Supreme Court of IndiaSupreme Court · 2011Division BenchAppeals allowed; directions to pay interest at ...

A KERALA STATE HOUSING BOARD & ORS. v. KERALA STATE HOUSING BOARD, NELLIKODE HOUSING COLONY ALLOTIEES ASSN. & ORS.

Case / Petition Number:
Civil Appeal No. 7835 of 2011; C.A. Nos. 7836 & 7837 of 2011
Neutral Citation:[2011] 11 S.C.R. 390

Case Synopsis & Summary

This case concerns the entitlement to interest on the differential amount between the tentative price fixed by the Kerala State Housing Board (the Board) and the final price fixed after enhanced compensation was ordered in land acquisition proceedings under the Land Acquisition Act, 1894. In 1984–85, land was acquired for two housing schemes; the landowners sought reference under Section 18, while the Board entered into sale agreements (1988–1990) with allottees, stipulating that after final price fixation, the difference with the tentative price plus interest at 15% per annum must be paid within 30 days or in installments over two years. After compensation references were resolved in 1997, the Board deposited the enhanced compensation (with interest) but served demand notices only in 1999. The allottees challenged the Board’s claim to interest on the differential amount from 1997 onward. The Kerala High Court rejected the claim, and the Division Bench dismissed the appeals. The Supreme Court, however, allowed the appeals in part: it held that the Board is entitled to interest on the differential amount at 8% per annum from the date of deposit of enhanced compensation (1997) until payment of the differential amounts by the allottees. The Court invoked Chandigarh Housing Board v. K.K. Kalsi to justify awarding a reasonable (not punitive) rate of interest when the money is in the possession or control of the recipient; the final orders set down this rate, overruling the Kerala High Court decisions and directing payment with costs to none.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • R. V. Raveendran
  • A. K. Patnaik
Judgment Date
2011-09-14
Court Decision / Holding
Appeals allowed. The Court held that the Board is entitled to interest on the differential amount at 8% per annum from the date of deposit or payment of the enhanced compensation (1997) until payment of the differential amount by the allottees, overruling the Kerala High Court’s view that no interest was payable from 1997 onward. The decision aligns with the equitable principle that the party withholding funds should compensate the other side for the use of those funds, applying Chandigarh Housing Board v. K.K. Kalsi to justify a reasonable rate of interest.
Final Disposition
Appeals allowed; directions to pay interest at 8% per annum on the differential amount from 1997 onwards until payment by the allottees.

Parties to the Case

Appellants / Petitioners

  • KERALA STATE HOUSING BOARD & ORS.

Respondents

  • KERALA STATE HOUSING BOARD, NELLlKODE HOUSING COLONY ALLOTIEES ASSN. & ORS.

Legal Representation & Advocates

Counsels for Petitioners

  • • M.T. George

Counsels for Respondents

  • • P. Vishwanatha Shetty
  • • A. Raghunath
  • • K. Rajeev

Provisions of Law Cited

Section 18 of the Land Acquisition Act, 1894Proviso to Section 34 of the Land Acquisition Act, 1894

Legal Doctrines & Maxims

  • Equity and good conscience: where money is retained or utilized by a party, it is equitable to pay a reasonable rate of interest (as applied in Chandigarh Housing Board v. K.K. Kalsi)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant-Board submitted that the sale agreements with allottees contained a clause obligating payment of the difference between tentative and final prices with interest at 15% per annum within 30 days of a demand notice, or in installments over two years, as determined by the Board. After enhanced compensation was determined in 1997, the Board deposited it with interest. Though demand notices were issued only in 1999, the clause was intended to secure payment of the enhanced amount and interest under the proviso to Section 34 of the Land Acquisition Act. The Board contended that it is entitled to recover interest on the differential amount to compensate for the Board’s loss of use of funds and to reflect the original intent of the agreements in light of the LA Act’s provisions.

