ALL SIKKIM YOUTH ASSOCIATION & ANR. v. H.R. SUBBA & ORS.

Case / Petition Number:
Civil Appeal No. 1834 of 2002
Neutral Citation:[2010] 13 (ADDL.) S.C.R. 345

Case Synopsis & Summary

This is a Public Interest Litigation filed in the High Court of Sikkim by the All Sikkim Youth Association (and an additional petitioner) alleging grave irregularities in the Public Works Department (Roads and Bridges) of the Government of Sikkim. The petition relied on news reports and a Finance Department report suggesting a large financial liability (initially over Rs. 60 crores, later reduced to Rs. 40 crores) and claimed that about Rs. 3.41 crores remained outstanding against several officials as on 29.02.2000. It was contended that no action had been taken to recover the sums due, that officers had assets disproportionate to income, and that independent investigation by CBI or CVC should be ordered, with recovery of the amounts to follow. The High Court dismissed the writ petition, holding that an investigation by CBI or CVC was unnecessary and that the inspection team appointed by the High Court had found no misappropriation and no breach of the Sikkim Financial Rules, 1979. On appeal to the Supreme Court, the Court noted that the Department had revised the Code to the Sikkim Public Works Code, 2009, introducing greater transparency. It held that there was no merit to interfere with the High Court’s decision and dismissed the appeal, leaving costs to be borne by the parties. The judgment emphasizes probity, transparency, and accountability in public finances under evolving statutory controls.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Dalveer Bhandari
Judgment Date
2010-10-08
Court Decision / Holding
Appeal dismissed. The Supreme Court upheld the High Court’s dismissal of the writ petition, found no breach of the relevant financial rules, and concluded that no interference was warranted; the matter was left to bear its own costs.
Final Disposition
Appeal dismissed; costs

Parties to the Case

Appellants / Petitioners

  • All Sikkim Youth Association & Anr.

Respondents

  • H.R. Subba and others (Officials of the Public Works Department, Roads and Bridges)
  • Government of Sikkim, Roads and Bridges Department

Legal Representation & Advocates

Counsels for Petitioners

  • • K. Swami
  • • Prabha Swami

Counsels for Respondents

  • • J.L. Gupta
  • • Harish Chandra
  • • A. Mariarputham
  • • Annam D.N. Rao
  • • Neelam Jain
  • • Shweta Verma
  • • A.K. Sharma (for P. Parmeswaran)
  • • Aruna Mathur (for Arputham, Aruna & Co.)
  • • Ashok Mathur

Provisions of Law Cited

Constitution of India, 1950 Article 226Sikkim Financial Rules, 1979Sikkim Public Works Code, 2009Article 136 of the ConstitutionArticle 14 of the ConstitutionRule 245 of the Sikkim Public Works Code, 2009

Legal Doctrines & Maxims

  • Mala fide
  • Rule of law
  • Probity and transparency in government functioning
  • Public Interest Litigation (as a doctrine/instrument)

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners contended grave irregularities in the Public Works Department (Roads and Bridges) of the State. Relying on news items and a Finance Department report, they asserted a significant financial liability and alleged misappropriation by officials (Rs. 3.41 crores outstanding as of 29.02.2000). They urged that an independent investigation by CBI or CVC be ordered and that money be recovered, arguing that public funds were being misused and that such conduct violated the rule of law and the constitutional rights of citizens. They pressed for transparency and accountability to protect developmental schemes and prevent misgovernance.

Contentions of Respondents

The respondents resisted the petition, denying misappropriation and alleging that the advances were properly accounted as temporary advances. They argued that the High Court correctly refused a CBI/CVC inquiry, and that the inspection team found no misappropriation and no breach of the Sikkim Financial Rules. They stated that the funds had been accounted for, that the advances were being reconciled, and that the writ petition was mala fide or motivated; no action for discipline or criminal prosecution was warranted. They emphasized that updated public works norms (Code 2009) promote transparency and financial probity.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,763 words•~18 min read

In The Court Record

ALL SIKKIM YOUTH ASSOCIATION & ANR. v. H.R. SUBBA & ORS.

