Case Synopsis & Summary

This Supreme Court judgment arises from two Civil Appeals (Civil Appeal Nos. 6372-6373 of 2025) in which Arabian Exports Private Limited challenged orders of the Bombay High Court dismissing Section 11 applications to appoint arbitrators under the Arbitration and Conciliation Act, 1996. The insured had taken two policies—Standard Fire and Special Perils Policy and a Fire Declaration Policy—covering a meat processing and cold storage unit at Taloja. In 2005, unprecedented floods damaged the factory, leading to substantial claims. After protracted delays and mounting financial pressure, the appellant signed an undated discharge voucher for Rs. 1.88 crore in December 2008, in full and final settlement, and encashed the accompanying cheque. In 2009 the appellant invoked arbitration and nominated a sole arbitrator; the respondent refused, contending accord and satisfaction barred arbitration. The High Court dismissed the petitions, holding no arbitrable dispute existed. The Supreme Court, by a two-judge Division Bench, held that the mere signing of a discharge voucher does not automatically extinguish the right to arbitration, especially where the dispute relates to the quantum under the policy and the arbitration clause remains intact. The Court emphasized Kompetenz-Kompetenz, and, while acknowledging earlier decisions (Nathani Steels, Boghara Polyfab), proceeded to determine that the dispute should be referred to arbitration. The appeals were allowed, and a retired Bombay High Court judge was appointed as sole arbitrator; there was no order on costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Abhay S. Oka, J.
  • Ujjal Bhuyan, J.
Judgment Date
2025-05-06
Court Decision / Holding
Appeals allowed. The High Court’s order dismissing the Section 11 applications is set aside. The Court holds that the existence of an arbitration agreement survives and that disputes arising under the contract and relating to the quantum may still be arbitrable. The Court appoints Justice (Retd.) Suresh Chandrakant Gupte as the sole arbitrator and directs the parties to report to him by 15.05.2025. There is no order as to costs.
Final Disposition
Appeals allowed; High Court order set aside; arbitration to proceed; retired judge Suresh Chandrakant Gupte appointed as sole arbitrator; no costs.

Parties to the Case

Appellants / Petitioners

  • Arabian Exports Private Limited

Respondents

  • National Insurance Company Ltd.

Legal Representation & Advocates

Counsels for Petitioners

  • • Kavin Gulati, Senior Advocate

Counsels for Respondents

  • • Dr. Manish Singhvi, Senior Counsel

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 (Section 11)Arbitration and Conciliation Act, 1996 (Section 11(6))Arbitration and Conciliation Act, 1996 (Section 11(6A))Arbitration and Conciliation Act, 1996Indian Contract Act, 1872, Section 63

Legal Doctrines & Maxims

  • Kompetenz-Kompetenz
  • Accord and Satisfaction
  • Economic duress
  • Arbitration agreement survives after accord and satisfaction
  • When in doubt, refer (Vidya Drolia principle)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the discharge voucher signed under extreme financial duress and after prolonged delay in settlement cannot bar arbitration. It argues that the two insurance policies carried an identically worded arbitration clause and that the 2009 IRDA circular clarifies that execution of discharge vouchers does not foreclose rights to seek higher compensation. It relies on National Insurance Co. Ltd. v. Boghara Polyfab Pvt. Ltd., Nathani Steels, and later jurisprudence (Duro Felguera, Vidya Drolia, Oriental Insurance, SBI General) to contend that the mere signing of a discharge voucher is not conclusive proof that an arbitrable dispute has ceased, especially where the dispute relates to quantum and the arbitration clause persists under the contract. The argument also emphasizes economic duress and the need to examine the existence of an arbitration agreement at the Section 11 stage, consistent with Kompetenz-Kompetenz.