Contentions of Respondents

The respondents contended that the Board cannot claim interest on the differential amount from 1997 until service of individual account statements, asserting lethargy on the part of the Board and the absence of timely notices. They argued that the High Court properly disallowed such interest, and that the Board’s attempts to impose 15% interest are unjustified beyond the statutory prohibition of default interest under Section 34.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Chandigarh Housing Board, Chandigarh v. K.K. Kalsi & Ors.(2003) 12 SCC 734PositiveThe Court relied on the proposition that it is equitable to pay a reasonable interest when funds are retained and used by the other party; this supported awarding 8% interest on the differential amount.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,371 words•~11 min read

In The Court Record

A KERALA STATE HOUSING BOARD & ORS. v. KERALA STATE HOUSING BOARD, NELLIKODE HOUSING COLONY ALLOTIEES ASSN. & ORS.

## [2011] 11 S.C.R. 390 A KERALA STATE HOUSING BOARD & ORS. v. KERALA STATE HOUSING BOARD, NELLIKODE HOUSING COLONY ALLOTIEES ASSN. & ORS. (Civil Appeal No.7835 of 2011) B SEPTEMBER 14, 2011 [R.V. RAVEENDRAN AND A.K. PATNAIK, JJ.] _Land Acquisition:_ c _Interest on differential amount betweef/ tentative price and final price_ - _Land acquired_ - _Reference for enhancement of compensation pending_ - Sale _deed in favour of allottees with stipulation to pay differential between tentative price and final_ D _price and to pay interest_ @ _15% on differential amount within 30 days of demand notice_ - _Enhanced compensation deposited in 1997_ - _Demand notice served in 1999_ - _Claim for 15% interest_ - _HELD: Interest till the date of deposit in 1997 would be payable@ 15%, and thereafter 8%_ - _It is not disputed that notices of demand were served on the allottees_ E _not immediately after finalization of the compensation by the court and payment or deposit of the enhanced amount by the Board in the year 1997, but after a period of more than a year some time in 1999_ - _The respondents will be liable to pay interest to the appellant-Board on the differential amount_ F _between the tentative price and the final price at the rate of 8% per annum from the date of deposit or payment of the enhanced compensation by the Board in 1997 till payment of the differential amounts by the allottees._ G _Chandigarh Housing Board, Chandigarh_ v. _K.K. Kalsi_ & _Ors._ (2003) 12 SCC 734 - relied on ## Case Law Reference: H (2003) 12 sec 734 relied on para 6 390 # KERALA STATE HOUSING BOARD _v._ KERALA STATE 391 HOUSING BOARD, NHCAASSN. CIVIL APPELLATE JURISDICTION : Civil Appeal No. 7835 of 2011. · A From the Judgment & Order dated 28.02.2006 of High Court of Kerala at Ernakulam in W.A. No. 1760 of 2004. ## WITH B C.A. Nos. 7836 & 7837 of 2011. M.T. Greorge for the Appellants. P. Vishwanatha Shetty, A. Raghunath, K. Rajeev for the C Respondents. The Judgment of the Court was delivered by **A. K. PATNAIK, J.** 1. Leave granted. 2. Civil Appeal arising out _of_ S.L.P.(C) No.10580 of 2006 is against the judgment dated 28.02.2006 in Writ Appeal No.1760 of 2004 of the Div_ision Bench of the Kerala High Court. Civil Appeal arising out of S.L.P.(C) No.21478 of 2008 is against the order dated 13.06.2008 in Writ Appeal No.1968 of 2007 disposing of the Writ Appeal in terms of the judgment dated 28.02.2006 in Writ Appeal No.1760 of 2004. Civil Appeal arising out of S.L.P.(C) No.21817 of 2008 is against the order 13.06.2008 in Writ Appeal No.1940 of 2008 disposing of the Writ Appeal in terms of the judgment dated 28.02.2006 in Writ Appeal No.1760 of 2004. These three appeals are being disposed of by this common order as common questions of fact and law arise in the appeals. D E F 3. The facts very briefly are that in the years 1984 and 1985 land was acquired for allotment of plots under the G Chevayur Housing Scheme and the Nellikode Housing Scheme respectively undertaken by the Kerala State Housing Board (for short 'the Board'). The landowners did not accept the compensation offered for the acquired land and sought a reference to the Civil Court under Section 18 of the Land H 392 SUPREME COURT REPORTS [2011] 11 S.C.R. A Acquisition Act, 1894. While the dispute in regard to quantum of compensation was pending, the Board entered into agreements of sale with various allottees of the plots of land during the years 1988-1990 and made a provision therein that the Board shall be entitled to re-fix the final price of the property B agreed to be sold to the allottees taking into account inter alia the enhanced compensation awarded by the Courts and Tribunals and that the decision of the Board in fixing the revised price of the property shall be conclusive and final. It was also expressly agreed in the agreements of sale that after finalization c of the price of the property agreed to be sold by the Board, the allottee shall pay to the Board together with interest at the rate of 15% per annum, the difference between the tentative price fixed and the price finally fixed for the property by the Board within thirty days of the date of a registered notice demanding the payment thereof or in such quarterly installments over a 0 period not exceeding two years to be determined by the Board. After the reference cases were finalized and disposed of in the year 1997, the Board deposited the enhanced compensation with interest, but did not promptly serve the demand notices on the allottees for payment of the difference between the tentative E price and the final price with interest and it was only in the year 1999 that the Board served the notices on the allottees to pay the said difference with interest at the rate of 15% per annum. 4. The allottees then filed Writ Petitions before the Kerala F High Court and the learned Single Judge passed orders refusing to interfere with the claim of interest on the enhanced amounts of compensation on the differential amount till 1997 when the references were finally disposed of by the Court and the Board deposited the enhanced compensation with interest. G The learned Single Judge, however, found that individual account statements giving the relevant details and calculations of the amounts demanded had not been served on the allottees and held that this was on account of the lethargy of the officials of the Board and, therefore, the Board was not entitled to any H interest on the differential amount from the allottees for the KERALA STATE HOUSING BOARD _v._ KERALA STATE 393 HOUSING BOARD, NHCAASSN. [A.K. PATNAIK, J.] period from 1997 till the date of service of individual account A statements on the allottees. 