A ## [2010] 13 (ADDL.) S.C.R. 345 ## ALL SIKKIM YOUTH ASSOCIATION & ANOTHER _v._ H.R. SUBBA & OTHERS (Civil Appeal No. 1834 of 2002) ## OCTOBER 8, 2010 B ## [DALVEER BHANDARI AND DEEPAK VERMA, JJ.) - - _Constitution of India, 1950 Article 226 Public Interest Litigation_ - _Filed on the basis of news items published in News Papers_ - _Alleging grave irregularities in Public Works_ C - _Department (Roads and Bridges) On the basis of Report of the Finance Department of the State also alleging misappropriation of public exchequer by certain officials of the_ - _Department Prayer made for direction of investigation into_ - _the case by CBI or eve High Court dismissing the petition_ D - _On appeal, held: Judgment of the High Court does not call_ - _for interference The Inspection team, on direction of the_ - _High Court did not find any misappropriation of funds No_ - _breach of Sikkim Financial Rules found Sikkim Financial Rules, 1979_ - _Sikkim Public Works Code, 2009._ E The appellant-Association filed a writ petition in public interest in the High Court. It was stated that the Public Works Department (Roads and Bridges) of Sikkim had submitted a report to the Finance Commission, showing a financial liability of more than 60 crores and after investigation into the matter by a Committee formed by the Chief Minister, the liabilities came down to 40 crores from 60 crores. It was alleged that there were grave irregularities in the Public Works Department (PWD) in repair of roads and bridges. The allegations were based on news items and articles published in various news papers. It was also alleged that on verification of cash-books and other relevant records of the PWD, Road F G H 345 346 SUPREME COURT REPORTS [2010] 13 (ADDL.) S.C.R. A and Bridges Department, it was found that a sum exceeding Rs. 3.41 crores was outstanding against certain departmental officials as on 29.2.2000. The names of the officials were mentioned in the writ petition. It was further alleged that despite the report of the Finance B Department of the State, recommending for recovery of the amount of Rs. 3.41 crores, no action was taken for the recovery and neither any criminal nor disciplinary action was taken against the erring officials; that most of the officials had acquired assets disproportionate to their c known sources of income. It was prayed that directions be issued for investigation by a competent investigating agency such as Central Bureau of Investigation (CBI) or the Central Vigilance Commission (CVC) to investigate into the acts of commission or omission of the officials mentioned in the report of the Finance Department; and 0 also for recovery of the amount. In defence of the case, it was submitted that the allegations of misappropriation against the officials was incorrect and the relief sought in that regard was misconceived, _ma/a fide_ and motivated. E The High Ccurt, dismissing the petition, held that it was not necessary to refer the matter for investigation to CBI or CVC. Therefore, the instant appeal was filed. Dismissing the appeal, the Court F HELD: In the facts of the instant case, no interference is called for. The inspection team, on the direction of the High Court, had thoroughly examined the entire matter and did not find any misappropriation of funds. Before the High Court, the Chief Secretary and the Finance G Secretary had filed affidavits and gave details of the entire expenditure of Rs.3,40,57,582/-, and liability of the only unidentified amount of Rs.32,990/- could not be established against any person. The appellants could not point out any breach of the Sikkim Financial Rules, 1979 or misappropriation of funds by the respondents. The H # ALL SIKKIM YOUTH ASSOCIATION & ANR. _v._ H.R. 347 SUBBA & ORS. **Government of Sikkim, Roads and Bridges Department** A **had revised the Code and now Sikkim Public Works Code, 2009 has been introduced, wherein greater transparency has been introduced. (Paras 24, 28, 29, 30, 32 and 33] (356-B; 355-D; 356-D-F; 357-F-G]** CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1834 of 2002. B From the Judgment & Order dated 19.10.2001 of the High Court of Sikkim at Gangtok in Civil Writ Petition No. 17 of 2001. c K. Swami, Prabha Swami for the Appellants. J.L. Gupta, Harish Chandra, A. Mariarputham, Annam D.N. Rao, Neelam Jain, Shweta Verma, A.K. Sharma (for P. Parmeswaran), Aruna Mathur (for Arputham, Aruna & Co.), 0 Ashok Mathur for the Respondents. The Judgment of the Court was delivered by **DALVEER BHANDARI, J.