Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 1969Division BenchAppeal dismissed with costs.

Abdul Rahiman Khan v. Sadasiva Tripathi

Case / Petition Number:
Civil Appeal No. 1723 of 1967
Neutral Citation:[1969] 1 SCR 352

Case Synopsis & Summary

The appellant Abdul Rahiman Khan, a building contractor in Orissa, had tenders for the Rental Housing Scheme. His tenders were accepted and he carried out part of the work, but the final contracts were not executed on behalf of the Governor. He stopped work after an injury and sought cancellation of the contract without penalty; he later sought to contest election to the State Legislative Assembly, alleging his nomination was improperly rejected. The High Court rejected his election petition, and he appealed under section 116-A of the Representation of the People Act, 1951. The Supreme Court examined whether a contract with the State, not executed with the Governor and not completed, can still disqualify a candidate from standing for election. It held that the appellant was rightly disqualified. The Court noted that the contract was not wholly performed and there was no clear mutual termination of the contract; however, letters and conduct suggested the contract continued, not cancelled, and the State treated the arrangement as subsisting in practice. It also held that even though the contract did not satisfy Article 299 of the Constitution for enforceability in civil courts, the contract arising from the acceptance of his tender could still disqualify under s.9A. Precedents Chatturbhuj Vithaldas Jasani and Laliteshwar Prasad Sahi were followed. The appeal was dismissed with costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • J. C. Shah
  • V. Bhargava
Judgment Date
1968-07-15
Court Decision / Holding
Appeal dismissed with costs.
Final Disposition
Appeal dismissed with costs.

Parties to the Case

Appellants / Petitioners

  • Abdul Rahiman Khan

Respondents

  • Sadasiva Tripathi

Legal Representation & Advocates

Counsels for Petitioners

  • • D. Goburdhun

Counsels for Respondents

  • • C. B. Agarwala
  • • Uma Mehta
  • • S. K. Bagga
  • • S. Bagga

Provisions of Law Cited

Representation of the People Act, 1951, s.9ARepresentation of the People Act, 1951, s.116-AConstitution of India, Art. 299(1)Constitution of India, Art. 299(1) (Explanation to s.9A)

Legal Doctrines & Maxims

  • Government ratification of a contract can render it binding for purposes of disqualification under s.9A, even if not enforceable in civil courts under Art. 299(1).
  • An agreement for execution of work not executed in the manner prescribed by Art. 299(1) may still disqualify if the Government treats the relation as binding.
  • Explanation to s.9A clarifies that full performance by the contractor does not automatically negate subsistence of a contract for disqualification purposes.
  • Where the Government's ratification or conduct treats a private agreement as binding, s.9A disqualifies a candidate.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant argued that there was no subsisting contract at the date of the nomination because the contract was cancelled at his request; he contended that Art. 299 of the Constitution did not render the contract a basis for disqualification since it was not executed in the Governor's name and the contract had not been determinated mutually; he urged that the contract, being not enforceable against the State, could not disqualify him under s.9A.

Contentions of Respondents

The respondents contended that the contract, though not enforceable, still stood as a binding arrangement treated as subsisting by the State and that its execution or non-execution did not erase the disqualification under s.9A; they relied on the State's implicit liability and the conduct of the parties indicating subsistence of the contract, as well as Article 299 and the related legal doctrines.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Chatturbhuj Vithaldas Jasani v. Moreshwar Parashram and Others[1954] S.C.R. 817PositiveThe Court cited this case and followed its principle that contracts with the State not executed in the form required by Art. 299 may still be binding; it held that such contracts are not void merely for non-compliance with Art. 299(1).
Laliteshwar Prasad Sahi v. Bateshwar Prasad & Ors.[1966] 2 S.C.R. 63PositiveThe Court followed this decision, which held that where an agreement for execution of work has been ratified by the State Government and treated as binding, it can result in disqualification under s.9A.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,337 words•~16 min read