Contentions of Respondents

The respondent contends that the appellant accepted the offer in full and final settlement, creating accord and satisfaction that extinguishes the claim and precludes arbitration. It cites Nathani Steels to contend that amicable settlements bar further arbitration unless such settlement is set aside in proper proceedings. It argues that the discharge relates to one policy, and there is no demonstrable fraud, coercion, or undue influence; the arbitration clause cannot be invoked where there is a valid settlement. It maintains that the High Court correctly rejected appointment of an arbitrator based on the discharge and that the dispute was extinguished by accord and satisfaction.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (8)

Case NameCitationTreatmentExplanation
National Insurance Co. Ltd. v. Boghara Polyfab Pvt. Ltd.(2009) 1 SCC 267PositiveUsed to support that accord and satisfaction does not automatically bar arbitration and that arbitral processes may proceed despite final settlements.
Nathani Steels Ltd. v. Associated Constructions(1995) Supp (3) SCC 324DistinguishedCited as a controlling authority in older context but distinguished for 1996 Act; court clarifies scope under 1996 Act.
Duro Felguera, S.A. v. Gangavaram Port Ltd.(2017) 3 SCC 392PositiveAffirms limited court intervention and focus on existence of arbitration agreement post amendment.
Vidya Drolia v. Durga Trading Corporation(2021) 2 SCC 1PositiveUnderscores arbitrability principles and need to refer unless prima facie dead wood.
Oriental Insurance Co. Ltd. v. Dicitex Furnishing Ltd.(2020) 4 SCC 621PositiveSupports that coercion or economic duress can be considered in Section 11 inquiries and that referral remains possible.
SBI General Insurance Co. Ltd. v. Krish Spinning(2024) SCC OnLine SC 1754PositiveAffirms that accord and satisfaction does not automatically extinguish arbitration rights in the presence of an arbitration clause.
Aslam Ismail Khan Deshmukh v. Asap Fluids Pvt. Ltd.—PositiveReiterates that at Section 11 stage, existence of arbitration agreement is the sole issue, not merits.
Associated Construction v. Pawanhans Helicopters Ltd.—PositiveCited for economic duress context supporting arbitration despite disputes arising from settlements.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,870 words•~23 min read

In The Court Record

Arabian Exports Private Limited v. National Insurance Company Ltd.