** 1. This appeal is directed against the judgment and order dated 19.10.2001 passed in Civil Writ Petition No. 17 of 2001 by the High Court of Sikkim at Gangtok. E 2. The All Sikkim Youth Forum, a registered body, filed a writ petition in public interest in the High Court. This appeal was based on a news item which was published in the 'Sikkim F Observer', a National Hill Weekly, from 13th to 17th November, 2000 under the title 'Transparency and Accountability-I'. In the news item it was published that according to well placed sources the Public Works Department (Roads and Bridges), Sikkim had submitted a report to the Finance Commission G showing a financial liability of more than Rs.60 crores. Sensing some foul play in the matter, the then Chief Minister of Sikkim had ordered for a thorough probe into the matter. A Committee was formed for this purpose. The Committee completed its investigation into the matter and submitted a report to the State H 348 SUPREME COURT REPORTS [2010] 13 (ADDL.) S.C.R. A Government. Surprisingly, the liabilities came down to Rs.40 crores from Rs.60 crores, showing a difference of Rs. 20 crores. 3. It was also mentioned in the writ petition that a news item was also published in another news-weekly 'Sikkimese' B in its Gangtok Edition from 22nd to 28th November, 2000. In this article it was published that the Sikkim Public Works Department had indiscriminately defied the Rules and that there had been grave irregularities by the Public Works Department in repair of roads and bridges. c 4. It was further mentioned in the writ petition that in the "Weekend Review" under the title "Finance Department stumbles upon Roads and Bridges excesses" an article was published. It was stated in the article that the report revealed D that Roads and Bridges department of Public Works Department had committed to 350 percent in excess of outlay and it would take four years to clear the dues. 5. The press reports, in general, had indicated and E suggested departure from the established norms and deviations in procedure had occurred on account of corruption. 6. The officers of the Finance and Revenue departments had been named in the writ petition. In the writ petition it was stated that the petition was not aimed at any individual or set F of persons and was not filed with any ulterior motive. The petition was genuinely filed in the larger public interest. 7. In the writ petition it was also stated that the report received by the appellants was in 5 chapters. Chapter 1 dealt G with the introduction. Chapter 2 dealt with the administrative setup of the department. Chapter 3 dealt with the liabilities projected-its general analysis. It also dealt with the South West circle comprised of the Jorethang Sub Division, the Namchi Sub Division, the Geyzing Sub Division, the Kaluk Sub division, H the Ravangala Sub Division. There was reference to the North ALL SIKKIM YOUTH ASSOCIATION & ANR. _v._ H.R. 349 SUBBA & ORS. [DALVEER BHANDARI, J.] East Circle comprising of the Singtam Sub Division, the A Mangan Sub Division, Sub Division IV, Station Sub Division and Pakyong Sub Division. Chapter 4 dealt with stores/stocks materials while Chapter 5 dealt with temporary advance. It was further stated in the writ petition that on verification of the cash book and other relevant records of the said Roads and Bridges B Department it was found that a whopping sum exceeding Rs.3.41 crores was outstanding against the following departmental officials as on 29.02.2000. |SI.<br>No.<br>1.<br>2.<br>3.<br>4.<br>5.<br>6.<br>7.|Name<br>No.