In The Court Record

Abdul Rahiman Khan v. Sadasiva Tripathi

**ABDUL** **RAHIMAN** **KHAN** _v._ **SADASIVA** **TRIPATHI** _July_ 15, 1968 (J. C. SHAH AND V. BHARGAVA, **JJ.)** _Representation_ _of_ _the People Act_ (43 _of_ 1951), _s._ _9A-Contract_ _with_ _Government-Not_ _entered with_ _Governor-If_ _disqualifies._ _**Constitution of India, Art,**_ _**229-Contract**_ _**not entered with**_ _**Governor-**_ _Whether disqualifies under_ _s._ _9A Representation_ _of_ _the People Act._ The appellant's tenders to carry out certain contracts with the State of Orissa were accepted but final contracts were not executed on behalf of the Governor. The appellant carried on a part of the work and thereafter requested the authorities to cancel the contract without any penalty. **No** **acceptance of** **this** **offer** **waSa** **communicated to the appellant.** **The** appellant wrote letters to the Superintending Engineer for extension of time and for permission to resume the work and finish it. Shortly thereafter the appellant filed his nomination paper for a seat to the State Legislative Assembly, which was rejected. The appellant filed an election petition for setting, aside the election of the respondent on the ground **ihat** **the appellants nomination** **paper** **was improperly** **rejected.** **fhe** **High Court rejected the petition.** **HELD** : The appellant was rightly disqualified. (i) The contract was not wholly performed by' the appellant. Unless he proved that he had completed the contract or showed that there was **determination** **by** **mutual assent** **of** **the:** **contract, the appellant could not** claim .that there was no subsisting contract at the date of the filing of the **nomination paper.** **The** **conduct** **of** **the** **appellant in writing the two** letters suggested that he did not treat the contract as cancelled, nor there **was any clear evidence to show that the authorities** **had** **treated the con-** tract as cancelled, [356 C-E] (ii) The contract resulting from the acceptance of his tender though not enforceable by suit against tho State Government, because it did not comply with Art. 299 of the Constitution must still be regarded as disqualifying the appellant under the Representation of People Act from standing as a candidate for election to the State Legislature. [357 HJ _Chatturbhuj Vithaldas_ _Jasani_ v. _Moreshwar_ _Parashram_ & _Ors.,_ [1954] S.C.R. 817 and _Laliteshwar_ _Prasad_ _Sahi_ v. _Bateshwar_ _Prasad_ & _Ors.,_ [1966] 2 S.C.R. 63, fOllowed. CIVIL APPELLATE JURISDICTION : Civil Appeal No, 1723 of 1967. **A** **B** #### c **D** **E** **F** **G** Appeal under section 116-A of the Representation of the People Act, 1951 of the judgment and order dated October **14,** **H** 1967 of the Orissa High Court in Election Petition No. 1 of 1967. _**D.**_ _Goburdhun,_ for the appellant. 352 SCPREME COURT REPORTS [ 1969] l S.C.R. C. _B. Agarwala,_ _Uma_ _Mehta, S._ _K._ _Bagga_ and _S. Bagga,_ for **A** the respondent, The Judgment of the Court was delivered by **Shalt,** **J.** At the last general elections, the respondent was declared elected to the Legislative Assembly of Orissa from the Nowrangpur General Constituency. The appellant filed an election petition before the High Court of Orissa for an order setting aside the election of the respondent, on the ground that the appellant's nomination paper was improperly rejected and he was illegally deprived of his right to contest the election. The High Court rejected the petition. The appellant has appealed to this Court under s. 116-A of the Representation of the People Act, 1951. It is common ground that the appellant was carrying on the business of a building contractor and that in pursuance of a notification issued by the Government of Orissa he had submitted tenders for construction of buildings of the Rental Housing Scheme at the rates specified therein. Those tenders were accepted and the appellant had carried out a part of the construction work, but had thereafter stopped the work becau~e he suffered serious injuries which necessitated his detention in a public hospital. The appellant claimed that at his request the contract was cancelled, and on that account at the date of the filing of his nomination there was, between him and the State of Orissa no subsisting contract for execution of works undertaken by him, and that in any event there was in law no contract between him and the State relating to the execution of works which disqualified him from standing at the election as a candidate for a scat in the State Legislative Assembly. **B** #### c **D** .E In January 1965 tenders were invited by the Government of Orissa for construction of buildings under the Rental Housing **F** Scheme. The tenders submitted by the appellant were accepted and on "'1arch 30, 1965, the appellant and the Executive Engineer signed an agreement in Form K-2. The principal recitals in the agreements were : "I do hereby tender to execute the undermentioned description of work by piece work, and in accordance G wit11 the conditions noted before in consideration of payment being made for the quantity of work executed at rate specified in the following schedule." A schedule of items was appended thereto which was followed hy the recital : **H** "Conditions as per F-2 contract which will be finalised." A B #### c D E' F ABDUL RAHIMAN _v._ SADASIVA _(Shah,_ _J.)