2025 INSC 630 **REPORTABLE** **==> picture [68 x 68] intentionally omitted <==** ## **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** **- CIVIL APPEAL NOS. 6372 6373 OF 2025 - (@ SPECIAL LEAVE PETITION (CIVIL) NOS. 16907 16908 OF 2012)** **ARABIAN EXPORTS PRIVATE LIMITED APPELLANT(S)** **VERSUS** **NATIONAL INSURANCE COMPANY LTD. RESPONDENT(S) J U D G M E N T** ## **UJJAL BHUYAN, J.** Leave granted. 2. These appeals by special leave are directed against the order dated 02.12.2011 passed by the High Court of Judicature at Bombay in Arbitration Application Nos. 186-187 of 2011. Signature Not Verified Digitally signed by ASHISH KONDLE Date: 2025.05.06 15:01:57 IST Reason: 3. In this case, delay was condoned and notice was issued on 11.05.2012. 1 4. The short issue for consideration in these appeals is whether a dispute raised by an insured after giving a full and final discharge voucher to the insurer can be referred to arbitration. 5. As we shall deliberate upon, this issue is no longer _res integra._ 6. However, for a proper perspective, relevant facts may be briefly noted. 7. Appellant is a company incorporated under the provisions of the Companies Act, 1956. It is engaged in the business of exporting meat and meat products. For this purpose, appellant used to process the meat and store the same at its factory premises at Taloja in the State of Maharashtra. 8. On 08.10.2004, appellant took a comprehensive Standard Fire and Special Perils Policy bearing No. 260301/11/04/3100585 from the respondent towards insuring the meat processing and cold storage unit as also the building, plant and machinery, furniture, fixtures and fittings 2 in the Taloja plant for an amount of Rs.3,28,55,000.00 which was for the period from 09.10.2004 to 03.10.2005. 9. Appellant also took a Fire Declaration Policy bearing No. 260301/11/04/3301441 insuring all its stock-in-trade and finished products stored in the cold storage facility at its factory premises at Taloja. This policy was for an amount of Rs.5,76,85,000.00 and covered the period from 15.03.2005 to 15.03.2006. 10. It is stated that appellant had paid the insurance premium towards both the insurance policies. 11. On 26.07.2005, there was very heavy and unprecedented rainfall in several parts of Maharashtra including at Taloja. Because of such unprecedented and very heavy rainfall, the factory premises at Taloja was completely flooded and got submerged under water for several hours. It is stated that all communication lines had broken down and there were no means of communication to and fro the Taloja plant leaving the incident unnoticed till 28.07.2005. It is further stated that appellant had suffered severe loss due to 3 the damage caused to the factory building, plant and machinery, furniture, fixtures and accessories as well as the stock lying at the Taloja plant. 12. Appellant had informed the respondent on 29.07.2005 regarding the damage suffered at the Taloja plant and requested the respondent to depute a surveyor to assess the damage. Appellant claimed loss and damage to the plant and machinery etc. under the Standard Fire and Special Perils also claimed loss and damage _qua_ the stock in cold storage under the Fire Declaration Policy for an amount of Rs. 5,15,62,527.00 13. It is stated that on 28.07.2005, Dr. A.S. Patil (it is not stated who he was or who had authorized him) had inspected the factory premises at Taloja and after inspecting the stock-in-trade certified that the same was unfit for human consumption. On 29.11.2005, Chempro Inspection Private Limited, the surveyor appointed by the respondent, conducted 4 a survey at the Taloja plant. In its report dated 29.11.2005, the surveyor acknowledged the loss suffered by the appellant. 14. Unfortunately, despite repeated requests and reminders by the appellant, respondent failed to settle the claims of the appellant. 15. After a considerable delay, appellant was presented with an undated and standardized voucher/advance receipt for a sum of Rs. 1,88,14,146.00 sometime in December, 2008. 16. Due to financial strain caused by the delay on the part of the respondent to settle the claims coupled with the pressure exerted by various bankers and creditors, appellant was left with no other option but to sign and submit to the respondent the said undated and standardized voucher/advance receipt on 12.12.2008 for an amount of Rs. 1,88,14,146.00 being claimed under the Fire Declaration Policy. Pursuant thereto, appellant received the cheque issued by the respondent for a sum of Rs. 1,88,14,146.00 on 19.12.2008. 5 17. It may be mentioned that the two insurance policies had identically worded arbitration clause. 18. On 24.12.2008, appellant while reserving its right to invoke the aforesaid arbitration clause called upon the respondent to settle and pay the balance amount of Rs. 3,83,55,408.00 being the difference between the claim lodged by the appellant and the amount paid by the respondent. Appellant also sought for a copy of the surveyor’s report. 