|Desi-<br>gna-<br>tion|Plan<br>Non-Plan|Plan<br>Non-Plan|Total| |---|---|---|---|---|---| ||H.R. Subba|A.E.|4539373.00|3919092.00|.<br>8458465.00| ||B.K. Rai|A.E.|1318451.00|3489045.00 4807490.00|3489045.00 4807490.00| ||S.S. Subba|A.E.|3014016.00|652895.00|3666911.00| ||L.D. Lamtha A.E.|L.D. Lamtha A.E.|1435025.00|1834112.00|3269137.00| ||C.V. Basnett A.E.|C.V. Basnett A.E.|1218933.00|1321757.00|2540690.00| ||M.K. Subba|A.E.|1008192.00|1184673.00|2192865.00| ||G.Lachungpa A.E.|G.Lachungpa A.E.|304471.00|1883666.00|2188137.00| |8.|P.K. Bhujel|A.E.|1354484.00|297453.00|1651937.00| |9.|D.C. Rai|A.E.|0.00|1039577.00|1039577.00| |10.<br>11.<br>12.|10.Mohan<br>Gurung|A.E.|370634.00|475374.00|846008.00| ||11.M.B. Gurung D.E.|M.B. Gurung D.E.|325000.00|417908.00|742908.00| ||12.B.P. Khare!|A.E.|232923.00|261681.00|494604.00| |13.|B.K. TamangA.E.|A.E.|220007.00|260771.00|480778.00| |14.Tensung<br>A.E.<br>Lepcha|||12271.00<br>333820.00||346091.00| 350 SUPREME COURT REPORTS [2010] 13 (ADDL.) S.C.R. |15.|15.M.K.Pradhan A.E.|M.K.Pradhan A.E.|0.00|236802.00|236802.00<br>236802.00<br>230981.00<br>48921.00<br>215114.00<br>129492.00| |---|---|---|---|---|---| |16.|16.T.P.<br>Sangderpa|A.E.|0.00|230981.00|| |17.|17.S.Oadul|D.E.|D.E.<br>166193.00|48921.00|| |18.|18.RajuRai|A.E.|48995.00|ao497.oo|| |19.|19.S.T. Bhutia|A.E.|14720.00|104798.00|104798.00<br>119518.00| |20.|20.Yongendra<br>Sharma|A.E.|0.00|104430.00|104430.00<br>104430.00| |21.|21.RajuBasnett A.E.|Basnett A.E.|0.00|100000.00|100000.00<br>100000.00| |22.|22.L.N.Sharma|J.E.|0.00|50258.00|50258.00<br>50258.00| |23.|23.Charanjit<br>Singh|A.E.|0.00|44672.00|44672.00<br>44672.00| |24.|24.0.8.Rai|D.E.|D.E.<br>28000.00|0.00|0.00<br>28000.00| |25.|25.P.N. Sherpa|A.E.|25000.00|0.00|0.00<br>25000.00| |26.|26.G.T. Dungel A.E.|el A.E.|0.00|17515.00|17515.00<br>17515.00| |27.|27.T.P. Karki|A.E.|0.00|6672.00|6672.00<br>6672.00| |28.|28.Neeraj<br>Pradhan|A.E.|4324.00|0.00|0.00<br>4324.00| |29.|29.M.K. Mukhia A.E.|M.K. Mukhia A.E.|0.00|100.00|100.00<br>100.00| |30.|30.Unidentified|-|39264.00|12832.00|12832.00<br>52096.00| ||Grant Total||~5680276.00 18410302.00 34090578.00|5680276.00 18410302.00 34090578.00|5680276.00 18410302.00 34090578.00| H ALL SIKKIM YOUTH ASSOCIATION & ANR. _v._ H.R. 351 SUBBA & ORS. [DALVEER BHANDARI, J.] 9. The grievance of the appellants in the writ petition was A that all the officers mentioned in Chapter 5 were heading responsible posts in the Public Works Department and other Departments in tile state. No action had been taken as recommended in the report for recovery of the amounts totaling to Rs.3.41 crores approximately outstanding as on 29.2.2000. B No disciplinary proceedings had been initiated against these officials. No criminal action as to the misuse and abuse of power had been initiated. The appellants submitted that most of these officials had acquired assets disproportionate to their known sources of income and it was only by a proper c investigation by an independent investigating agency that the exact quantum of assets disproportionate to their known sources of income could be ascertained, warranting initiation of proceedings under the Prevention of Corruption Act, besides Departmental Disciplinary Proceedings. D 10. It was lastly submitted in the writ petition that the citizens of the State of Sikkim had a constitutional guarantee to be governed by the rule of law and the funds of the State should be prudently utilized according to the norms. Arbitrary, whimsical and capricious acts of high officials in the administration of the State resulting in a fraud on the State exchequer, would result in violation of their fundamental rights guaranteed under Article 14 of the Constitution. The citizens of the State of Sikkim were also entitled to a life of dignity and a loss to the State exchequer would deprive them of access to developmental programmes, welfare measures aimed at protecting their fundamental rights and other constitutional rights. E F 11. In the writ petition the appellants had also prayed that the Court may direct an investigation by a competent investigating agency such as the Central Bureau of Investigation G or the Central Vigilance Commission to investigate into the acts of commission or omission of the officials mentioned in Chapter 5 of the Report of the Finance Department, Government of Sikkim on the Public Wo.rks Department, Roads and Bridges. The appellants further prayed that appropriate H 352 SUPREME COURT REPORTS [2010] 13 (ADDL.) S.C.R. - A steps may be taken for recovery of the amount. 