCC 628 _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 21 of 28**_ 17. In consideration of the facts of the present case, another important aspect to be duly noted is the power of the courts/judicial authorities to mould relief. While holding that the general approach is that the claimant who succeeds in establishing the unlawfulness of administrative action is entitled to grant of remedial order, the general proposition does not undermine the discretion which the courts or judicial authorities have in assessing “what is fair and just to do in the particular case – to withhold the remedy altogether or to mould the remedy by grant of a declaration rather than a more coercive quashing, prohibiting or mandatory order or injunction which may have been sought.”[12] Relief may be granted in respect of one aspect and not others. The general approach, therefore, is that a complainant who succeeds in establishing unlawfulness of an action is entitled to a remedial order, but the court has discretion in the sense of determining what is fair and just to do in a particular case. This discretionary aspect of grant of relief even with reference to post litigation events has been highlighted in _**Beg Raj Singh**_ v. _**State of U.P. and Others**_ ,[13] wherein it was held as under: “ 7. Having heard the learned counsel for the petitioner, as also the learned counsel for the State and the private > 12 _De Smith’s Judicial Review_ , Eigth Edition (2018), at page 1006 13 (2003) 1 SCC 726 _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 22 of 28**_ respondent, we are satisfied that the petition deserves to be allowed. The ordinary rule of litigation is that the rights of the parties stand crystallized on the date of commencement of litigation and the right to relief should be decided by reference to the date on which the petitioner entered the portals of the court. A petitioner, though entitled to relief in law, may yet be denied relief in equity because of subsequent or intervening events i.e. the events between the commencement of litigation and the date of decision. The relief to which the petitioner is held entitled may have been rendered redundant by lapse of time or may have been rendered incapable of being granted by change in law. There may be other circumstances which render it inequitable to grant the petitioner any relief over the respondents because of the balance tilting against the petitioner on weighing inequities pitted against equities on the date of judgment. Third-party interests may have been created or allowing relief to the claimant may result in unjust enrichment on account of events happening in-between. Else the relief may not be denied solely on account of time lost in prosecuting proceedings in judicial or quasijudicial forum and for no fault of the petitioner. A plaintiff or petitioner having been found entitled to a right to relief, the court would as an ordinary rule try to place the successful party in the same position in which he would have been if the wrong complained against would not have been done to him...” Reference in this regard can be also made to an earlier ## decision of this Court in _**Rameshwar and Others**_ v. _**Jot Ram and Another.[14]**_ 18. In the present case, it is clear from a bare perusal of the letter dated 7[th] November 2016 sent by the Bank to its Zonal Manager - that the Bank actively considered the Borrower’s request for extension of the moratorium period. The Borrower did not submit 14 (1976) 1 SCC 194 _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 23 of 28**_ the viability report and failed to bring in Rs. 45,00,000/- (Rupees forty five lakhs only). Post this default also there were negotiations with assurances and promises by the Borrower. Displaying forbearance, the Bank granted indulgence as action under the SARFAESI Act was deferred for nearly one year from 7[th] November 2016 till 6[th] October 2017. Thereafter, negotiations were held on 30[th] October 2017, 6[th] November 2017 and 8[th] November 2017. The email dated 30[th] November 2017 addressed by the Bank to the Borrower highlights the dilatory and tricky approach of the Borrower as it had failed to submit details of the additional collateral security offered along with the legal opinion and the engineer’s valuation report. Even visit to the proposed collateral security property was not arranged. The Borrower again tried its luck and submitted a restructuring proposal _vide_ communication dated 18[th] December 2017, but this did not fructify into an acceptable settlement. The Bank having lost faith could not rely on the Borrower. Only thereafter, the Bank proceeded with the auctions under the SARFAESI Act on 28[th] March 2018 and 14[th] June 2018. The Borrower then kept silent. As the earlier auctions failed, the Bank issued notice dated 20[th] August 2018 informing the Borrower about the fourth auction to be held on 11[th] September 2018 at a reduced reserve price. The Borrower challenged the _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 24 of 28**_ actions taken by the Bank after the Subject Property had changed hands and third party interests had been created. Taking into consideration the entire facts of the case, which perspicuously reflect disingenuous conduct on part of the Borrower to gain indulgence, unfulfilled assurances and promises, their unwillingness to pay, and in light of the law laid down by this Court, we are of the view that the Borrower has waived and is estopped from challenging violation of Section 13(3A) of the SARFAESI Act and hence, the first issue is decided in favour of the Bank. Given the aforesaid position, we do not think we are required to examine the second point, i.e. whether in an application under Section 17 of the SARFAESI Act, which can be filed when a Borrower is aggrieved by any of the measures referred to in sub-section (4) to Section 13 within forty five days from the date such measures are taken, the Borrower can challenge other measures, steps and procedures which preceded the ultimate sale even if barred by the limitation period of forty five days. 19. With regard to the third issue of the valuation of the machinery and the adverse finding of the High Court on the question of valuation before the machinery was sold in auction, it is to be noticed that the valuation report which has been placed on record is dated 19[th] _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 25 of 28**_ February 2018, values the land, the building and the machinery separately. The machinery has been valued with specific reference to as many as 55 separate items under the Heading ‘Description of Machinery’. The valuation report itself has not been disputed or challenged. We do not agree with the High Court that the machinery should have been separately auctioned or sold. This would be putting fetters and restrictions on the Bank by baring the Bank from selling the machinery along with the building and the land. Prejudice and loss caused to the Borrower is not shown and established. Auction sale as confirmed was at a price higher than the fair market valuation of the land, the building and the machinery. Whether or not the price of the machinery should be accounted for the purpose of payment of stamp duty on a composite sale wherein the land, the building and the machinery located in the building are sold, would not be of any relevance and importance as the issue in question does not concern payment of stamp duty and the principles applicable. On the other hand, the law recognises that the lender knows its interests and how to secure best value of the property given the fact that the mortgaged property had to be sold for recovery of the debts due and payable to the Bank. _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 26 of 28**_ 20. The fourth issue relating to the date of the valuation report also does not help the Borrower. The valuation certificate or report is dated 19[th] February 2018. As held above, attempts to sell the property were made thereafter on 28[th] March 2018 and 14[th] June 2018 but without success as there were no bidders. Accordingly, it was decided to reduce the reserve price from Rs.2,78,10,000/(Rupees two crores seventy eight lakhs ten thousand only) to Rs.2,60,00,000/- (Rupees two crores sixty lakhs only). However, in the fourth auction the successful bid given by Basa Chandramouli was for Rs.2,91,20,000/- (Rupees two crores ninety one lakhs twenty thousand only), which is much higher than the reserve price of Rs.2,60,00,000/- (Rupees two crores sixty lakhs only) or the fair market value of Rs.2,73,80,000/- (Rupees two crores seventy three lakhs eighty thousand only) in terms of the valuation report. 21. Resultantly, we allow the present appeals and set aside the impugned order dated 24[th] January 2020 passed in Writ Petition No. 13936 of 2019. The writ petition would be treated as dismissed. The order passed by the Debts Recovery Tribunal dated 1[st] July 2019 upholding the procedure and sale of the Subject Property under the SARFAESI Act is upheld. _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 27 of 28**_ However, in the facts of the present case, there would be no order as to costs. **......................................J. (L. NAGESWARA RAO) ......................................J. (SANJIV KHANNA) ......................................J. (B.R. GAVAI)** **NEW DELHI; DECEMBER 03, 2021.** _**Civil Appeal a/o. of SLP (C) No. 5051 of 2020 & Anr.**_ _**Page 28 of 28**_
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.