19. By letter dated 21.03.2009, respondent provided the appellant with a copy of the surveyor's report giving details of the respondent’s assessment of the appellant's claim. 20. Though the appellant made repeated attempts to resolve the matter but the respondent did not cooperate. Consequently, appellant addressed letter dated 17.04.2009 to the respondent invoking the arbitration clause contained in the insurance policy and at the same time nominated Mr. Ramakant W. Gudal, a retired Joint Commissioner and Controlling Authority, Food and Drugs Administration, 6 Maharashtra as the sole arbitrator. It is stated that this letter was hand delivered to the respondent on 20.04.2009. 21. Respondent issued letter dated 18.05.2009 to the appellant through its lawyer denying its liability and refusing to accept arbitration and failed to nominate an arbitrator in terms of Clause 30 of the insurance policy. Respondent _vide_ further letter dated 12.10.2009 stated that it was not agreeable to refer the matter to arbitration. 22. Thereafter, appellant filed applications under Section 11 of the Arbitration and Conciliation Act, 1996 (briefly, ‘the 1996 Act’ hereinafter) before the High Court of Judicature at Bombay for appointment of an arbitrator to arbitrate the claims of the appellant. Thus two arbitration applications were filed in respect of the two policies which were registered as arbitration application Nos. 186 of 2011 and 187 of 2011. 23. Learned Single Judge of the High Court of Judicature at Bombay (briefly, ‘the High Court’ hereinafter) observed that the amount paid by the respondent was 7 accepted by the appellant in full and final settlement of the claim. It was accepted without any demur and after encashing the cheque, the dispute was raised on 24.12.2008. Therefore, _vide_ the impugned order dated 02.12.2011, learned Single Judge held that no arbitrator could be appointed in view of acceptance of the amount in full and final settlement. Both the arbitration applications were accordingly dismissed. 24. Mr. Kavin Gulati, learned senior counsel for the appellant has drawn our attention to the relevant facts and submits that learned Single Judge had rejected the applications under Section 11 of the 1996 Act on the ground that the discharge voucher signed by the appellant in favour of the respondent constituted full accord and satisfaction having accepted the amount paid by the respondent without demur. 24.1. Learned senior counsel submits that in the present case, ‘accord and satisfaction’ is not voluntary but under compulsion. Appellant was under financial duress on account of the huge loss caused by the rainwater and flooding; additionally, there was long delay on the part of the 8 respondent in processing the claim. That apart, appellant was pressurized by the banks and creditors for repayment of credit. In such circumstances, appellant had no other option but to sign the undated and standardized voucher/advance receipt for a wholly inadequate amount of Rs. 1,88,14,146.00 against the _bona fide_ claim of Rs. 5,71,69,554.00. In this connection, learned senior counsel has drawn the attention of the Court to the letter dated 24.12.2008 and the pleadings in the applications under Section 11 of the 1996 Act which reads thus: The fact that the voucher relating to payment of our claim under the Standard Fire and Special Perils Policy refers to article/property “stolen” clearly establishes the complete non application of mind and disregard by your company to our repeated representations and the nature of our loss. Looking to the financial strain cast on us by virtue of the willful delay on the part of your organization in settlement at our claims coupled with the pressure exerted by our bankers and creditors, we were left with no option but to sign and submit to you the said undated and standardized voucher on December 9 12[th ] 2008, for the grossly inadequate amount of Rs. 1,88,14,146.00. 24.2. Learned senior counsel submits that the case of the appellant is squarely covered by the decision of this Court in _National Insurance Company Limited Vs. Boghara Polyfab Private Limited[1] ._ He has also distinguished the decision of this Court in _Nathani Steels Ltd. Vs. Associated Constructions[2]_ relied upon by the respondent _._ He submits that in _Nathani Steels_ (supra), there were negotiations between the parties culminating in a voluntary negotiated settlement of all pending disputes. Contract was thus discharged by ‘accord and satisfaction’. This is not so in the present case. He further submits that issue in question is covered by the decision of this Court in _Boghara Polyfab_ (supra). 