5. Aggrieved by the orders of the learned Single Judge, the Board filed Writ Appeals before the Division Bench of the Kerala High Court and by the impugned judgments and orders B the Division Bench dismissed the appeals. In the impugned judgments and orders, the Division Bench of the High Court agreed with the view taken by the learned Single Judge that the Board was not entitled to claim any interest and that too at the rate of 15% per annum for the period from the date of deposit of enhanced compensation in 1997 till the date of C service of the individual account statements saying that the Board cannot punish the allottees for its own lethargies. Aggrieved, the Board is in appeal before us. 6. Learned counsel for the appellant-Board submitted that D. there was a clause in the agreements of sale executed between the Board and the allottees that after finalization of the price of the property agreed to be sold by the Board, the allottee shall pay to the Board together with interest at the rate of 15% per annum, the difference between the tentative price fixed and the E price finally fixed for the property by the Board within thirty days of the date of a registered notice demanding the payment thereof or in such quarterly installments over a period not exceeding two years to be determined by the Board. He submitted that it was only in the year 1998 that the price was F finalized and the demand notices were served in the year 1999 on the allottees to pay the difference between the tentative price and the final price together with interest at the rate of 15% per annum as per the aforesaid clause in the agreements. He further submitted that till the allottees paid the difference between the tentative price and the final price, they retained the differential G amount with them and made use thereof while the appellantBoard was deprived of the use of the money. He relied on the ·decision of this Court in _Chandigarh Housing Board, Chandigarh v. K.K. Kalsi_ & _Ors._ [(2003) 12 SCC 734] wherein H [2011] 11 S.C.R. 394 SUPREME COURT REPORTS - A it has been held that in such cases where the allottees have retained the money with them and made use thereof while the Board has been deprived of the use of the money, it will be equitable for the allottees to pay a reasonable interest to the Board on such money. B 7. Learned counsel appearing for the respondents, on the other hand, supported the orders of the learned Single Judge and the impugned judgment and orders of the Division Bench of the Kerala High Court contending that there was no justification whatsoever for the appellant-Board to claim any C interest on the differential amount between the tentative price and the final price from 1997 till the date of service of individual account statements on the allottees. 8. We have considered the submissions of the learned o counsel for the parties and we find that the reason why a clause in the agreements of sale executed by the Board and the allottees for payment of interest at the rate of 15% per annum on the differential amount between the tentative price and the final price of the land allotted to the allottees was inserted was E that in the proviso to Section 34 of the Land Acquisition Act, 1894 it is provided that if the compensation for the acquired land or any part thereof is not paid or deposited within a period of one year from the date on which possession of the acquired land is taken, interest at the rate of fifteen per centum per F annum shall be payable from the date of expiry of the said period of one year on the amount of compensation or part thereof which has not been paid or deposited before the date of such expiry. Since references under Section 18 of the Land Acquisition Act, 1894 were pending in the Civil Court when the agreements of sale were executed by the Board and the G allottees, a stipulation had to be made in the agreements of sale that as and when the Court finally determines the compensation and the Board becomes liable to pay enhanced compensation, the Board will have to deposit not only the enhanced compensation but also interest at the rate of 15% H KERALA STATE HOUSING BOARD _v._ KERALA STATE 395 HOUSING BOARD, NHCAASSN. [A.K. PATNAIK, J.] per annum on such enhanced compensation. If this was the A purpose of the clause in the agreements of sale between the Board and the allottees, once the compensation was finalized by the Court and the enhanced compensation was paid or deposited in the year 1997, the Board was not liable for any interest under the proviso to Section 34 of the Land Acquisition B Act, 1894 from the date of such payment or deposit. Since the purpose of stipulating the rate of interest of 15% per annum was to take care of the liability on the enhanced compensation provided in the Land Acquisition Act, 1894 and not to enrich the Board by recovery of high rate of interest from the allottees, C we agree with the view taken by the High Court that the Board was not entitled to interest at the rate of 15% per annum on the difference between the tentative price and the final price after the finalization of the compensation and payment· or deposit of the enhanced compensation by the Board in the year D 1997. 9. We, however, do not think that the High Court was right in taking a view that the appellant-Board was not entitled to any interest for the period from the date of payment or deposit of the enhanced compensation in 1997 till the date of service of individual account statements on the allottees. The relevant clause in the agreements of sale requires the Board to serve only a notice of demand on the allottee and such no.tice of demand must obviously indicate the tentative price and the final price as determined by the Board and the differential amount between the tentative price and the final price, which the allottee was required to pay along with interest. The clause did not stipulate that the individual account statements giving the details and calculations as enumerated in the orders of the learned Single Judge were also required to be served on the allottees by the Board. It is not disputed that notices of demand were served on the allottees not immediately after finalization of the compensation by the Court and payment or deposit of the enhanced a·mount by the Board in the year 1997, but after a period of more than an year some time in 1999. During the E F G H [2011] 11 S.C.R. 396 SUPREME COURT REPORTS A period the allottees did not make payment of the differential amount between the tentative price and the final price, they retained the differential amount in their hands and used the same and the Board lost the opportunity to utilize this for its activities, the Board would be entitled to interest on tlie B differential amount at a reasonable rate as has been held by this Court in _Chandigarh Housing Board, Chandigarh v. K.K. Kalsi_ & _Ors._ (supra). In our considered opinion, interest at the rate of 8% per annum on such differential amount between the tentative price and the final price would be reasonable, which c the allottees must pay to the Board. 10. We accordingly set aside the order passed by the learned Single Judge and the impugned judgment and orders of the Division Bench of the High Court and dispose of the Writ Petitions of the respondents with the direction that the D respondents will· be liable to pay interest to the appellant-Board on the differential amount between the tentative price and the final price at the rate of 8% per annum from the date of deposit or payment of the enhanced compensation by the Board in 1997 till payment of the differential amounts by the allottees. E The appeals are allowed to the extent indicated above with no order as to costs. R.P. Appeals allowed
End of Judgment Record
Browse All Supreme Court of India (2011) Decisions
2011-10-13