_ 3 5 3 The Executive Engineer then made an endorsement on the tenders. "Accepted by me for item 5 only," and submitted them to the Superintending Engineer for approval of "excess items". Apparently sanction was given by the Superintending Engineer but no formal contracts in Form F-2 were executed. Advance payments were however made to the appellant after execution .of the agreements in Form K-2 and the appellant proceeded with the work of construction. On October 13, 1965 the appellant suffered serious · injuries which necessitated his admission to a public Hospital and the construction work wa~ stopped. On January 6, 1966. the Sub-Divisional Officer, P.W.D. Nowrangpur, addressed a letter to the appellant calling upon him to resume work on or about the January 12, 1960, failing which, he was informed, his contract will be terminated and "measurements will be recorded". On February 10, 1966. the appellant addressed a letter to the Executive Engineer, P.W.D. stating that it was not possible for him to resume the work and to complete it. and he requested that the contract be cancelled without imposition of penalty. On the letter of the appellant there are two endorsements at the foot of the letter which have been marked Ext. 2(a) and Ext. 2(b) : Exhibit 2(a) reads: "Submitted to the Executive Engineer, Koraput Division. The reason for terminating the contract, as mentioned by Shri A. R. Khan, contractor, is correct. His contract may be terminated without imposing penalty and permission given to take up work through job work soon." Exhibit 2(b) dated March 18, 1966 bears the initials of the Executive Engineer, and states : ' "I know of the unfortunate accident. As the applicant is still in the Vizag Hospital his work may be finally measured and closed without penalty. The balance of the work may. be completed through job **work."** The Sub-Divisional Officer, Nowrangpur. wrote a letter on March 16, 1955, requesting one Harihar Bisoi nursuant to his G annFcation dated March 5, 1966, to fake up the Rental Housing Schedule building work at Nowrangpur "immediatelv at current schedule of rates after taking detailed instructions from the Sectional Officer, Nowrangpur." It appears that Harihar Bisoi did some construction work, but no payment was made to him and he also stopped the work. H The appellant strongly relies upon the endorsements made on the letter dated February 10. 1966. the letter Ext. 3, and the evidence of Ram Mohan Patnaik-the Executive Engineer. Ram Mohan Patnaik stated that .he by his endorsement Ext. 2(b) on 354 SUPREME COL'RT REPORTS [1969] l S.C.R. lhe application dated February I 0, 1966, had clearly directed that the work of the contractor (appellant) would be finally measured and his contract would be treated as closed and no penalty would be charged from him; that the question of accounting had nothing to do with the closing of the contract; and that on March 18, 1966, he had passed an order Ext. 2(b) that the contract was closed. According to the witness closure of the contract was no1 conlingent upon the mcasuremrnt of the work done by the appellant, and that by his order dated March 18, 1966 Ext. 2(b) the appellant was excused from liability to complete the work, as tbc contract was rescinded and by implication Ext. 2(b) meant that the Sub-Divisional Officer would give intimation to the contractor about the cancellation of his contract. The witness could not say whether lhe Sub-Divisional Officer did ###### give intima1ion to the contraclor. He asserled that it was not his intention that job work should be entrusted to job workers only afcr the final bill of the appellant was submitted : his clear intention was that after measurement was taken, the work may be entrusted to job workers. According to the witness by Ext. 2(b) he accepted the incomplete work of the appellant "as a complete satisfaction of his contract." This evidence _prima facie_ supports the case of the appellant that it was the intention of the Executive Engineer to terminate the contract. But there is a mass of evidence on the record which shows that no steps were taken to intimate to the appellant about the detennination of the contracls and both the parties treated the contract as subsisting. To that evidence we may advert. On April 15, 1966, the appellant wrote a Jetter in reply to a letter dated April 13, 1966 from the Sub-Di\isional Officer that he "had completed upto slab