24.3. In any event, the discharge voucher was in relation to only one policy i.e. Fire Declaration Policy. It did not cover the Standard Fire and Special Perils Policy. Learned senior counsel has referred to and relied upon the circular dated > 1 (2009) 1 SCC 267 2 (1995) Supp (3) SCC 324 10 24.09.2015 issued by the Insurance Regulatory and Development Authority of India clarifying that execution of vouchers as full and final discharge did not foreclose the rights of the policy holders to seek higher compensation before any judicial fora or any other fora established by law. This has been endorsed and reiterated _vide_ subsequent circular dated 07.06.2016 issued by the Insurance Regulatory and Developmentary Authority of India. He, therefore, submits that learned Single Judge erred while rejecting the applications for appointment of arbitrator. Therefore, the impugned order is liable to be set aside. 25. _Per contra,_ Dr. Manish Singhvi, learned senior counsel for the respondent submits that a three Judge Bench of this Court in _Nathani Steels_ (supra) has clearly held that once a dispute or difference between the parties arising out of a contract is amicably settled by the parties, unless such settlement is set aside in proper proceedings, it is not open to one of the parties to the settlement to further seek arbitration. 11 According to him, this case is squarely covered by _Nathani Steels Ltd._ (supra). 25.1. Learned senior counsel submits that _Nathani Steels Ltd._ (supra) is a decision of a three Judge Bench whereas _Boghara Polyfab_ (supra) is by a two Judge Bench. Therefore, the conflict between _Nathani Steels_ (supra) and _Boghara Polyfab_ (supra) needs to be resolved by referring the matter to a larger Bench. 25.2. He submits that in so far the present case is concerned, there is no question of any fraud. In fact, there was no pleading and argument as regards fraud. There is also no pleading as to duress or coercion. Mere citation of the expressions fraud, duress or coercion will not make it a case of fraud, duress or coercion. There has to be adequate pleadings. That apart, appellant has not produced any document to even _prima-facie_ show that the appellant was being pressurized by the respondent to enter into a settlement. 25.3. In so far letter of the appellant dated 24.12.2008 is concerned, learned senior counsel submits that the said letter 12 mentioned about the policies but did not contain any statement to the effect that the settlement was only for one policy. Respondent had processed the claim of the appellant on the basis of the report of the surveyor. The figure of Rs. 1.88 crores was not an imaginary or illusory figure but based on the assessment of the surveyor. 25.4. Dr. Singhvi also argued an alternative prayer. If the Court is of the opinion that the High Court had not considered the aspect of duress and coercion, then the matter may be referred back to the High Court. In that event the High Court would consider the aspect of duress and coercion. Otherwise, no case for arbitration is made out. Therefore, he seeks dismissal of the appeals. 26. Submissions made by learned counsel for the parties have received the due consideration of the Court. 27. The two insurance policies contain an identically worded arbitration clause which read as follows: 13. If any dispute or difference shall arise as to the quantum to be paid under this policy liability 13 being otherwise admitted such difference shall independently of all other questions be referred to the decision of sole arbitrator to be appointed in writing by the parties to or if they cannot agree upon a single arbitrator within 30 days of any party invoking arbitration, the same shall be referred to a panel of three arbitrators, comprising of two arbitrators, one to be appointed by each of the parties to the dispute/difference and the third arbitrator to be appointed by such two arbitrators and arbitration shall be conducted under and in accordance with the provisions of the Arbitration and Conciliation Act, 1996. It is clearly agreed and understood that no difference or dispute shall be referable to arbitration as hereinbefore provided, if the Company has disputed or not accepted liability under or in respect of this policy. It is hereby expressly stipulated and declared that it shall be a condition precedent to any right of action or suit upon this policy that the award by such arbitrator/arbitrators of the amount of the loss or damages shall be first obtained. 28. In its letter dated 24.12.2008 addressed to the respondent, appellant stated that after an inordinate delay of 14 42 months, a grossly inadequate amount of Rs.1,88,14,146.00 was offered by the respondent in response to the _bona fide_ and genuine claim of the appellant for the aggregate sum of Rs.5,71,69,554.00. Appellant further stated that because of the financial strain caused due to the delay on the part of the respondent in settling its claims coupled with the pressure exerted by its bankers and creditors, appellant was left with no other option but to sign and submit to the respondent the undated and standardized voucher forwarded by it on 12.12.2008 for Rs.1,88,14,146.00. Appellant further stated that it received a cheque for the aforesaid amount on 19.12.2008. Referring to the arbitral clause in the insurance policies, appellant stated that there is an arbitrable dispute in the context of the quantum of claim, the liability being admitted by the respondent. Appellant called upon the respondent to pay the balance amount of Rs.3,83,55,408.00 with interest at the rate of 18 percent. Respondent was put to notice that if the said amount was not paid, appellant would invoke the arbitration clause not only claiming the balance amount but also damages and compensation. 