GRASIM INDUSTRIES LTD. v. UNION OF INDIA

Grasim Industries Ltd. v. Union of India deals with whether metal scrap or waste generated during repair of worn-out machinery used in a cement manufacturing plant constitutes manufacture and thus obligations to pay Central excise duty. The core dispute arose after Grasim repaired plant components and generated scrap, which was cleared without duty; the Tribunal later held that such scrap did not arise from any manufacturing activity and was not excisable. The Rajasthan High Court initially upheld the duty demand and penalties, while the Tribunal had dropped them. The Supreme Court reversed the High Court, restoring the Tribunal’s order and allowing the appeal. The Court held that although repair work produces metal scrap, this scrap does not participate in the manufacture of cement and cannot be treated as a by-product of the final product. It emphasized that excise duty is on manufacture of goods, requiring that the goods be produced or manufactured in India, and the charging Section 3 applies only when the goods are excisable under Section 2(d) and are manufactured under Section 2(f). Section 2(f) defines manufacture as including any process incidental or ancillary to the completion of the manufactured product, involving transformation of raw material into a new or distinct excisable product. The process of repair, using non-raw materials, does not satisfy this test. The Court also cautioned against deeming provisions in tariff notes as creating manufacture unless expressly stated, relying on various precedents such as Shyam Oil Cake, Ujagar Prints, Hindustan Polymers, and Union of India v. Delhi Cloth and General Mills, among others, to delineate the law of manufacture.