12. In pursuance to the notice of the High Court in the writ petition, counter affidavit was filed by the respondents, which revealed that the advances shown against each of the individual officers being respondents No. 1 to 27, as outstanding had in B fact been already utilized for the purpose for which it was advanced. It was also stated in the counter affidavit that allegation of lapse or irregularity had been categorically denied. 13. The appellants in this appeal were concerned with Chapter 5 relating to temporary advances, these respondents C had also dealt specifically with the said part of the allegation. The other allegations being of a general character had been denied. 14. In the counter affidavit it was also stated that in order to understand the matter in its proper perspective, it was 0 necessary to explain what an advance is, under the prevailing system of the department and when the advance drawn was considered adjusted. The Assistant Engineers or the Divisional Engineers in the absence of the Assistant Engineer drew money for payment of monthly wages of labour force or E supervisors who were employed throughout the year for regular maintenance of roads or for the wages of labour force and supervisors who were engaged to complete a particular project. 15. The money was drawn on the basis of acquittance roll that gives the number of labourers/supervisors, the number of F days for which the work was done and rates of wages payable to them. Money was also drawn as advance for purchase of materials immediately required for carrying out urgent works like repair of bridges which needed immediate attention and G opening of roads closed by damages that occurred during monsoon. 16. The most of the advanced amounts drawn, as explained above, was for the payment of wages of labour force and supervisors. They were considered as temporary advance H as per the prevailing system of the Department. After ALL SIKKIM YOUTH ASSOCIATION & ANR. _v._ H.R. 353 SUBBA & ORS. [DALVEER BHANDARI, J.] disbursement of the payment. to the drawees, the detailed A account along with the paid acquittance roll was submitted to the Accounts Section of the Department. The Accounts Section, on receipt of the details, examined the same and finally booked the expenditure on the proper debitable head and removed the amount from the list of advance given to the Assistant B Engineers or the Divisional Engineers. Till the expenditure was booked in the proper debitable head, the amount drawn remained to be shown as ou_tstanding against the name of the officer, even though the accounts may have been already rendered by the officer concerned. If the budgetary provision c was not available in the particular financial year, the expenditure was debited to the budgetary provision of the succeeding year and the advance shown against the name of the particular officer would remain till that time, even though he had submitted the accounts and paid acquittance roll. D 17. The reports, as extracted in the paragraph under reply, revealed that the advance money shown as outstanding as on 29.02.2000 against the names of the officers who had been impleaded as respondents No. 1 to 28 is Rs.3.41 crores. Out of the total amount of Rs.3.41 crores, the amount under Plan was Rs.1.57 crores. The bulk of this amount could not be adjusted during the financial year 1999-2000 because of the cut in the plan allocation of funds for the financial year 19992000. This· cut in the allocation was corroborated by the letter written by the then Principal Chief Engineer-cum-Secretary, Roads & Bridges on 17.03.2000 addressed to the