level the construction of Rental Housing Scheme" and that thereafter he was lying injured in a hospital and that as he had no au1horised agents to look afler further work, early action may be taken to make final measurement upto slab level and for payment of the amount due to him. On December 20, 1966, the appelJant wrote a Jetter to the Superintending Engineer stating that he had recovered and was in a position to leave the Hospital and to attend to his normal avocation and that he bad learnt that the Department wanted to cancel his contract and call for new tenders and had taken some action towards that end. He requested the Superintending E112ineer to desist from such a course and to favourably consider his request for extension of time to complete the work. He stated that he had advanced large sums of money to the labourers and for the supply of materials, and there were large quantities of building materials belonging to him which had been lying at the site of the work and if his contracts "were 10 be cancelled he would sustain irreparable loss"; that he had always been a very efficient A B #### c D E F G II ' ABDUL RAHIMAN _v._ SADASIVA _(Shah,_ _J.)_ 355 and good contractor and was executing the works in time and diligently and well; and that he could not complete the work due to the unfortunate accident. He then stated : "I, therefore, request you to kindly grant me time upto end of March 1967 and I shall resume the work by about 15th January 1967 and will finish it by 31st March, 1967. The cancellation of my contract at this stage when nearly 75% of the work was already done by me and the roofing alone remains to be completed and the stoppage of the work was due to circumstances over which I had no control due to more or less vismajor will be most inequitable if not unjust. I, therefore, earnestly appeal to you to sympathetically consider this representation of mine and grant me time till end of March 1967 and order withdrawal or cancellation of the fresh tenders that might have been called for by the Executive Engineer Koraput." At the foot of the letter there is a notation that tenders had been called for the balance of the work "as per instructions of the Executive Engineer, Koraput, and that the contract may be res· cinded as instructed by the Executive Engineer, Koraput." There is another notation : "It is an old case wherein Executive Engineer has already ordered to close the contract and do by job (illegible) order its without penalty (illegible)". There is one more notation dated January 4, 1967-"Submitted for favour of orders. What penalty is to be imposed in rescinding the contract." Exhibit 13 is a letter dated January 22, 1967, from the Assistant Engineer, P.W.D. Nowrangpur to the Returning Officer which sets out the circumstances in which the work entrusted to the appellant was stopped. The letter states that "the balance work which was suggested to take up on job-work basis would not affect the accounts of Sri A. R. Khan for his work portion. The final bills for hls above two works of the aforesaid contractor have been submitted _to_ Division Office vide this office letter Nos. 120 and 121 dated 18-1-67 and I have been mtimated vide Divisional letter No .. 902 dated 20-1-67 that the said contractor has to return 435 bags of cement and 7.954 quintals of rods to the undersigned to finalise his accounts. But no material has been returned by the contractor yet and as such it ensures that his accounts have not yet been finalised." Exhibit 14 is a letter dated January 22, 1967 addressed to the appellant which also indicates that the P.W.D. authorities had not treated the contract as cancelled and had not intimated to him the order made by the Executive Engineer, _l_ . A B ### c D E F G H 356 SUPRH!E COURT REPORTS [ 1969] 1 s.c.R. In February 1966 the appellant requested cancella0tion of the contract. The Executive Engineer was willing to accept the offer. of cancellation and made an endorsement !n that behalf, but nothing was done thereafter. Harihar Bisoi was apparently asked to take up the work "at the current schedule of rates", but even thereafter the contract with the appellant was not treated as In February 1966 the appellant requested cancella cancelled. It is true that by virtue of the Explanation to s. 9A of the Representation of the People Act, where a contract has been ###### fully performed by the person by whom it has been entered into with the appropriate Government, the contract >hall be deemed not to subsist by reason only of the fact, that the Govcrrunent has not performed its part of the contract either wholly or in part. In the present case the contract was not wholly performed by the appellant, and unless he had completed the contract or showed that there was determination by mutual a~sent of the contract, the appellant cannot claim that there was no subsisting contract at the date of the filing of the nomination