15 29. Finally, appellant through its advocate issued notice to the respondent on 17.04.2009 invoking the arbitration clause and nominated Mr. Ramakant W. Gudal, retired Joint Commissioner and Controlling Authority, Food & Drugs Administration, Maharashtra as the Sole Arbitrator. Respondent was called upon to concur with the said nomination or alternatively to nominate its own arbitrator in which event the two nominated arbitrators would appoint a presiding arbitrator. 30. However, respondent informed the appellant _vide_ letter dated 12.10.2009 that it was not agreeable to refer the matter to arbitration as the appellant had accepted the amount offered in full and final settlement which amounted to ‘accord and settlement’. 31. It was thereafter that appellant approached the High Court by filing applications under Section 11 of the 1996 Act. The relevant pleadings have already been extracted and noted. 16 32. Learned Single Judge _vide_ the impugned order observed that the amount offered by the respondent was accepted by the appellant in full and final settlement of the claim. The acceptance was not without prejudice to the rights and contentions of the appellant or reserving the right to challenge the amount that was being paid. The payment was made on 19.12.2008. It was accepted without any demur and after encashing the cheque the dispute was raised on 24.12.2008. Learned Single Judge referred to one of his previous orders where he had taken a view that if such a receipt is issued which accepts the payment in full and final settlement, then a dispute cannot be raised. He therefore held that no arbitrator can be appointed in view of acceptance of the amount in full and final settlement. 33. In _Nathani Steels_ (supra), a three-Judge Bench of this Court opined that once the parties reach a settlement in respect of any dispute or difference arising under a contract and that dispute or difference is amicably settled by way of a final settlement by and between the parties, unless that 17 settlement is set aside in proper proceedings it cannot lie in the mouth of one of the parties to the settlement to spurn it on the ground that it was a mistake and thereafter proceed to invoke the arbitration clause. 33.1 Of course the Bench held that unless the settlement is set aside in proper proceedings, it would not be open to one of the parties to the settlement to invoke arbitration. But at the same time, it needs to be pointed out that this view was taken in the context of an amicable settlement arrived at between the parties in the presence of a third party and reduced to writing. If there is an amicable settlement of the dispute between the parties unless such settlement is set aside in proper proceedings, it would not be open to one of the parties to invoke arbitration. Therefore, the crucial expression here is ‘amicable settlement’. 34. This decision was explained by this Court in _Boghara Polyfab_ (supra). A two-Judge Bench of this Court noted that in _Nathani Steels_ (supra) this Court on examination of the facts of that case was satisfied that there were 18 negotiations leading to voluntary settlement between the parties in all pending disputes. Thus the contract was discharged by ‘accord and satisfaction’. The Bench categorized such claims under two categories. In the first category there would be cases where there is bilateral negotiated settlement of pending disputes, such settlement having been reduced to writing either in the presence of witnesses or otherwise. _Nathani Steels_ (supra) falls in this category. In the second category of cases, there would be ‘no dues/claims certificate’ or ‘full and final settlement discharge vouchers’ insisted upon and taken, either in a printed format or otherwise, as a condition precedent for release of the admitted dues. In the latter group of cases, the disputes are arbitrable. Mere execution of a full and final settlement receipt or a discharge voucher cannot be a bar to arbitration even when validity thereof is challenged by the claimant on the ground of fraud, coercion or undue influence. The Bench further distinguished _Nathani Steels_ (supra) by clarifying that the observations made that unless the settlement is set aside in proper proceedings, it would not be open to a party to the settlement to invoke 19 arbitration was with reference to a plea of ‘mistake’ taken by the claimant and not with reference to allegations of fraud, undue influence or coercion. Further, the said decision was rendered in the context of the provisions of the Arbitration Act, 1940. The perspective of the 1996 Act is different from the Arbitration Act, 1940. 