Principal Secretary, Finance Department vide letter No. 2 [67]Gen/R&B/ 96-97/245 dated 17.03.2000. E F 18. In the case of non-plan, the budgetary provision was extremely inadequate. Bulk of this could be adjusted only after G 31.3.2000 for the same reason as in the case of plan. The road length was increasing every year. The cost of maintenance of roads had also increased. Over and above, there was unprecedented down pour during the monsoon of the year 1999. Therefore, to meet the demand for restoration works and H 354 SUPREME COURT REPORTS [2010] 13 (ADDL.) S.C.R. A maintenance works of the roads, the requirement of funds was rnuch more than the funds allocated in the year 1999-2000 i.e. Rs.s_,oo crores. B c D 19. In such circumstances, the adjustment of these advar11:es could be effected only in the year 2000-2001 that was afiter 31.03.2000 and most of the advances were adjusted after 31.3.2000, in a few cases the advances shown as unadjusted pertain:s to past years. In these cases it was found that the .officers tiad submittecl the vouchers and details of accounts and the .A.ccounts Division also had made entries in the cash book. Bu1t, in the register, where the advance was recorded, the nece$sary corrections in the entries were not made. That is why the advance shown against the officers continued to be shown as outstanding. In such cases, though there was no actual advance outstanding, the advance was shown as outstandin~1 against the officers erroneously. E 20. In .some cases the officers had submitted the vouchers and obtained receipts from the cash section. However, they remained unadjusted inadvertently. Such cases are very few and there accounts had reconciled later on after due verification. In fact, all the advances against all the respondentsofficers had been settled. F G H 21. ·.Detailed verification of the accounts and paid · cicquittance rolls were submitted by the officers concerned from time to time anc! taking into account the budgetary sanctions available in the financial year 2000-2001 etc. the advances had been, as stated above, duly booked to the relevant budget heads. It was stated that there were no outstanding advances against any officer. 22. Out of Rs.3.41 crores, only an advance of Rs.32750 [Rs.12987 under Non-plan + Rs.19763 under Plan] which could not be. assigned to anyone was indicated. As the previous advances taken by different drawees got adjusted, new advances were drawn and, therefore, at no point of time the total advance got adjusted to zero level and therefore, this ALL SIKKIM YOUTH ASSOCIATION & ANR. 1v. H.R. 355 SUBBA & ORS. [DALVEER BHANDARI, J.] amount of advance that could not be assigned to anyone A remained undetected. This amount obviously ha, d rolled over from past many years. Efforts were being made to reconcile this. The department had kept the record of tota I amount of money which was outstanding against the officers: at the end · of the every month and periodic adjustments were t ieing made B regularly. It was stated that a!I the advances a:·gainst the respondents had been accounted for. 23. In view of the above, it was submitted that the allegation that the officers concerned had misappropriated the amount or that it was to be recovered from them was incorrect and the C relief sought in this regard was misconceived, mala fide and motivated. 24. It is pertinent to mention here that before the Higt1 Court Chief Secretary and Finance Secretary had filed affidavits and 0 gave details of the entire expenditure of Rs.3,40,57,582/- and liability of the only unidentified amount of Rs.32,990/- coulld not be established against any person. 