2011-03-02

Bharat Petroleum Corporation Ltd. v. Chembur Service Station

This Supreme Court appeal concerns BPCL’s licence-based relationship with a dealer at a Retail Petroleum Outlet (RPO) in Chembur, Mumbai. BPCL (then Burmah Shell) leased the land and services premises to operate the RPO; in 1972 a DPSL (Dispensing Pump and Selling Licence) granted the respondent the right to sell BPCL’s petroleum products from the outlet. A 1995 renewal extended the arrangement. In 2007, a show-cause notice alleged tampering with dispensing equipment, prompting BPCL to terminate the dealership. The respondent filed suits in the Court of Small Causes claiming tenancy or deemed tenancy under rent-control laws and sought an injunction to continue supply, while BPCL argued the arrangement was a revocable licence, not a tenancy, and the remedy lay in due process and contract law, not eviction under rent-control statutes. The lower courts issued status-quo orders preserving possession and continuing supplies, with various challenges under Public Premises Act and rent-control regimes. The Supreme Court clarified that the DPSL licence creates a limited, revocable right to enter and use the premises to sell BPCL’s products, not a tenancy; the licence terminates with revocation and the licensee has no independent right to possession. The Court ultimately referred the matter to a larger Bench due to divergent views and, in the order, dismissed the appeal with directions to proceed under due process of law.

2011-07-04

Sudam @ Rahul Kaniram Jadhav v. State of Maharashtra

Sudam alias Rahul Kaniram Jadhav challenged a conviction for the murder of a woman with whom he lived as husband and wife and her four children. The victims were found in a village pond in August 2007. The trial court convicted the appellant under IPC Sections 302 and 201 and sentenced him to death; the Bombay High Court affirmed. The State relied on circumstantial evidence: the victims were last seen alive with the appellant; he had posed as single, later marrying another woman (PW-6); the deceased had agreed to pay Rs. 15,000 to PW-6 to settle the dispute; extra-judicial confessions were made by the appellant to PW-6 and PW-9; he absconded and could not explain the deaths. The defense argued that the circumstantial chain was not complete and could admit alternate explanations; there were no direct eyewitnesses. The Supreme Court reiterated the standard for circumstantial evidence: the evidence must be cogently and firmly established, form a complete chain, point to guilt beyond reasonable probability, and be inconsistent with innocence. It concluded all five deaths were homicidal and, applying the rarest-of-the-rare doctrine, upheld the conviction and the death sentence, while dismissing the appeals.

2011-04-18

J.S. Yadav v. State of U.P. & ANR.

This case concerns a challenge to a May 28, 2008 notification declaring the appellant, a member of the Uttar Pradesh State Human Rights Commission, ceased to hold office after amendments to the Protection of Human Rights Act, 1993 were introduced by the Protection of Human Rights (Amendment) Act, 2006. The appellant joined the Commission on 29 June 2006 for a five-year tenure and argued that the amendment, which requires seven years of experience as a District Judge for eligibility, could not curtail an incumbent’s tenure and could not be applied retrospectively. He also contended that Section 26 of the Act guarantees that terms and conditions of service shall not be varied to his disadvantage after appointment, and that the proposed reconstitution would deprive accrued rights. The State argued that fresh appointments to the Commission had to be made, that the amendment could alter service conditions, and that public funds cannot pay two persons for one post; non-joinder of relatives and the lack of a suitable remedy rendered the petition academic. The Supreme Court held that tenure posts must be allowed to endure to the end of the fixed term and that accrued rights cannot be taken away by a repealing or amended statute without express or necessary implication. It held the 2006 Amendment prospective and the impugned notification illegal, allowed the appeal to the extent discussed, and awarded Rs. 1 lakh as costs to the appellant.