Anjali Rathi and Others v. Today Homes & Infrastructure Pvt. Ltd. and Ors.
Case Synopsis & Summary
The petitioners are home buyers in a group housing project (Canary Greens, Sector 73, Gurgaon) who contracted for delivery of apartments within 36 months but allege abandonment of the project by the developer. The petitioners approached the National Consumer Dispute Redressal Commission (NCDRC), which on 12 July 2018 directed the developer to refund principal amounts with interest and costs. Execution proceedings ensued under COPRA (COPRA: Consumer Protection Act, 1986) Sections 25 and 27; the NCDRC’s order was challenged in High Court, which stayed the order, and later, further proceedings explored settlements. In October–November 2019, the first respondent faced insolvency actions: the National Company Law Tribunal (NCLT) admitted a Section 9 petition (IBC 2016) and initiated the Corporate Insolvency Resolution Process (CIRP) with a moratorium under Section 14. A consortium of home buyers proposed a Resolution Plan; the Committee of Creditors (CoC) approved it by a large majority, and the RP filed for approval under Section 31(1) of the IBC, with pending objections. The petitioners contend that promoters should be held personally liable to honor settlements by attaching personal properties, relying on the Plan’s clause 10(g). The Court, while noting the Plan approval process is ongoing, declined to issue a directive to attach personal properties at this stage, explaining that consequences would flow only after Plan approval. It directed the NCLT to decide the Plan’s approval expeditiously (within six weeks) and clarified moratorium scope (corporate debtor only). The matter is disposed with liberty to pursue remedies after the Adjudicating Authority’s decision; pending applications are disposed.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- Dhananjaya Y. Chandrachud
- Vikram Nath
- Hima Kohli
- Judgment Date
- 2021-09-08
- Court Decision / Holding
- 1. The Court held that the Resolution Plan approved by the CoC and now pending before the Adjudicating Authority under Section 31(1) should be expeditiously decided, preferably within six weeks. Objections to the Plan must be placed before the Adjudicating Authority; 2. It declined to direct the attachment of promoters’ personal properties at this stage, noting that such consequences would follow only after Plan approval; 3. The moratorium under Section 14 IBC continues to operate against the Corporate Debtor, but petitioners may pursue remedies against the promoters in relation to pre-CIRP settlements, not grounded on the pending Plan; 4. SLPs and Civil Appeals disposed of; petitioners are free to pursue remedies under the law after the Adjudicating Authority’s decision on the Plan; pending applications disposed.
- Final Disposition
- SLPs and Civil Appeals disposed of; liberty to petitioners to pursue remedies after the Adjudicating Authority’s decision on the Section 31(1) approval; pending applications disposed.
Parties to the Case
Appellants / Petitioners
- Anjali Rathi and Others
Respondents
- Today Homes & Infrastructure Pvt. Ltd.
- Ors.
Legal Representation & Advocates
Counsels for Petitioners
- • Pawanshree Agarwal
- • Himanshu Satija
- • E. C. Agrawala
- • Manoj Yadav
- • Sushil Kaushik
- • Ranbir Singh Yadav
- • Mrs. Shally Bhasin
- • Ayush Sharma
- • Aditya Parolia
Counsels for Respondents
- • G Piyush Singh
- • Nithin Chandran
- • Akshay Srivastava
- • Ms. Aditi Sinha
- • Rajesh Kumar
- • Gaurav Goel
Provisions of Law Cited
Legal Doctrines & Maxims
- Moratorium under Section 14 IBC applies to the corporate debtor, not to promoters/management; proceedings against promoters may proceed.
- Resolution Plan pending cannot justify attachment of personal properties; consequences flow only after Adjudicating Authority approves the Plan.
- P Mohanraj v. Shah Bros. Ispat (P) Ltd. (2021) 6 SCC 258 — moratorium applies to corporate debtor; promoters may be pursued for pre-CIRP settlements; supported the Court’s reasoning.
Submissions & Arguments
Contentions of Appellants / Petitioners
The petitioners urged that the promoters be attached and held personally liable to honor settlements, relying on paragraph 10(g) of the approved Resolution Plan. They argued that the moratorium under Section 14 does not bar actions against the promoters and that the personal assets of the promoters should be attached now to enforce settlements, especially given the NCDRC order and the ongoing settlements with the Court.
Contentions of Respondents
The respondents argued that the Resolution Plan is still pending approval under Section 31(1) of the IBC; no directive to attach promoters’ personal properties should be issued at this stage; the moratorium bars actions only against the corporate debtor; the appropriate remedy lies after the Adjudicating Authority approves the Plan.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (2)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| P. Mohanraj v. Shah Bros. Ispat (P) Ltd. | (2021) 6 SCC 258 | Positive | Cited for the proposition that moratorium under Section 14 applies to the corporate debtor but does not bar actions against promoters; supports the observation that promoters may be pursued for their pre-CIRP commitments. |
| Aneeta Hada v. Godfather Travels & Tours (P) Ltd. | (2012) 3 SCC (Civ) 350 | Positive | Cited to contextualize moratorium implications and the limitations of the moratorium with respect to non-debtor entities/persons; used to frame the permissible scope of action against directors/promoters. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Anjali Rathi and Others v. Today Homes & Infrastructure Pvt. Ltd. and Ors.
Related Decisions & Precedents from Supreme Court of India (2021)
HARI OM @ HERO v. STATE OF U.P.
This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.
INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL
This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.
Hasmat Ali v. Amina Bibi & ORS.
This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.
Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.
This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.