25. The High Court had carefully examined the averments made in the writ petition and the counter affidavits. The High Court, after carefully considering the affidavits of the Chief Secretary and the Finance Secretary and the report of the Inspection Committee, came to a clear conclusion that in the facts and circumstances it was not necessary to refer the matter for investigation by the Central Bureau of Investigation or Central Vigilance Commission and the writ petition filed by the appellants was dismissed by the High Court. E F 26. The appellants, aggrieved by the impugned judgment of the High Court, had approached this Court under Article 136 of the Constitution. G 27. In pursuance to the court notices counter affidavits have been filed by the respondents. The averments of the appeal had been denied in the counter affidavit. In the counter affidavits it Nas mentioned that in the instant case there was no H 356 SUPREME COURT REPORTS [2010] 13 (ADDL.) S.C.R. - A misappropriation of any funds and there was no culpable conduct on the part of any one and the writ petition was rightly dismissed by the High Court. 28. The inspection team, on the direction of the High Court, had thoroughly examined the entire matter and did not find any B misappropriation of funds. It was also stated in the counter affidavit that the enquiry by the inspection team was an independent and impartial inquiry. In the counter affidavit it was also denied that there has been any loss to the State exchequer which had deprived the appellants access to the development - C programmes, welfare measures aimed at protecting their fundamental rights of the Constitution. According to the impugned judgment the writ petition filed in the High Court by the appellant was devoid of any merit and was dismissed. The appellants being dissatisfied with the impugned judgment - D approached this Court. E 29. This Court in order to ensure probity and transparency in the functioning of the government examined the matter in great detail. We have also carefully examined the Sikkim Financial Rules, 1979. In the instant case the appellants could not point out any breach of the Sikkim Financial Rules, 1979 or misappropriation of funds by the respondents. F 30. It may be pertinent to mention here that the Government of Sikkim, Roads and Bridges Department had revised the Code and now Sikkim Public Works Code, 2009 has been introduced. 31. The relevant Rule 245 of the Sikkim .Public Works Code, 2009 reads as under: G - **"245.** The following are the important initial 'ccounts to maintain by the Assistant Engineer. **1. Cash Book:** - The Assistant Engineers/Divisional Engineers should maintain cash book in Form 1 in accordance H ALL SIKKIM YOUTH ASSOCIATION & ANR. _v._ H.R. 357 SUBBA & ORS. [DALVEER BHANDARI, J.] with the instructions contained in Chapter VI. The A Assistant Engineer should also see that the accounts of all the imprest holders are received and incorporated in the cash book before it is closed for the account month concerned. Immediately, after the cash book of a month has been closed the cash B balance i.e. report should be prepared and sent to the Division Office/circle Office. The officer should satisfy themselves before signing the cash book that the entries are corred and as a further precaution, the total of the cash column on both sides should be expressed in words in their own hand. c It is also permissible for officers to maintain two alternative cash books one being submitted in original to the Division Office/ Circle Office at the end of the month and the other being used in the following month. D **2. Temporary Advance Accounts** In case where the Assistant Engineer takes cash E from the Division Office for making payment to persons stationed elsewhere, the amount so taken out should be accounted for as a temporary advance against his name in the cash book and account should be rendered to the Division before F drawl of next temporary advance." 32. In our view, by the Sikkim Public Works Code, 2009 greater transparency has been introduced. 33. We have carefully considered the averments, submissions of the counsel appearing for the parties and the G relevant rules. In our considered opinion, no interference is called for. The appeal, being devoid of any merit, is accordingly dismissed, leaving the parties to bear their own costs. K.K.T. Appeal dismissed. H \_~
End of Judgment Record
Browse All Supreme Court of India (2010) Decisions
2010-09-24