paper. By letter written by the appellant on July 22, 1966, Ext. C, the appellant made a request for extension of time by six months to enable him to complete tile work and by his letter Ext. D dated December 20, 1966 he requested tile Superintending Engineer not to cancel the contract or call for new tenders. This conduct of tile appellant clearly suggests that he did not treat the contract as cancelled, nor is there any clear evidence to show "that the authori!ies had treated the contract as cancelled. The High Court was, therefore, right in holding that the case did not fall within the explanation to s. 9A of the Representation of the People Act and there was no evidence of determination of the contract by mutual agreement. Counsel for the appellant contended that the contract for execution of works was between the State and the appellant and Art. 299 of the Constitution applied thereto, and since the contract was not shown to be executed in the name of the Governor, and by an. authority competent to execute the contract on behalf of the Governor, the disqualification under s. 9A did not apply. By cl. (I) of Art. 299 all contracts made in the exercise of the execute power of the State must be expressed to be made by the Governor of the State, and all such contracts made in the exercise of that power must be executed on behalf of the Governor bv such persons and in such manner as he mav direct or authorise. It is true tllat agreements were executed ·by the Executive Engineer in Form K-2 but no final contracts were executed in Forni F-2. The appellant proceeded on the footing that there was a binding contract under which he had undertaken the work of construction for the State, and tile State had allowed him to work and had offered to pay him for the work done at tile A B #### c D E F ## ... G ### '" H A B #### c D E F # G H ABDUL RAHIMAN _V._ SADAS!VA _(Shah, J.)_ 357 rates set out in Form K-2. The appellant could not by virtue of Art. 299 sue in a civil court on the agreement in Form K-2 for compensation for breach of contract. But we are unable to hold that the appellant was not disqualified under s. 9A of the Representation of the People Act merely because the contracts were not enforceable against the State because of Art. 299 ( 1) of the Constitution. In _Chatturbhuj Vithaldas Jasani_ v. _Moreshwar Parashram and others('),_ Bose J., in dealing with a case of disqualification under the Representation of the People Act 1951, resulting from a contract with the State which is not executed in the form and manner prescribed by Art. 299, 0 #### observed : ; ', !' q "It may be that Government will not be bound by the contract in that case, but that is a very different thing from saying that the contracts as such are void and of no effect. It only means that the principal cannot be sued; but we take it there would be nothing to prevent ratification, especially if that was for the benefit of Government, . . . We accordingly hold that the contracts in question here are not void simply because the Union Government could not have been sued on them by reason of Article 299 (1) ." Undoubtedly f9r breach of the terms of a contract not executed in the manner- prescribed by Art. 299 ( 1) a suit for relief in a civil court will not lie, but on that account it cannot be said that a contract for execution of works undertaken by a person though not executed in manner prescribed by Art. 299, but which is treated by both the parties thereto as binding will not operate as a disqualification. In a recent judgment of this Court in _Lalitesh-_ _war Prasad Sahi_ v. _Bateshwar Prasad and others(_ _[2]_ _),_ this Court ##### held that where an agreement for execution of work h¢ been entered into between the State Government and a private person by correspondence and the State Government has ratified the agreement and has treated the relation between the parties as contractual and has accepted liability arising under the terms of the agreement as if it were a pendin!! contract, a disqualification under the relevant provisions of the Representation of the People Act results. As already pointed out, the appellant had commenced execution of the work but had not completed it. Payment for the work done was not made to the appellant. The contract was not determined by mutual agreement nor was it abandoned. The contract resulting from the acceptance of his tender though not enforceable by suit against the State Government, be {!) [1954) S,C.R. 817. (2) [1966] 2 S,C.R.63 358 SUPREME COURT REPORTS (1969] i S.C.R. cause it did not comply with Art. 299, must still be regarded as A disqualifying the appellant under the Representation of the People Act from standing as a candidate for election to the State Legislature. The appeal therefore fails and is dismissed with costs. B Y.P. _Appeal dismissed._ ### ..
End of Judgment Record
Browse All Supreme Court of India (1969) Decisions
1969-04-15