35. In _Duro Felguera, S.A. Vs. Gangavaram Port Ltd._[3] , a two-Judge Bench of this Court examined Section 11(6) of the 1996 Act as well as Section 11(6A) inserted in the 1996 Act by way of the Arbitration and Conciliation (Amendment) Act 2015 and concluded that courts should look into only one aspect: existence of an arbitration agreement. Already the width of jurisdiction under Section 11(6) of the 1996 Act was considerably wide following judicial dicta but post the aforesaid amendment, all that the courts need to see is whether an arbitration agreement exists – nothing more, nothing less. The legislative policy and purpose is essentially to minimize the court’s intervention at the stage of appointing the arbitrator. > 3 (2017) 9 SCC 729 20 36. A three-Judge Bench of this Court in _Vidya Drolia Vs. Durga Trading Corporation_[4] held that subject matter _qua_ arbitrability cannot be decided at the stage of Sections 8 or 11 of the 1996 Act unless it is a clear case of dead wood. The court under Sections 8 and 11 has to refer a matter to arbitration or to appoint an arbitrator, as the case may be, unless a party has established a _prima facie_ case of nonexistence of a valid arbitration agreement. The court should refer a matter if the validity of the arbitration agreement cannot be determined on a _prima facie_ basis. The rule should be: when in doubt, do refer. 37. In _Oriental Insurance Company Ltd. Vs. Dicitex Furnishing Ltd_ .[5] , a two-Judge Bench of this Court considered the objection of the insurer about maintainability of the application under Section 11(6) of the 1996 Act in which the High Court had appointed an arbitrator. The objection was that the claimant had signed the discharge voucher and had accepted the amount offered, thus signifying ‘accord and > 4 (2021) 2 SCC 1 5 (2020) 4 SCC 621 21 satisfaction’ which in turn meant that there was no arbitrable dispute. This Court rejected the objection of the insurer and held thus: **26.** An overall reading of Dicitex's application [under Section 11(6)] clearly shows that its grievance with respect to the involuntary nature of the discharge voucher was articulated. It cannot be disputed that several letters — spanning over two years—stating that it was facing financial crisis on account of the delay in settling the claim, were addressed to the appellant. This Court is conscious of the fact that an application under Section 11(6) is in the form of a pleading which merely seeks an order of the court, for appointment of an arbitrator. It cannot be conclusive of the pleas or contentions that the claimant or the party concerned can take in the arbitral proceedings. At this stage, therefore, the court which is required to ensure that an arbitrable dispute exists, has to be prima facie convinced about the genuineness or credibility of the plea of coercion; it cannot be too particular about the nature of the plea, which necessarily has to be made and established in the substantive (read : arbitration) proceeding. If the court were to take a contrary approach and 22 minutely examine the plea and judge its credibility or reasonableness, there would be a danger of its denying a forum to the applicant altogether, because rejection of the application would render the finding (about the finality of the discharge and its effect as satisfaction) final, thus, precluding the applicant of its right even to approach a civil court. There are decisions of this Court ( _Associated Construction_ v. _Pawanhans Helicopters Ltd._ and _Boghara Polyfab)_ which upheld the concept of economic duress. Having regard to the facts and circumstances, this Court is of the opinion that the reasoning in the impugned judgment cannot be faulted. 37.1. Thus, this Court held that at the stage of Section 11(6) of the 1996 Act, court is required to ensure that an arbitrable dispute exist; it has to be _prima facie_ convinced about the genuineness or credibility of the plea of coercion; it cannot be too particular about the nature of the plea which naturally has to be made and established in the arbitral proceeding. If the courts were to take a contrary approach, there would be the danger of denying a forum to the claimant altogether. This Court upheld the concept of economic duress and held that notwithstanding signing of discharge voucher 23 and accepting the amount offered, the dispute is still arbitrable. Pleading in a Section 11(6) application cannot be conclusive whether there is fraud, coercion or undue influence or otherwise. 