Department of Telecommunications v. Gujarat Co-operative Milk Marketing Federation Ltd.

This Supreme Court decision concerns a billing dispute arising from two bi-monthly telephone bills totaling Rs. 4,54,652 raised against the Managing Director of the Gujarat Co-operative Milk Marketing Federation Ltd. for calls categorized as international “party” or “sex talk” calls. The respondent subscriber alleged mischarging and that calls were made from another number, prompting a complaint to the Department. Verification upheld the bills; an administrative appeal was dismissed; the matter was referred to arbitration under section 7B of the Indian Telegraph Act, 1885, following a High Court direction. The arbitrator, Vineet Bhatia, concluded the bills were proper. The respondent challenged this award by writ petition, which the High Court (Single Judge) quashed, holding that the arbitrator was junior to the appellate authority, and proceeded to find the award invalid on presumptions and inferences unsupported by evidence; a Letters Patent Appeal was dismissed. The Supreme Court reversed, holding that the High Court exceeded its judicial review scope, misapplied the standard for review of arbitral awards under section 7B, and erred in imputing bias based on rank. It affirmed that the arbitrator’s findings were grounded in the department’s records and meters, and that independence was maintained. The appeal is allowed and the writ petition dismissed, with the High Court orders set aside.

2010-11-23

BHAGWAN BUDHA PRATHMIK TECHNICAL TRAINING COLLEGE NIRMALI v. STATE OF BIHAR

This is a consolidated Supreme Court decision in Civil Appeal Nos. 9896 and 9897 of 2010 arising out of Bihar. Bhagwan Budha Prathmik Technical Training College, Nirmali, a minority Buddhist institution established in 1987, challenged Bihar’s and other authorities’ recognition/approval decisions for its teacher-training course in light of the National Council for Teacher Education Act, 1993 (NCTE Act). The central issue is whether, after the NCTE Act’s appointed day (1 July 1995), State Governments retain power to grant recognition to teacher-education institutes and whether students of unrecognized colleges may sit for qualifying examinations. The matter traces a long litigation history: initial directions in the early 1990s required the Government to decide recognition while allowing students to appear at their own risk; subsequent orders and representations culminated in a 16 March 2007 order recognizing the college from 1987-89 on the ground that inspection warranted it, followed by a 2 September 2008 order withdrawing that recognition in light of NCTE’s sole jurisdiction post-appointed day. The High Court affirmed the sequence, but this Court held that a power to issue an order includes a power to withdraw it for valid reasons, and that recognition is vested in the NCTE after the appointed day. The judgment emphasizes that the NCTE Act must be implemented with full force to protect standards in teacher education. Ultimately, the Supreme Court dismissed the appeals, modified a cost order, and held there should be no further costs in these appeals, while acknowledging the students’ plight and the need for orderly implementation of the regulatory regime.

2010-06-03

State of Punjab & ors. v. G.S. Randhawa

This Civil Appeal arises from a petition challenging a demand for additional price under the Punjab Urban Estate (Sale of Sites) Rules, 1965. The Supreme Court hears counsel for the appellant and notes that the respondent did not enter appearance. Relying on the decision in Smt. Fuljit Kaur v. State of Punjab & Ors., (2010) 7 SCR 317, the Court states that, for the reasons recorded in Civil Appeal No. 5292 of 2004 (the Fuljit Kaur decision) decided on this date, the appeal must be allowed. The High Court’s December 6, 2006 order is set aside and the Demand Notice is upheld. The appellant is entitled to recover the additional price in accordance with law. The decision clarifies that liability to pay additional price under the Punjab Urban Estate Rules can be enforced consistent with the Fuljit Kaur framework, upholding the validity of the demand and permitting recovery by the State. The judgment thus resolves the previous split on allotment price adjustments and prescribes a uniform approach for enforcing such recoveries in analogous cases going forward.

2010-07-15

Harish Singh Nagra & Ors. v. Kapil Sibal & Ors.

Mehfil-e-Wukala, a Supreme Court cultural-literal association of lawyers, published a souvenir containing messages, articles, and poems by judges and senior advocates. Kapil Sibal, a senior advocate and then a candidate for President of the Supreme Court Bar Association, sent a message criticizing the junior Bar and urging reforms, which was circulated within Mehfil’s members but not released to the press or sold publicly. Petitioners, five practicing advocates from the Punjab and Haryana High Court, filed criminal contempt proceedings under Article 215 of the Constitution alleging that Sibal conspired with others to bring the administration of justice into disrepute. The High Court transferred the case to this Court. The central issue was whether the message, read in its proper context, amounted to contempt under Section 2(c) of the Contempt of Courts Act, 1971. The Court held that the message, read in its prospective context, did not scandalize or tend to scandalize any court, nor obstruct the administration of justice; it was a fair critique aimed at improving the system. Citing P.N. Duda, Mulgaokar, Ambard, Vishwanath, and others, the Court reaffirmed that freedom of expression under Article 19(1)(a) protects fair, reasoned criticism of judgments and judicial institutions. It noted that the Times of India article excerpt misrepresented the message, but the souvenir’s limited internal distribution and the respondent’s apology supported dismissal. Accordingly, the contempt petition was dismissed and notices discharged.