Volleti Venkatarama Rao v. Kesapraga da Bras.Kara Rao & ors.

This is a Hindu law adoption case concerning the validity of an adoption performed in 1904 by Seshamma, the widow of Bhaskara Rao, under authority in a will dated 1903. The appellant, claiming to be the nearest heir of Bhaskara Rao, challenged the adoption of Rajeswararao on the ground that Seshamma had not attained the age of discretion at the time of adoption, rendering the act invalid. The suit for possession of Bhaskara Rao’s immovable property was filed in 1953; the trial court and the Andhra Pradesh High Court upheld the validity of the adoption, relying on a long lapse since adoption and the long-standing family recognition of Rajeswararao as Bhaskara Rao’s adopted son. The court noted little live evidence to rebut the presumption of validity after decades of conduct and records, and emphasized that those who could have testified had long since passed away. Cited authorities include Venkataseetaramil Chandra Row v. Kanchu Marthi Raju (A.L.R. 1925 P.C. 201), applied to support a strong presumption in favor of validity when many years have elapsed. Mulla’s Hindu Law and the age of discretion for a minor widow were discussed, but the absence of concrete age evidence did not overcome the presumption. The appeal was dismissed with costs, affirming the adoption’s validity and the consequent title to property in the adopted line.

1969-09-16

RAM NARAIN MAHTO v. STATE OF MADHYA PRADESH

Ram Narain Mahto v. State of Madhya Pradesh concerns a timber contract between a Jagirdar of Sonpur Jagir and Ram Narain Mahto, a timber contractor. In 1949 the Jagirdar executed a deed in favor of Mahto for sale of logs from forests with girth of two feet or more, to be cut and supplied in four periods, at a total price of Rs. 51,501. In 1951 the State prevented cutting and, on March 31, 1951, the Madhya Pradesh Abolition of Proprietary Rights Act, 1950 came into force, vesting the Jagirdar’s estate in the State. Mahto sued in 1954 for Rs. 1,50,000 for breach of contract, seeking compensation for (i) logs cut but not removable, (ii) logs cut but lost due to negligence, (iii) standing timber in four villages not yet cut, and (iv) logs in villages from which the plaintiff could not cut. The Trial Court granted compensation; the High Court disallowed items (ii), (iii) and (iv) and reduced item (i) to Rs. 3,712. The Supreme Court, dismissing the appeal, held the estate had vested in the State before severance and delivery; thus the property in the logs did not pass to Mahto, and the contract was for future goods not yet in deliverable state. The decision relied on the Sale of Goods Act provisions (ss. 18, 21), and on earlier case law distinguishing rights in pre-vesting contracts. The appeal was dismissed with costs.

1968-07-30

Standard Motor Union Pvt. Ltd. v. State of Kerala & Ors.

Standard Motor Union Pvt. Ltd. v. State of Kerala & Ors. concerns a nationalisation scheme under Chapter IV A of the Motor Vehicles Act, 1939, for nine routes in Ernakulam and Kottayam. The Kerala State Transport Undertaking prepared draft Form II scheme for partial exclusion of existing private operators. After hearings, the State Government approved the scheme on October 17, 1966 and published it on October 24, 1966. The appellant contends that the impugned scheme is a complete exclusion that should have been in Form I and that, since earlier schemes existed, the new scheme modified them without compliance with Section 68E. The Kerala High Court dismissed the writ petition; on appeal the Supreme Court evaluated whether the scheme constitutes a complete exclusion, whether Form II is permissible, and whether the earlier schemes were validly modified. The Court rejected the appellant’s claim of complete exclusion, noting that there are 33 overlapping routes and common road sectors; the scheme does not extinguish private services on the shared road segments. It held that Form II was appropriate as a partial exclusion, and that modification of earlier schemes occurred pro tanto under Section 68E, which does not require explicit cancellation. The decision clarifies the framework for nationalisation under Sections 68C-68F and the 1960 Rules, and disposes of the appeal with costs.

1969-02-14

C.I.T. v. Allahabad Bank

The case concerns the computation of rebates in super‑tax under the Finance Acts, 1956 and 1957, for Allahabad Bank Ltd. The central issue is whether the amount represented by share premium, which is part of the company’s reserves, should be included in the paid‑up capital for the purpose of reducing the rebate when dividends exceed the prescribed limit (6% of paid‑up capital). The Income Tax Officer had reduced the rebate in super‑tax by excluding the share premium, treating it as not to be counted in paid‑up capital. The Appellate Assistant Commissioner and the Tribunal took the position that the share premium could be included in the paid‑up capital, and the Calcutta High Court agreed. The Finance Act provisions define paid‑up capital and provide for an explanation linking the paid‑up capital to share premium accounts. The key legal question was whether the share premium maintained within reserves could be treated as a genuine share premium account for purposes of the statutory calculation, or whether it had to be in a separate account outside reserves. The Supreme Court held that the share premium, even when maintained within reserves as an identifiable component of the reserves, qualifies for inclusion in the paid‑up capital for computing the rebate in super‑tax. Accordingly, for the 1957‑58 assessment year the share premium within reserves can be included; the appeals were dismissed with costs.