38. A three-Judge Bench of this Court in _SBI General Insurance Co. Ltd. Vs. Krish Spinning_[6] held that even if the contracting parties in pursuance to a settlement agree to discharge each other of any obligations arising under the contract it is does not _ipso facto_ mean that the arbitration agreement too would come to an end, unless the parties expressly agree to do the same. The Bench also explained the concept of ‘accord and satisfaction’ under Section 63 of the Indian Contract Act, 1872. Any dispute pertaining to the full and final settlement itself by necessary implication being a dispute arising out of or in relation to or under the substantive contract would not be precluded from reference to arbitration as the arbitration agreement contained in the original contract continues to be in existence even after the parties have > 6 2024 SCC OnLine SC 1754 24 ## discharged the original contract by ‘accord and satisfaction’. This Court held thus: 53. Thus, even if the contracting parties, in pursuance of a settlement, agree to discharge each other of any obligations arising under the contract, this does not _ipso facto_ mean that the arbitration agreement too would come to an end, unless the parties expressly agree to do the same. The intention of the parties in discharging a contract by “accord and satisfaction” is to relieve each other of the existing or any new obligations under the contract. Such a discharge of obligations under the substantive contract cannot be construed to mean that the parties also intended to relieve each other of their obligation to settle any dispute pertaining to the original contract through arbitration. 54. Although ordinarily no arbitrable disputes may subsist after execution of a full and final settlement, yet any dispute pertaining to the full and final settlement itself, by necessary implication being a dispute arising out of or in relation to or under the substantive contract, would not be precluded from reference to arbitration as the arbitration agreement contained in the original contract continues to be 25 in existence even after the parties have discharged the original contract by “accord and satisfaction”. 39. Again, in the case of _Aslam Ismail Khan Deshmukh Vs. Asap Fluids Pvt. Ltd_ .[7] , a three-Judge Bench of this Court reiterated the above proposition and held as under: **51.** It is now well-settled law that, at the stage of Section 11 application, the referral courts need only to examine whether the arbitration agreement exists - nothing more, nothing less. This approach upholds the intention of the parties, at the time of entering into the agreement, to refer all disputes arising between themselves to arbitration. However, some parties might take undue advantage of such a limited scope of judicial interference of the referral courts and force other parties to the agreement into participating in a time-consuming and costly arbitration process. This is especially possible in instances, including but not limited to, where the claimant canvasses either _ex facie_ time-barred claims or claims which have been discharged through “accord and satisfaction”, or cases where the impleadment of a non-signatory to the arbitration agreement is sought, etc. 7 (2025) 1 SCC 502 26 **52.** In order to balance such a limited scope of judicial interference with the interests of the parties who might be constrained to participate in the arbitration proceedings, the arbitral tribunal may direct that the costs of the arbitration shall be borne by the party which the tribunal ultimately finds to have abused the process of law and caused unnecessary harassment to the other party to the arbitration 40. Thus, the doctrine of _Kompetenz-Kompetenz_ is now firmly embedded in the arbitration jurisprudence in India. This doctrine is based on the principle that an arbitral tribunal is competent to rule on its own jurisdiction including on the issue of existence or validity of an arbitration agreement. The object is to minimize judicial intervention which is an acknowledgment of the concept of party autonomy. 41. In view of the clear legal proposition, we have no hesitation in holding that the High Court was wrong in rejecting the Section 11(6) applications of the appellant. The question as to whether the appellant was compelled to by the respondent out of economic duress and whether 27 notwithstanding receipt of Rs.1,88,14,146.00 as against the claim of Rs. 5,71,69,554.00 the claim to arbitration is sustainable or not are clearly within the domain of the arbitral tribunal. 42. That being the position, the impugned order of the High Court dated 02.12.2011 is set aside. 43. Having regard to the long lapse of time we are of the view that it would be appropriate for this Court to appoint a retired Judge of the Bombay High Court as the sole arbitrator. Accordingly, we appoint Justice (Retd.) Suresh Chandrakant Gupte (Mobile No.- 9821010104) as the sole arbitrator. Parties to report to the sole arbitrator by 15.05.2025. 44. Appeals are accordingly allowed. However, there shall be no order as to costs. **………………………………J. [ABHAY S. OKA]** **.……………………………J. [UJJAL BHUYAN]** **NEW DELHI; MAY 06, 2025.** 28
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.